Loading...
HomeMy WebLinkAboutWPO202000035 Preconstruction Form 2021-02-22 ara Request for Pre-construction Meeting and Grading Permit from Albemarle County-VSMP 4t . Approved Plan Number: WPO- 2020 - 00035 Approved Plan Name: Valvoline Instant Oil Change (Plans must be approved prior to a pre-construction meeting.) (Bonds must be approved and posted prior to a pre-construction meeting or permit.) Responsible Land Disturber:b Print Name: f.\C.t&rA s State Certification Number: 9,L C)'t ' (0 ' 0 Address 30\ G`eve\&( & fiACt t 5�,; )-e_)-e_ Id3 p City v,S V��n�ll� Dekci, State VA- Zip 10i-102— Daytime Phone(151) 10 L r 22-i-3 E-mail V AMA N.es e ; C_ V q L. C o Primary Contractor: `JJ Print Name n d e fe in of e h c t-. CO in.) ►-. C o. irf VA . Address 3 0 C 1EVt the f J i(e t ,S k. ,03 City V t 1t‘01ik g fctck State Vi°1- Zip Z 3 4'b Z- Daytime Phone(151) k Q 0 I S'D6 E-mail W A4-V--; V S e C V Q L. co N 3 Permit Issuance and First Year Maintenance Fees (Request must include payment): Total acres proposed to be disturbed is contained on the approved plan and application:VSMP: Acres to be disturbed Fee Due at Grading Permit Less than 1 $63.80 1 and less than 5 $594.00 5 and less than 10 $748.00 10 and less than 50 $990.00 50 and less than 100 $1,342.00 100 and more $2,112.00 Annual Maintenance Fees[Section 17-208 of the Albemarle County Code]-Annual maintenance fees will be assessed in March of every year this permit is active.Fees cannot be prorated after the first year of permit issuance. 7/1/14,Revised:8/29/14,8/28/19,8/25/2020 Page 1 of 3 Person(s)to attend the Pre-construction Meeting: Names(type or print) Firm Contact Number or email —3-ac8_ \ & , pvpsSctf- Ply,- =►.der,,„Aeh (dru1-1-1-,t'Nti,.-N 3 ALI t? i c v�l c. cov.-, 6kv._ Tvstts , s 4 re i-Nith0-" �ncitrehdncct Co,,-1L,c .,-, v �- ,•; ae s �_Jt(v j c-co,\ FOR OFFICE USE ONLY WPO# Fee Amount$ Date Paid _By who? Receipt# Cktt By: 7/1/14,Revised:8/29/14,8/28/19,8/25/2020 Page 2 of 3 Jonney Otto From: Carrie Watkins <cwatkins@icvgc.com> Sent: Tuesday, March 2, 2021 2:36 PM To: Jonney Otto;Jack Kay; Richard Trites; Sarah Clark Cc: Carla Harris - CDD; Matthew Wentland; Kenny Thacker Subject: Re:Valvoline Instant Oil Change-VSMP project (WP02020-00035) preconstruction meeting CAUTION:This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open attachments unless you are sure the content is safe. VSMP/VESCP Contact Information Project Name: Valvoline Instant Oil Change- Project/WPO Number: WPO-2020-00035 VSMP Tax Map/Parcel 45-111C/04500-00-00-111C0 DEQ Permit Number VAR10P111 (if applicable): Valvoline-John Culley, Land Handley Excavation & construction manager 859-221- Site Operator/phone Owner/contact 8641 Development/434-806-8895 Qualified Jack Kay, ICV project manager Principle Carrie Watkins/757-490- Personnel/phone 757-679-8096 contact/phone 1500 RLD name& number Rick Trites-757-402-2243/ Contact E-Mail: cwatkins@icvgc.com contact info rtrites@icvgc.com Inspector: Jonney Otto/434.981.5154 Nutrients Credits Disturbed Acreage: 1.14 acres Carrie W. Watkins Vice President of Business Development Independence Construction Co. of VA 3oi Cleveland Place, Suite io3 Virginia Beach,VA 23462 757-470-5531 direct 757-552-0768 fax www.icvgc.com 1 rfrTF GI Erosion & Sediment Control-Stormwater Management Preconstruction Conference Agenda Project Name: Plan No.: WPO- Approved Date: 1. Copies of approved plan given to: Owner or Authorized Agent Contractor 2. Responsible Land Disturber: Cert./Lic.No.: Type: Address/Phone/ Mobile Phone: 3. Name of Prime Contractor: Address/Phone/ Mobile Phone: Name of Subcontractor: 4. Introductions—please introduce yourself and state your roll in this project. Name Firm 5. County Inspector to confirm prior to and during meeting with the contractor: a. Approved Plans in CountyView? Yes No b. Approved SWPPP in CountyView? Yes_ No c. Bond has been posted? Yes_ No d. County Permit in file? Yes_ No e. DEQ Permit submitted and paid? Yes_ No _ f. Does the contractor have a copy of the approved plans/SWPPP/Permits?Yes No 6. VDOT Entrance Permit —Contractor must obtain permit prior to starting construction. Contact Brenda Loving 434-422-9399 (Brenda.loving@vdot.virginia.gov). 7. ESC Inspections and Requirements a. Review project-specific erosion and sediment control measures and tree protection—all perimeter measures must be installed prior to any other land disturbance. b. Review project-specific Erosion and Sediment Control Narrative and Sequence of Construction. c. Are there slopes greater than or equal to 3:1 anywhere on the site? If so,they should be surveyed/confirmed prior to applying final stabilization(the sooner the better). Ground cover required for slopes steeper than 3:1 (unless in full sun and otherwise noted on plans). Slopes steeper than 2:1 are prohibited and MUST be field confirmed. d. Placement of topsoil for required stabilization? Recommend Buckwheat for stockpile stabilization and Millet for temporary stabilization. Lepozedia is an invasive and cannot be used —check to make sure mixes do not include this seed. 1 of3 https://albemarlecountyva-my.sharepoint.com/personal/fpohlalbemarle_org/Documents/Documents/1-Engineering/Resourees/Preconstruction Conf Checklist 9-21-17.doc e. Is the site balanced (cut/fill)?If export will result in 10,000 sf of land disturbance,where will the export go?Must include offsite areas on DEQ permit/SWPPP. If offsite area is not already included on Registration Statement and want to add it to existing permit, operator must submit a permit modification to the County ESC inspector 1 week prior to starting export activities. Otherwise, a separate permit is required. f. Review Frequency of Inspections: Every 4 business days or every 5 business days and within 48 hours of a major rain event. Major rain event is 0.25" or more. Less frequent in areas of non-impaired waterways (5 days or every 7days and within 48hours of a major storm event). Must self-report to DEQ within 24 hrs if there is a sediment release. g. Enforcement and Fees: Warnings, NTC and SWO in that order with re-inspection fees of$250 for NTC's and SWO's (Mud in the roadway will have a NTC issued without a warning). h. VSMP-SWPPP requirements. i. Record Keeping ii. Pollution Prevention requirements iii. 7-day temporary stabilization requirement iv. Concrete/Material Washout requirement v. Recording of pollutants and their location on site vi. Documentation of progress. i. Onsite postings i. Registration Statement. ii. DEQ Coverage Letter. SWPPP documents. If not in the mailbox, provide information on where SWPPP is located and who to contact to view (must be located on site). iv. County permit. j. County Maintenance Fees — due yearly on April 151. Close-out must be approved prior to April 1st, including final stabilization and stormwater facility reviews/inspections/approvals,to avoid the next year's fee. 8. Stormwater Management Facilities a. Review project-specific SWM facilities as shown on the approved drawings. i. TYPE (list) ii. TYPE (list) iii. TYPE (list) b. Review construction requirements as shown on the approved drawings. c. Pond construction requirements. d. Required documentation/inspections. e. Drainage areas. f. Closeout requirements. 9. 9-month County ordinance. Refer to Ordinance below: Article II,section 17-207 B. Each permit shall also be subject to the following: 1. The permitted land disturbing activity shall be deemed to have commenced on the date the permit was issued, provided that the program authority may establish another date of commencement based on documentation submitted by the owner that clearly demonstrates that the land disturbing activity commenced on that date. 2. Permanent vegetation shall be installed on all denuded areas within nine (9) months after the date the land disturbing activity commenced, except for areas that the program authority finds are necessary parts of the construction that are subject to an active building permit and areas where erosion is prevented by a non-erosive surface. For the purposes of this section,a"non-erosive surface"includes, but is not limited to, roadways and sidewalks covered by gravel, asphalt pavement, or concrete; trails or paths covered by gravel, stone dust,or mulch; buildings and other permanent structures; and such other surfaces that the program authority determines would adequately provide a permanent barrier to erosion. 3. The time limit for installing permanent vegetation as required by paragraph (B)(2) may be extended by either the program authority or the board of supervisors,or both,as follows: a. The program authority may extend the time limit for installing permanent vegetation up to an additional six (6) months, provided the owner submits a written request to the program 2 of3 https://albemarlecountyva-my.sharepoint.com!personal/fpohl albemarle_org/Documents/Documents/I-Engineering/Resourees/Preconstruction Conf Checklist 9-21-17.doc authority no less than one (1) month prior to the deadline for installing the permanent vegetation. The program authority may grant the extension if it finds that: (i) the additional time is necessary due to factors beyond the control of the owner; (ii)the owner had made good faith efforts to comply with the time limit; and (iii)the owner has effectively controlled erosion and sedimentation on the property during the land disturbing activity. In granting an extension, the program authority may impose reasonable conditions. b. The board of supervisors may extend the time limit for installing permanent vegetation for duration it determines to be appropriate, provided the owner submits a written request to the clerk of the board of supervisors no less than two (2) months prior to the deadline for installing the permanent vegetation. The program authority shall provide its opinion to the board as to the condition of the property with respect to compliance with this chapter and an estimate of the minimum time needed to complete grading and install permanent vegetation for the land disturbance covered by this permit. The board may grant the extension if it finds that: (i)the additional time is necessary due to factors beyond the control of the owner; (ii)the owner had made good faith efforts to comply with the time limit; and (iii) the owner has plans to effectively contro I or has effectively controlled erosion and sedimentation on the property during the land disturbing activity. In granting an extension, the board shall set a time limit and may impose other reasonable conditions. Notes: 3 of3 https://albemarlecountyva-my.sharepoint.com/personal/fpohl albemarle_org/Documents/Documents/1-Engineering/Resources/Preconstruction Conf Checklist 9-21-17.doc Request for Pre -construction Meeting and Grading+ Permit from Albemarle County -VSMP t nxavr Approved Plan Number: WPO- Approved Plan Name: (Plans must be approved prior to a pre -construction meeting.) (Bonds must be approved and posted prior to a pre -construction meeting or permit) Responsible Land Disturpber:1 Print Name: h\ CyN f&vA T✓. }tS State Certification Number: V L D I b 1 D Address 301 C\e-ve\aid, glace t SI91 City .Vivt1+ht(ti eOLCL. State VA_ Zip 2-O'HO L-- Daytime Phone (1n) k02—' 2-2-A-3 E-mail }CS e- 'I �v I L• Cow+ Primary Contractor: J L,� Print Name 3--ntdf:VevAehCt t`oa-+�'}'✓ti,t'T�h Co. a"f' VA. Address 3 01 C- \eVC I ct "d e l a (4t d S t c; J u 3 City V t ✓ t,1ia 6 eac�\ State V%r Zip Z 3 `fib Z Daytime Phone (15 j) k I D 1 S 00 E-mail L W A-� ki 1,1S e t Cy g L. C o ✓`i Permit Issuance and First Year Maintenance Fees (Request must include payment): Total acres proposed to be disturbed is contained on the approved plan and application: VSMP: Acres to be disturbed Fee Due at Grading Permit Less than 1 $63.80 1 and less than 5 $594.00 5 and less than 10 $748.00 10 and less than 50 $990.00 50 and less than 100 $1,342.00 100 and more $2,112.00 Annual Maintenance Fees [Section 17-208 of the Albemarle County Code] — Annual maintenance fees will be assessed in March of every year this permit is active. Fees cannot be prorated after the first year of permit issuance. 7/1/14, Revised: 8/29/14, 8/28/19, 8/25/2020 Page 1 of 3 Person(s) to attend the Pre -construction Meeting: Names (type or print) Firm �ac� Kati ovo�ct} r,ri� =••fie �- T� 1�; t 1L T. �e c Z r Contact Number or email ,1��titi�r �kat� e�cov&, FOR OFFICE USE ONLY WPo# Fee Amount liDate Paid By who? Receipt # CkN By: 7/1/14, Revised: 8/29/14, 8/28/19, 8/25/2020 Page 2 of 3 2/19/2021 (https://www.virginia.gov) Search Results - CATS Agencies (httpsEO ://www.virginia.gov/agencies) i Governor (https://www.governor.virginia.gov) Search Virginia.Gov (https://www.virginia.gov/search) IAA IKt 3V11(A'I:AL (�14tl,rfw` (https://www.deq.virginia.gov) arch (/CATS/Home/Search) ;earch (/CATS/Home/Search?FirstName=richard&LastName=trites&Page=1&ExactCertMatch=False&ZipRadius=5) Search Results Found 1 items (1 page). Page: a » Phone and email address will only appear if the certificate holder has granted permission to display this information publicly. I rates, Richard INDEPENDENCE CONSTRUCTION COMPANY OF VIRGINIA Virginia Beach, VA Certifications: • Responsible Land Disturber (RLD) #RLD11610 -Expires 02/11/2022 Page: '', « 1❑ » For assistance with the Certification Accreditation Tracking System (CATS) please email certification@deq.virginia.gov (mailto:certification@deq.virginia.gov) or telephone (804) 698-4375. https://apps.deq.virginia.gov/CATS/Home/SearchResults?LastName=trites&FirstName=richard&CertType=&ExactCertMatch=False&CertNumber=&Or... 1 /1 Information for Permit applicants; 9-Month Permanent Stabilization Deadline: Code Sec. 17-808 Duty to stabilize denuded areas with permanent vegetation within nine months after commencing land disturbing activity A. When permanent vegetation required. The owner shall install on all denuded areas on the site within nine (9) months after the date the land disturbing activity commenced, except for areas that the administrator determines are necessary parts of the construction that are subject to an active building permit and areas where erosion is prevented by a non -erosive surface, including, but not limited to, the following surfaces: (i) roadways and sidewalks covered by gravel, asphalt pavement, or concrete; (ii) trails or paths covered by gravel, stone dust, or mulch; (iii) buildings and other permanent structures; and such other surfaces that the administrator determines would adequately provide a permanent barrier to erosion. (see code 17-808 for information about possible extensions) Notice to Comply and Permit Revoked for Overdue Fees Late fees will incur interest, and enforcement actions per code section 17-210. (1) Owners with late payments of fees required by 17-207C6 will be issued a Notice to Comply (NTC). The notice gives 7 days to make payments. (2) At the end of the NTC time period, the permit will be revoked, and a Stop Work Order will be issued for working without a current permit. Disturbed Area Reductions Acreage for the purpose of fee computations will be the entire permitted acreage. This is the disturbed acreage on approved plans. If fees are to be reduced, an application for plan amendment must be made, and areas reduced by changes in limits of disturbance and appropriate plan changes. Such amendments must be approved prior to the fee due date. Amendments to remove disturbed areas can only be approved when such areas are completely stabilized and all erosion control measures (including traps and basins) removed. Refunds The County does not have a refund program. Fees will not be refunded based on completion within the year. Fees will not be pro -rated at payment, other than the first year VSNW fee as indicated in code section 17-209B. Re -inspection Fees Re -Inspection Fees will be charged for inspections following a Notice to Comply or a Stop Work Order. Fees are $250 per inspection, or as given in code sections 17-207 and 17-208. 7/1/14, Revised: 8/29/14, 8/28/19, 8/25/2020 Page 3 of 3