HomeMy WebLinkAboutSDP202000080 Review Comments Final Site Plan and Comps. 2021-01-26County of Albemarle Department of Community Development Memorandum To: Ryan Perkins Ryan. Perkinsnae kimley-hom.com and Craig Van Bremen craig@gcawearess.com From: Kevin McCollum - Planner Division: Planning Services Date: January 26, 2021 Subject: SDP202000080 Green Clean at 3290 Worth Xing - Site Plan Final The Planner for the Planning Services Division of the Albemarle County Department Community Development will recommend approval of the plan referred to above when the following items have been satisfactorily addressed. (The following comments are those that have been identified at this time. Additional comments or conditions may be added or eliminated based on further review.) [Each comment is preceded by the applicable reference to the Albemarle County Code.] Applicable Comments from Initial Site Plan Action Letter (December 22, 2020) If the comment has been addressed, it has been blurred out. Additional comments are added in bold font, like this. 1. 132.5.2 (a)] Update the cover sheet to say "Rivanna Magisterial District" Comment Addressed 2. ]32.5.2 (a)] Correct Owner address on left hand side of the cover sheet, under the contact list. Comment Addressed 3. [32.5.2 (a)] Add "Entrance Corridor, Airport Impact Area, and Steep Slopes —Managed" to the site statistics on the cover sheet. Please clarify that they are "Steep Slopes — Mana¢ed." 4. 132.5.2(b) and 4.121 A drive through car wash or simply a car was is not a use identified in Section 4.12.6, therefore, the proposed use would be subject to 4.12.7. The Zoning Administrator will need to approve the number of proposed parking spaces prior to final site plan approval, although it appears to be an appropriate amount. I would recommend changing the box to read "Parking Schedule" instead of "Parking Requirements" and then only include the number of provided spaces. Since this use is subject to 4.12.7 and doesn't have a parking rate and required amount this schedule is best left without it. Comment has been addressed by Zoning approval. 5. 132.5.2 (b)] Update the "Proposed Use" section of the cover sheet so that it states "Car wash." Comment Addressed 6. 132.5.2 (b)] Update the setbacks listed on the cover sheet so that it states the minimum and maximum permitted setbacks. Per Section 18-4.20, there is no maximum front setback since this is a comer lot abutting a principal arterial highway. Update the side setback so that is states "primary structures shall be constructed and separated in accordance with the current edition of the Building Code." Comment Addressed 7. [32.5.2 (d)] Show and label all areas of Managed Steep Slopes on the site plan. Identify the source used to locate areas of Managed Steep Slopes. Clarify the label on Sheet CV-101 to identify these slopes as Managed Steep Slopes. 8. 132.5.2 6)1 Show all existing and proposed stormwater and drainage easements. State the dimensions of the easements. Comment Addressed 9. 132.5.2 (1)] Show all existing and proposed easements for water, sewer, and other utilities. State the dimensions of each easement. Comment Addressed 10. 132.7.9.7 (a)(3)] Please provide a construction detail in plan and profile view of the proposed dumpster enclosure. The detail should identify materials to be used, color, dimensions, etc. Please be aware that walls used for screening must be a minimum of 6' in height. Comment Addressed 11. 132.7.4.21 Prior to final site plan approval, the applicant must submit an easement application for review that shows all proposed stormwater and drainage easements. The plat must be approved by the County and recorded prior to final site plan approval. The final site plan will need to be updated to state the deed book and page number of the recorded instruments associated with all new easements. Comment Addressed 12. [32.7.5.31 Prior to final site plan approval, the applicant must submit an easement application for review that shows all proposed ACSA water and sewer easements. The plat must be approved by the County and recorded prior to final site plan approval. The final site plan will need to be updated to state the deed book and page number of the recorded instruments associated with all new easements. Comment has been addressed pending ACSA approval/comment. 13. lGeneral Comment] Please add the Site Review Committee (SRC) signature panel (attached) to the cover sheet. Comment Addressed 14. lGeneral Comment] Prior to final site plan approval, the final site plan will need to meet all applicable requirements of Section 18-32.6 and 18-32.7 of the Zoning Ordinance. Comment Addressed 15. lGeneral Comment] It should read "Entrance Corridor" not Entry Corridor on the Landscaping Plan sheet. Comment Addressed 16. lGeneral Comment] The first general landscaping note appears to have a typo where there is an extra 1. Comment Addressed 17. [General Comment and 4.171 Prior to final site plan approval, all applicable requirements of Section 18-4.17 must be met related to outdoor site lighting. Comment Addressed 18. 14.171 Lighting Loss Factor should be 1.0 and not 0.9. Comment Addressed New Comments Final Site Plan 1. 132.7.5.41 If any new easements for cable or public service utilities are needed, please include these on the easement plat mentioned in comment # 12 above 2. [32.7.9.4(b)(2)] Please have the owner or contract purchaser sign the conservation checklist on Sheet CP-101. 3. [General Comment] The label for "10 Po" on the landscaping plan (Sheet CP-101) should be corrected to 9. There is a total of 15 of these shrubs on the site, a string of 9 (not 10) and a string of 6. Please contact Kevin McCollum at the Department of Community Development at kmccollum&albemarle.org or (434) 296-5832 ext. 3141 for further information. Albemarle County Engineering Services (Engineer): Contact: Matthew Wentland / ianderson2galbemarle.org Review Status: Requested Changes, see below (1/21/2021) 1. A VSMP plan will need to be submitted and approved prior to Final Site Plan approval. Review of the VSMP plan may generate additional comments on the Final Site Plan. Albemarle County Department of Fire & Rescue (Fire -Rescue): Contact: Shawn Maddox / smaddoxkalbemarle.org Review Status: No Objection (1/25/2021) Albemarle County Building Inspections (Inspections): Contact: Betty Slough / bsloug]galbemarle.org Review Status: No Objection (1/25/2021) Albemarle County Information Services (E911): Contact: Brian Becker /bbeckergalbemarle.org Review Status: No Objection (1/7/2021) Albemarle County Service Authority (ACSA): Contact: Richard Nelson / melson@serviceauthority.org Review Status: Review Pending. Will send review comments once they are available to me (1/26/2021) Virginia Department of Transportation (VDOT): Contact: Adam Moore / Adam.Moore&vdot.vireinia.Qov Review Status: Review Pending. Will send review comments once they are available to me (1/26/2021) Virginia Department of Health (VDH): Contact: Alan Mazurowski / alan.mazurowski(2vdh.vir ig nia. go Review Status: No Objection (1/23/2021) Albemarle County Zoning Services Contact: Francis MacCall / finaccall a albemarle.org Review Status: No Objection to the parking provided (1/25/2021) Albemarle County Architectural Review Board (ARB) Contact: Khristopher Taggart / fmaccall(a-)albemarle.org Review Status: Review Pending, see comments below (1/22/2021) 1. Review pending an ARB fmal site plan submittal