HomeMy WebLinkAboutSP202100007 SP Checklist 2021-03-15SPECIAL USE PERMIT CHECKLIST for
OF ALB
Jefferson Mill Hydroelectric / TMP 123-1713, -26C
After the mandatory pre -application meeting, county staff will mark this checklist appropriately so
that it is clear to the applicant the information from Section 33.4 (c) that must be submitted with
t'1RG1N�P
the official application
smc
Name or initials of
staff filling out form
Required for
Provided with
application?
Staff)
application
SECTION 33.4(c)
(County
(Applicant)
X
X
YES
NO
X
A narrative of the project proposal, including its public need or benefit;
A narrative of the proposed project's consistency with the comprehensive plan,
X
including the land use plan and the master plan for the applicable development area;
A narrative of the proposed project's impacts on public facilities and public
X
infrastructure.
X
A narrative of the proposed project's impacts on environmental features.
X
A narrative of the measures (conditions) proposed to address impacts from the proposed
project.
One or more maps showing the proposed project's regional context and existing natural
X
and manmade physical conditions;
A conceptual plan showing, as applicable:
1) the street network, including circulation within the project and connections to
X
existing and proposed or planned streets within and outside of the project;
2) typical cross -sections to show proportions, scale and streetscape/cross-
X
sections/circulation;
X
3) the general location of pedestrian and bicycle facilities;
X
4) building envelopes; existing structures
X
5) parking envelopes;
X
6) public spaces and amenities;
X
7) areas to be designated as conservation and/or preservation areas;
SPECIAL USE PERMIT CHECKLIST 04/2013 Page 1 of 2
x
8) conceptual stormwater detention facility locations; (if any)
x
9) conceptual grading; (if any)
Other special studies or documentation, if applicable, and any other information
identified as necessary by the county on the pre -application comment form.
x
Please make sure to submit two special use permit applications: a special use
permit for "hydroelectric power generation" under Section 10.2.2 and a special
use permit for "hydroelectric power generation" under Section 30.3.11.
• Review and respond as necessary to the special regulations outlined in Section 5.1.26 —
Hydroelectric power generation.
• Please pay careful attention to the section of the SP application form on getting appropriate
signatures from owners and applicants
• Conceptual plan should show: limits of disturbance; areas of vegetation removal; all new
infrastructure, paving, equipment, structures;
• Narrative should address any changes/impacts to be made historic mill building
and dam
• Please provide design specifications/information, to the available level of detail, on
intake, outlet, generators, fish -protection systems, fish ladder/bypass
• Please provide confirmation of noise levels created by proposed equipment.
• The following information will be needed for Engineering review of the permit
applications:
o Submit a Floodplain Development Permit application and a no -rise
certificate (assuming there will be no rise) to the County. This must be
reviewed and approved before any development activities can begin
within the Floodplain Hazard Overlay District (FHOD). Additional
information about the FDP application can be found in our Design
Standards Manual.
o Provide a copy of any other permits required for this project, including USACE for
working in the stream.
o All improvements in the floodplain must meet our Construction Standards
o The floodplain development permit with all documentation should be submitted
along with the Special Use Permit request so that I can provide a recommendation
for the SP.
Please note: There are additional submittal requirements outlined on the official application for a Special Use Permit.
Read and Sign
I hereby state that, to the best of my knowledge, the official application submitted contains all information marked on
this checklist as required for application.
Signature of person completing this checklist Date
Aaron Van Duyne it,
Print Name
(973)808-1445
Daytime phone number of Signatory
SPECIAL USE PERMIT CHECKLIST 04/2013 Page 2 of 2