HomeMy WebLinkAboutWPO201800007-79062-Full Inspection ReportCOUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
(434)296-5832
WRITTEN WARNING
Hand delivered
Project: WP0201800007
RIVANNA VILLAGE -Amendment 1 and Phase II
Operator/Contractor: Haley, Chisholm & Morris, Incorporated
RIVANNA INVESTMENT HOLDINGS LLC
Issued Date:3/15/2021
This is your Written Warning in accordance with § 17-900 of the Water Protection Ordinance of
Albemarle County and Section 62.1-44.15:37 of the Virginia Stormwater Management Act.
This Written Warning is being issued because of the following deficiencies:
Deficiency: Great coverage. Minimum overseed recommended
Corrective Action:
Deficiency: Stabilize any that are not actively working or are larger then what can be worked within any
7 day period
Corrective Action:
Deficiency: Repair needed at SB being utilized from phase one. Dewatering device is broken
Corrective Action:
Deficiency: Great job in stabilized areas
Corrective Action:
Deficiency: Minor repairs required
Corrective Action:
Deficiency: Minor silt fence repais needed.
Corrective Action:
Unless subsequently amended in writing by this office, it is expected all corrective
measures will be completed by
Failure to comply by the required date may subject the owner to penalties and remedies as listed
under § 17-900 et -al of the Water Protection Ordinance of the Albemarle County Code.
Should you have a legitimate reason you cannot complete your required corrections by the
above given date, you must immediately contact your erosion control inspector. Unless you
have contacted the inspector and agreed to alternative arrangements, all compliance work is
expected to be completed by the above date.
County Inspector Name: Geoff Elsie
County Inspector Phone Number: (434) 296-5832
orA1.4 Inspection Result: Warning
TH
Ljk GI'.�ti�
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
VSMP/VESCP PERMIT SITE INSPECTION REPORT
Project Name:
RIVANNA VILLAGE -Amendment land
Phase II
project/WPO Number:
WP0201800007
TMP:
093A1000000300
DEQ Permit Number (if
applicable):
VARlOJ510
Project Operator:
Haley, Chisholm & Morris,
Incorporated
Operator Telephone #:
(434) 978-1000
Project Contact:
RIVANNA INVESTMENT HOLDINGS LLC
Contact Telephone #:
Contact E-Mail:
tculpepper@robinsondevelopment.com
Qualified Personnel (QP):
Charles Justin Maxey
Inspector:
Geoff Elsie
Weather (Wet/Dry/Rain):
Disturbed Acreage:
Inspection Date & Time:
3/15/2021
Single -Family:
Stage of Construction: Grading
Re -Inspection: No
COVERAGE & POSTING REQUIREMENTS
Compliant?
Reviewed during re -inspection? No
Comments/Description
1
Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A)
(9VAC25-870-31 0)(Al b. Co. Code §17-300, 17-302)
2
A copy of the notice of coverage letter is posted conspicuously near the
main entrance of the construction activity? (CGP Part II.C)
Notice of the location of the SWPPP is posted near the site's entrance, if
3
applicable, and information for public access is provided? (9VAC25-870-
54.G)(CGP Part II D.2 & 3)
SWPPP AVAILABILITY AND CONTENTS
Compliant? Reviewed during re -inspection? No
Comments/Description
4
The SWPPP is on -site or made available during the inspection? (CGP
Part II D.1 & 2)(9VAC25-870-54.G)
5
The SWPPP contains a signed copy of the registration statement?
(CGP Part II A.1.a)
6
The SWPPP includes, upon receipt, a copy of the notice of coverage
letter and the CGP? (CGP Part II A.1.b & c)
The SWPPP includes a narrative description of the nature of the
7
construction activity, including the function of the project? (CGP Part II
A.1.d)
The SWPPP includes a legible site plan identifying all appropriate
8
measures and that includes the locations of support activities and the
onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7))
Page 1 of 4
9
The SWPPP contains the name, phone number and qualifications of
"Qualified Personnel" conducting inspections? (CGP Part II A.6)
10
The SWPPP contains an approved erosion and sediment control plan?
(9VAC25-870-54.B)(CGP Part II.A.2)
The SWPPP contains an approved stormwater management plan or an
11
existing construction site has a stormwater management plan that
ensures compliance with the water quality and quantity requirements?
(9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ II.0 ❑
12
The SWPPP contains an adequate pollution prevention plan? (9VAC25-
870-54.D)(CGP Part II.A.4)
The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of
13
concern, exceptional waters and the additional controls measures
applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b))
14
Delegation of Authority is provided and signed in accordance with Part III
K? (CGP Part 11 A.7)
15
The SWPPP is signed and dated in accordance with Part III K? (CGP Part
11 A.8)
SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES
Compliant?
Reviewed during inspection? No
Comments/Description
Is the SWPPP being amended whenever there is a change in the design,
16
construction, operation, or maintenance that has a significant effect on the
discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870-
54.G)
Has the SWPPP been amended if inspections or investigations by the
17
operator's qualified personnel, or by local, state or federal officials find that
existing control measures are ineffective in minimizing pollutants in
discharges? (CGP Part II B(2))(9VAC25-870-54.G)
18
Contractor(s) that will implement and maintain each control measure are
identified? (CGP Part 11 B(3))(9VAC25-870-54.G)
Have there been updates to the SWPPP when any modifications to its
implementation have occurred, including a record of dates when major
19
grading activities occur, construction activities temporarily or permanently
cease on a portion of the site or stabilization measures are initiated? (CGP
Part 11 B.4(a))(9VAC25-870-54.G)
20
Is there documentation in the SWPPP of replaced or modified controls?
(CGP Part 11 B.4(b))(9VAC25-870-54.G)
21
Is the SWPPP updated to indicate areas that have reached final
stabilization? (CGP Part 11 B.4(c))(9VAC25-870-54.G)
Is the SWPPP updated to indicate properties that are no longer under the
22
legal control of the operator and the dates on which the operator no longer
had legal control over each property? (CGP Part II B.4(d))(9VAC25-870-
54.G)
Does the SWPPP identify the date of any prohibited discharges, the
23
volume released, actions taken to minimize the impact of the release and
measures taken to prevent the recurrence of any prohibited discharge?
(CGP Part 11 B.4(e-f)) (9VAC25-870-54.G)
24
mendments, modifications, or updates to the SWPPP are signed in
accordance with Part III K? (CGP Part II B(5))(9VAC25-870-54.G)
INSPECTIONS AND CORRECTIVE ACTIONS
Compliant?
Reviewed during inspection? No
Comments/Description
Inspections required by the SWPPP are conducted at the required
25
frequency, including a modified frequency for impaired water(s), approved
TMDL(s), and exceptional waters when applicable? (CGP Part II F (2))
(CGP Part II A.5.b.3)
26
Inspection reports are completed and signed in accordance with CGP
Part 11 F (3-4)? (CGP Part 11 F (3-4))
Page 2 of 4
27
Corrective actions are taken consistent with the requirements of the
CGP? (CGP Part II G(1-2))
ESC AND SWM PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? Yes
Comments/Description
28
Have stream buffers and steep slopes been protected as shown on the
Yes
plan?
Sequencing of the project is implemented in accordance with the
Yes
29
approved erosion and sediment control plan and stormwater management
plans? (9VAC25-870-54.B and C)
Have all denuded areas requiring temporary or permanent stabilization
Great coverage. Minimum overseed recommended
been stabilized, and have stabilization requirements for impaired waters,
30
approved TMDL(s), pollutants of concern and exceptional waters, when
Yes
applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25-
880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8))
(CGP II E(1-2))
Are soil stockpiles adequately stabilized with seeding and/or protected
Stabilize any that are not actively working or are larger
31
with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II
No
then what can be worked within any 7 day period
A.2(c)) (9VAC25-870-54.B)
A permanent vegetative cover has been established that is uniform,
N/A
32
mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3)
(CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Have sediment trapping facilities been constructed as the first step in land
Yes
Minor silt fence repais needed.
33
disturbance activities? (9VAC 25-840-40.4) (CGP Part 11 A.2(c)) (CGP II
E(1-2)) (9VAC25-870-54.B)
Have earthen structures been stabilized immediately after installation?
Yes
34
(9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.6)
Are sediment traps and basins installed in accordance with MS-6 and the
Yes
Repair needed at SB being utilized from phase one.
35
approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II
Dewatering device is broken
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Are finished cut and fill slopes adequately stabilized to prevent or correct
Yes
Great job in stabilized areas
36
excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1-
2)) (9VAC25-870-54.B)
Is concentrated runoff down cut or fill slopes contained in an adequate
Yes
37
permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Is adequate drainage or other protection provided for water seeps?
Yes
38
(9VAC 25-840-40.9) (CGP Part 11 A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Do all operational storm sewer inlets have adequate inlet protection?
No
Minor repairs required
39
(9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Are stormwater conveyance channels adequately stabilized with channel
Yes
40
lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c))
(CGP II E(1-2)) (9VAC25-870-54.B)
Is in -stream construction conducted using measures to minimize channel
Yes
41
damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are temporary stream crossings of non -erodible material installed where
Yes
42
applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
43
Is necessary restabilization of in -stream construction complete? (9VAC
N/A
25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B)
Are utility trench operations conducted and stabilized in accordance with
Yes
44
MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are soil and mud kept off paved or public roads to minimize the transport
Yes
45
of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
46
Have all temporary control structures that are no longer needed been
N/A
removed and disturbed soil resulting from their removal permanently
Page 3 of 4
stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are properties and waterways downstream from development adequately
47
protected from erosion, sediment and damage in accordance with the
Yes
standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840-
40.19(a-n))
48
Permanent control measures included in the SWPPP are in place?
N/A
(9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a))
POLLUTION PREVENTION PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? No
Comments/Description
Practices are in place to prevent and respond to leaks, spills, and other
releases including (i) procedures for expeditiously stopping, containing,
49
and cleaning up spills, leaks, and other releases; and (ii) procedures for
reporting leaks, spills, and other releases in accordance with Part III G?
(CGP Part II A.4.e(1))(9VAC25-870-56)
Practices are in place to prevent the discharge of spilled and leaked fuels
50
and chemicals from vehicle fueling and maintenance activities? (CGP Part II
A.4.e(2))(9VAC25-870-56)
Practices are in place to prevent the discharge of soaps, solvents,
51
detergents, and wash water from construction materials, including the
clean-up of stucco, paint, form release oils, and curing compounds? (CGP
Part II A.4.e(3))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from vehicle
52
and equipment washing, wheel wash water, and other types of washing?
(CGP Part II A.4.e(4))(9VAC25-870-56)
53
Concrete wash water is directed into a leak -proof container or leak -proof
settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from
54
storage, handling, and disposal of construction products, materials, and
wastes? (CGP Part II A.4.e(6))(9VAC25-870-56)
Practices are in place to prevent the discharge of fuels, oils, and other
55
petroleum products, hazardous or toxic wastes, and sanitary wastes?
(CGP Part II A.4.e(7)(9VAC25-870-56)
Practices are in place to minimize any other discharge from the potential
56
pollutant -generating activities not addressed above, when applicable?
(CGP Part II A.4.e(8))(9VAC25-870-56)
Page 4 of 4
Construction General Permit Site Inspection Report
Request for Correction Action
Check
Regulatory Citation/Legal
Occur.
Observation
Recommended Corrective
List #
Requirement*
Action
30
(9VAC 25-840-40.1)
Great coverage. Minimum
(9VAC25-870-54.B)
overseed recommended
(9VAC25-880-60) (CGP
Part I F.1(a)) (CGP Part
II A.5.b(1)) (CGP Part 11
A.2.c (8)) (CGP 11 E(1-2))
31
(9VAC 25-840-40.2)
Stabilize any that are not
(CGP Part 11 A.2(c))
actively working or are larger
(9VAC25-870-54.B)
then what can be worked
within any 7 day period
35
(9VAC 25-840-40.6)
Repair needed at SIB being
(CGP Part 11 A.2.c (9))
utilized from phase one.
(CGP Part 11 A.2(c))
Dewatering device is broken
(CGP 11 E(1-2))
(9VAC25-870-54.B)
36
(9VAC 25-840-40.7)
Great job in stabilized areas
(CGP Part 11 A.2(c))
(CGP 11 E(1-2))
(9VAC25-870-54.B)
39
(9VAC 25-840-40.10)
Minor repairs required
(CGP Part 11 A.2(c))
(CGP 11 E(1-2))
(9VAC25-870-54.B)
33
(9VAC 25-840-40.4)
Minor silt fence repais
(CGP Part 11 A.2(c))
needed.
(CGP 11 E(1-2))
(9VAC25-870-54.B)
Recommended 3/31/2021
Corrective Action
Deadline:
Targeted Re- 3/31/2021
Inspection Date:
Comments: Warning given to emphasize the few areas of concern, overall site is very well
maintained, continue to place topsoil and seed as areas are complete to ensure a
successful outcome of strong vegetative cover.
*Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control
Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from
Construction Activities (9VAC25-880).
Construction General Permit Site Inspection Photo Log
Photos for Item 2
Photos for Item 4
Photo Description:
Photos for Item 10
Photo Description:
Photos for Item 33
20210315_132237.jpg.jpg 545.42KB
Photo Description: Example of one incident of failing silt fence.
Photos for Item 35
20210315_131102.jpg.jpg 230.16KB
4
Photo Description: Dewatering device missing
20210315_131057.jpg.jpg 2.07MB
Photo Description: Dewatering device found, remove from basin bank and reinstall
Photos for Item 39
20210315_132127.jpg.jpg 2.25MB
4
v a
Photo Description: Example of failing inlet protection
X C-�sy
County Inspector
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
434 296-5832
Inspection Date: 3/15/2021