Loading...
HomeMy WebLinkAboutWPO200700053 Review Comments WPO VSMP 2019-06-26COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP Permit plan review Project title: Ashcroft — Phase III Project file number: WPO201000056/VTPO200700053 (Amendment) Plan preparer: Dominion Engineering [dgreene@roudabush.com] Owner or rep.: Richard L. Beyer [rick@beyerhomes.com] Plan received date: Jan 30, 2018 Jan 7, 2019 May 17, 2019 Date of comments: March 7, 2018 Feb 15, 2019 (Rev. 1) June, 2019 (Rev. 2) Reviewer: David James (ext. 3273) County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the comments below. The application may be resubmitted for approval if all of the items below are satisfactorily addressed. The VSMP application content requirements can be found in County Code section 17-401. Amendments (General): 1. The approved plans must be included in the plan set, with the specific areas of amendment clearly outlined by bubbling or circling. The approved plans must not otherwise be altered. (Rev. 1) Addressed. 2. (Rev.1) Submit the E&SC Plan for review. Comments under section E below have not been addressed. (Rev.2) Addressed. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary. 1. Registration Statement— Update the R.S. to include (1) a phone# & (7) County of Albemarle as MS4 operator. (Rev. 1) Addressed. 2. Provide an overall map `exhibit sheet' insert of the PPP showing the potential sources of stormwater pollution generating activities (location & type). (Rev. 1) Not addressed. (Rev.2) Partially addressed. See B.1. comment. 3. Provide any additional locations on PPP & ESC plan for support activities (17-405A(5)a). (Rev. 1) Not addressed. (Rev.2) Partially addressed. See B.1. comment. B. Pollution Prevention Plan (PPP) The PPP content requirements can be found in County Code section 17-404. Engineering Review Comments Page 2 of 7 1. Submit `exhibit sheet' for review. (Rev.1) Not addressed. (Rev.2) Partially addressed. It needs to be updated to show any proposed clearing/grading activities, paving operations, landscaping operations, E&S controls, staging, stockpile, borrow, fueling, waste disposal, vehicle/equipment washing, concrete washout locations. Also, show locations where concentrated stormwater discharges. C. Stormwater Management Plan (SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is not approved, and the reasons are provided in the comments below. The stormwater management plan content requirements can be found in County Code section 17-403. 1. Provide any state permits authorizing disturbance of the streams and wetland areas. Letter provided on Sheet E2 is a letter of determination, not a permit to impact wetlands or waters of the State. (Rev.1) Acknowledged. Show WPO buffer. (Rev.2) Addressed. 2. According to SWM narrative you plan to meet energy balance by using a biofilter, but the amended plan proposes to remove all biofilters. Please clarify. (Rev.1) Addressed. 3. It appears that the existing drainage area of 175 ac. to SWM-1 according to the plans is smaller than what I assessed. Please confirm and correct the DA size accordingly. (Rev.1) Addressed. 4. Show how you determined the phosphorus removal rates (water quality under Part II Q. (Rev.1) Addressed. 5. Remove approval block from cover sheet. (Rev.1) Addressed. 6. Show direction of stormwater flow and approximate slopes after grading operations (17- 405A(5)a). (Rev.1) Comment still valid. Response: The direction of stormwater flow and approximate slopes after grading have been shown on sheet 5. (Rev.2) The note stating that all slopes are 4:1 or 3:1 appears to be inaccurate. See comment E.10 below. 7. Show SWM Facility & access easement. Show drainage easements & widths. (Rev.1) Currently addressed. (Rev.2) Include vegetative buffer within SWM facility easements. 8. Stormwater maintenance agreement & SWM bond required prior to issuing grading permit. (Rev.1) SWM bond required prior to issuing grading permit. (Rev.2) Comments still apply. 9. Provide mitigation plan for WPO buffer disturbance. (Rev.1) Addressed. 10. SWM facility easement plat and deed must be submitted, reviewed, approved and recorded prior to VSMP plan approval. If these were already recorded, please provide a copy of the plat and deed. (Rev.1/2) Comment still valid. 11. (Rev.1) Sheet 3/4 - a. Show WPO buffer. (Rev.2) Addressed. b. Show sediment forebays in the details. (Rev.2) Addressed. c. Design adequate outfall protection from the principal spillway to receiving channel; 12. 13. 14. 15. 16. Engineering Review Comments Page 3 of 7 Designed to control the expected weir flow and velocity. (Rev.2) Label the energy dissipater at the outfall points. It's hard to see the contours there (recommend lightening the hatching pattern). d. Extend concrete armoring to toe of dam. (Rev.2) Use grouted riprap to toe. e. Veg. emergency spillway should not be located on any portion of the embankment fill. Armored spillway may be provided. (SWM HB, Min. Standard 3.03) (Rev.2) Correct details on sheet 3, remove `grassed' label and leave `emergency spillway'. f. There should be a defined & adequate receiving channel from the spillways. (Rev.2) Addressed. g. Show minimum 20' wide vegetative buffer strip, as measured from the maximum WSE. (Rev.2) Show it as 20' from the 100-yr elevation. Include this buffer width in SWM facility easements. h. Basin should be 20' from any structure or proper, line, and 100' from any septic tank/drainfield. (Rev.2) Currently addressed. Will need to show any proposed drainfields, lot lines for SUB plan, Dept. of health to review. i. Retention basin should be a 50' (min) from any steep slopes. Alternatively, a geotechnical report must address the potential impact the basin will have constructed near such slope in accordance with SWM HB, Min. St'd 3.01. (Rev.2) Not addressed. Steep slopes (not critical slopes) defined as greater than 15%. (SWM HB, Min St'd 3.06) j. An aquatic bench should be provided if the basin's surface area exceeds 20,000 sf. (SWM HB, Min. St'd 3.06) (Rev.2) Provide landscaping plan requirements for the aquatic benches. (SMW HB, Min. St'd 3.05) k. The embankment cutoff trench should be excavated a min. 4' in to suitable material. (Rev.2) Addressed. 1. Trees & shrubbery should not be planted on the embankment & in area extending 25' beyond toe of dam. (Rev.2) Addressed. in. The forebays should be accessible by maintenance equipment. Provide access to other forebay. (Rev.2) Addressed. n. Provide trash rack detail. (Rev.2) Addressed. o. Verify if the invert of the barrel is 725.5' and not 7261. 725.5' shown in plan, 726' in calcs. Provide anti -seep collar or filter diaphragm for barrel. Joints should be made watertight. (SWM HB, Min. St'd 3.02) (Rev.2) Addressed. p. SWM-2 - Show 12" orifice. Show emergency spillway cross-section detail. (Rev. 2) Addressed. q. Provide posted warning signs around SWM-1. (SWM HB, Min St'd 3.06) (Rev.l) The channels leading from SWM basins will have to meet channel / flood protection to your limits of analysis. (Rev.2) Addressed. (Rev.l) A geotechnical engineer or technician should be on site during embankment construction to monitor and report proper installation/construction. (Rev.2) Addressed. (Rev.l) Provide narrative for the maintenance requirements of the proposed SWM facilities. (Rev.2) Addressed. (Rev.1) All culverts/conveyances shall discharge concentrated runoff to a natural channel or adequate channel, or SWM facility (i.e. culverts on sheet 3 do not). (Rev.2) You must show each conveyance channel from every outfall point meets adequate channel (2410-yr design) to your limits of analysis (VAESC HB, Ch.5, V-122). (Rev.1) Sheet 5 - a. You're showing undetained areas in your disturbance - DA-Y and DA-B 1. Provide stormwater management for the runoff in those areas. Show how those areas will meet Engineering Review Comments Page 4 of 7 water quantity req. (Rev.2) Show adequacy of outfall channels (2-yr/10-yr channel analysis) for each outfall point to your limits of analysis. b. Label your Tc flow path. (Rev.2) Currently addressed. c. (Rev.2) Why is the pre-dev Tc (25.3 min) much lower than the approved plans pre- dev Tc (44.26 min)? Show computation of Tc using `Worksheet 3 (TR-55)' for DA- A, DA-B, DA-M & DA-Q & determination of Q. 17. (Rev. 1) Calc. packet — a. Your DA of 142.28ac should match the plan 142.8ac going to SWM-L (Rev.2) Addressed. b. According to Hyd. No. 10 the 10 yr peak discharge is 86.71cfs. What is the velocity from the spillway? (Rev.2) Addressed with energy dissipation at outfall prior to entering stream. c. Show the outflow (discharge/velocity for the 1,2,10,100yr) report for the pond orifice and weir controls. i. (Rev.2) Provide report of the outflows from the controls (velocity & discharge rate). ii. (Rev.2) SWM-1 report— Show staging starting from bottom elev. 656'. D. Mitigation Plan (MP) The mitigation plan requirements can be found in County Code Chapter 17-406. 1. Submit plan & fee for review (17-208). (Rev. 1) Addressed. 2. (Rev. 1) Must provide mitigation elsewhere in the stream buffer to meet the 2:1 requirement. Identify other areas in the buffer where mitigation (restoration or reclamation) can be applied. Response: Mitigation has been provided to the maximum extent possible. (Rev.2) Conduct a survey to identify other possible mitigation areas on the property in the buffer to meet this requirement. 3. (Rev. 1) Concentrated discharges are to be treated or extended to adequate channels to preserve buffers. (Rev.2) Determination of adequate channels from outfalls to be included with next review. E. Erosion and Sediment Control Plan (ESCP) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is not approved, and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17-402. 1. Remove approval block from cover sheet. (Rev.2) Addressed. 2. Provide date & source of topographic information: All topography should be at least visually field verified by the designer within the last year. (Rev.2) Addressed. 3. Show WPO buffer limits; 100' from stream or edge of wetland. (Rev.2) Addressed. 4. Show all steep slopes (typically shaded). Existing critical slopes are not to be disturbed, unless a waiver or exemption has been granted for the disturbance (18-4.2, 14-304). Response: Steep slopes have been shown. The project is exempt from the critical slopes ordinance. (Rev.2) Partially addressed. Refer to Sect 17-405 A.6. Engineering Review Comments Page 5 of 7 5. Show any existing easements with deed book references.-Meadaw Crossing Trail 50'Private Access Easement (Rev.2) Not addressed. 6. Show construction staging, parking area(s). (Rev.2) Addressed. 7. Adjust the LOD to encompass all disturbances, entrances (i.e. Lego Road intersection - Sta. 10+00 to Sta. 15+00), areas where sediment laden runoff will cross, and any construction related activities (e.g. Sheet E7 - grading shown outside LOD). (Rev.2) Currently addressed. 8. Indicate areas already disturbed with constructed fill depth or cut noted. The amended plan shows that the grading for the road entranceway from intersection of Lego Road to Sta. 15+00 has been completed (paving operations remain). (Rev.2) Addressed. 9. Show CE draining to sediment trap (or ST device location). (Rev.2) Addressed. 10. Show low maintenance (not grass) ground cover area(s) for proposed slopes greater than 3:1. Low maintenance cover is required as a final stabilization measure. (Rev.2) Not addressed. Show/label areas of constructed slopes that are 3:1 and steeper. I've identified slope areas steeper than 3:1 with the proposed grading shown on sheets E4 - E14. 11. Show OP symbol at all ends of pipe outfalls. (Rev.2) Addressed. 12. Please double check the sheet number references match the right sheet and make corrections. (Rev.2) Partially addressed. Correct for sheet E5, E12 & E13. 13. Sheet E4 - Extend OP to an adequate (MS-19)/natural channel (Energy Balance). (Rev.2) Acknowledged. 14. Sheet E4 - Provide a sediment trap (silt fence inadequate) at low point with diversions going to it. (Rev.2) Addressed. 15. Sheet E5 - Show diversion (DD) along LOD perimeter near lots 25 and 26. (Rev.2) Addressed. 16. Sheet E7 - Show diversion (DD) along LOD perimeter beside Elmcroft Circle. (Rev.2) Addressed. 17. Add ST-12 (missing) design to table of detail. (Rev.2) Addressed. 18. Re -compute earthwork cut/till volumes shown on sheet E12 to incorporate any changes to grading (this will be a road plan comment also). (Rev.2) Addressed. 19. ESC bond required prior to issuing grading permit. (Rev.2) Acknowledged. 20. (Rev.2) Recommend revising E&SC plan and narrative - Phase 1 sheets should show only perimeter controls in place (silt fence, diversions, sediment traps, construction entrance, etc.) and protective controls of existing site features in the disturbance (drainage & waterways, trees, etc.). 21. (Rev.2) Temporary CE, (Std. & Spec. 3.02) needs to be shown located at the beginning of the proposed project in order to meet the minimum State requirements. Once the grading and road surface has been installed, the Owner can work with the E&SC inspector to move the Temp. CE as needed to protect the pavement as required. a. Please correct the narrative accordingly (B12/E2). 22. (Rev.2) Sheet E5 - a. Make the silt fence continuous (near elev. 690' bottom grade) to provide a more effective trapping barrier. Engineering Review Comments Page 6 of 7 b. SCC-2 outfall velocity of runoff will erode bank unless adequately contained. c. Culvert A outlet protection should run parallel with pipe and not askew. Discharge could potentially blowout and erode protection there. d. Outlet protection (riprap) will need to be extended into adequate receiving channel. e. Provide stream protection controls for the crossing (ESC). MS-12-15 23. (Rev.2) Extend channel/outlet protection (Culvert H, Culvert K, SCC-11A, SCC-12, SCC- 24, SCC-20, SCC-13, SCC-18, SCC-19). MS-8 24. (Rev.2) Provide riprap stone sizing is adequate for all proposed channels (Std. and Spec 3.19, Appx 3.19a). 25. (Rev.2) Sheet E5/E10 — Move E&SC controls & drainage structures out of stream buffers & existing steeps slopes that are not part of the road design where possible.17--603 B/17--405 A.( 26. (Rev.2) Provide additional stream protection controls were needed (ESC) & details. MS-12- 15 27. (Rev.2) Sheet 14 — Provide SCC (Std. & Spec. 3.17) and Rip -rap (Std. and Spec 3.19) details. Specify filter/lining to be used. 28. (Rev.2) (CW) is not the State symbol for Std. and Spec. 3.09 (Temporary Diversion Dike) as stated in the Legend and E&SC narrative. Please correct the submittal to reduce potential confusion between the inspector and owner/contractor. 29. (Rev.2) Temporary Diversion Dike (Std. and Spec. 3.09) have a maximum allowable drainage area of 5 acres. Drainage areas of 5 acres or more should have a SCC (Std. & Spec. 3.17). 30. (Rev.2) Show OP at ends of the temporary diversions (CW). 31. (Rev.2) OP (Std. and Spec. 3.18) should not be used on slopes steeper than 10%. Riprap should be used to protect the slope and/or SCC (Std. & Spec. 3.17) designed to an adequate receiving channel or SWM facility. Follow E&SC, Ch. 5 guidance. 32. (Rev.2) Sheets E14/E16 — The drainage area to traps must include all area(s) diverted to it for volume/sizing purposes. Additional (Road plan) comments: A. Sheet E14 — The road plan sheet 19 lists BW (bottom width?) in the remark's column. Are these all V-ditches now? Update the channel calcs for the road plan (Road plan comment). B. Endwall required for culverts 48" or wider (VDOT drainage manual, Ch 8). C. Sheet 20 — (VDOT drainage manual, Ch 8) a. Culvert H should use the 25-yr design. State the design storm frequencies used? b. Culvert B — Headwaters < 1.5 x culvert height. c. Culverts (general), (HW/D) should be at least 1.0 and not exceed 1.5. The VSMP permit application and all plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a completed application form. Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Process: After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate request form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and check parcel and easement information based on the approved plans. The Engineering Review Comments Page 7 of 7 County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted along with court recording fees. After bonding and agreements are complete, county staff will need to enter project information in a DEQ database for state application processing. DEQ will review the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter. This should be copied to the county. After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Applicants will need to complete the request for a pre -construction conference form, and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; http://www.albemarle.org/deptforms.asp?department—edengno File_ W PO201000056 W PO200700053 (amendment) Ashcroft -Phase I II - 2-2019 - ReN ( I )_docs