Loading...
HomeMy WebLinkAboutSDP202100008 Review Comments Final Site Plan and Comps. 2021-03-19�.� OF A(� A$ O � � `IR 1N,P ra COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902-4596 Memorandum To: Justin Shimp, P.E. (justin@shimp-en ing eering com ) From: Cameron Langille — Senior Planner II Division: Planning Services Date: March 19.2021 Subject: SDP202100008 — Proffit Road Townhomes South — Final Site Plan The Planner for the Planning Services Division of the Albemarle County Department Community Development will recommend approval of the plan referred to above when the following items have been satisfactorily addressed. (The following comments are those that have been identified at this time. Additional comments or conditions may be added or eliminated based on further review.) [Each comment is preceded by the applicable reference to the Albemarle County Code.] Applicable Comments from Initial Site Plan Action Letter (December 19, 2019): [32.5.2a] The front maximum setback is listed incorrectly on the cover sheet. The maximum front setback for R15 is 25 feet. Revise. First submittal: Comment addressed. 2. [32.5.2a] List the building separation requirement of 10 feet. First submittal: Comment addressed. 3. [32.5.2b] The Land Use schedule needs a number of revisions: a. The open space listed on one location states 51,717sf, then is listed as 7,000sf below. Open space has a definition and it's unclear if there are elements being counted as open space that are permitted as open space under the definition. First submittal: Comment not fully addressed. The Cover Sheet states that 51, 717 sq. ft. of open space are provided. However, Sheet C5 does not identify the square footage/acreage of open space areas. There are 7,400 sq. ft. of recreation area identified (including the tot lot) along Private Road A. But the open space area adjacent to Lot 40 does not list an acreage. Please add the acreage of that open space area to the callout. It does not appear that the open space area adjacent to Lot 40 plus the 7,400 so. ft. recreation area will equal 51,717 so. ft. Please clearly label and identify all land within the project that is open space on Sheet C5. b. The percentages and square feet calculations don't seem to be correct. Double check the math. The amounts provided do not seem to add up. First submittal: Comment not fully addressed. The Cover Sheet states that 7,000 sq. ft. of recreation area are provided, but Sheet C5 shows 7.400 so. ft. including the 2.000 so. ft. tot lot. Please revise labels and calculations as necessary. 4. [32.5.2b] The number of parking spaces listed does not meet the requirements of the ordinance. 2.25 spaces are required for each unit, which equals 90 total required spaces. Revise to meet the requirements. First submittal: Comment not fully addressed. The parking schedule on Sheet 1 lists the parking standard requirements for multifamily units. However, these are attached single-family units. Please update the require parking calculation so that it states the correct use "attached single family dwellings." Furthermore, the applicant comment response letter states that some units will have garages to meet the minimum parking requirements. Staff cannot approve the final site plan unless the garaee units are identified. If garages won't be provided, then each driveway must meet the dimensions required for parking spaces. 9' x 18.' These dimensions need to be shown on the driveways on individual lots to ensure that 90 total parking spaces are provided. 5. [32.5.2n] Label the area between the emergency access and the main entrance. Will this be open space? First submittal: Comment stands. If this area will be counted toward open space, please clearly delineate the boundaries of the open space area, and show the emergency access easement within it. State a sq. ft. or acreage figure in the label/callout for this open space area. See comment #3 above for more information. 6. [32.5.2n] Sidewalk connections are needed from the public sidewalks to the front of the units for pedestrian access. First submittal: Comment addressed. [32.5.2n] A sidewalk connection is needed to connect the sidewalks from Private Road A to the sidewalks on Private Road C. There is only a landscape strip and pedestrian access is needed. First submittal: CG12 is now provided, but please line up the sidewalk and ramp on the south side of Road C with the sidewalk and ramp on the east side of Road A. Currently, the Road C ramp is in the middle of the intersection. There appears to be adequate space to move it to the side lot line of Lot 22 so that the ramps are aligned. 8. [32.5.2n] Will ramps be provided for the comers of the blocks on the sidewalks for ADA access? Show ramps. First submittal: Comment not fully addressed. Please show a ramp at the north end of the sidewalk on the east side of Road A at the intersection with Road B. 9. [32.5.2n] Label the materials for the sidewalks and paths. First submittal: Comment addressed. 10. Will lighting be provided? If so, a lighting plan that meets the requirements of the ordinance needs to be provided with the final site plan. First submittal: Comment addressed. 11. [32.5.2n] If the tot lot will contain the equipment required in the ordinance provide a note on the plan that states that tot lot equipment will be provided in accordance with 4.16. First submittal: Comment addressed. 12. Easements will be required for sidewalk and planting strips that are contained in the lots and not within the right of way. First submittal: See comment #13 below. New Comments Final Site Plan: 13. [ZMA201800019] Alley A behind lots 32-40 has been removed. However, this alley was shown on the approved ZMA concept plan and the approved initial site plan. Why was the alley removed? 14. [32.7.9.5 (d)] All street trees must be located within the street ROW. Currently, the trees along Road B for lots 1-15 are within the parcels. Street trees at lots 17, 20, 32, and 40 are also within the lots. Relocate these trees so they are within the street. 15. [General Comment] Prior to final site plan approval, an Easement Plat Application must be submitted, review, approved, and recorded. Please address the following related to easements: a. [ZMA201800019] Access easements are required to be platted and recorded prior to approval of the final site plan. Proffer #3 requires access easements to be made to TMPs 32-29D and 46B4-5A. These should be provided at the end of Road C where adjoining both properties. Once the easement plat is approved and recorded, show the access easements on the site plan with dimensions, and state the recorded instrument number in the easement labels. b. [32.6.2 (d)] All new ACSA water and sewer easements must be shown on the easement plat and recorded. Once the plat is recorded, update all water and sewer easements so that they state the dimensions and recorded instrument number. c. [32.6.2 (e)] All stormwater and drainage easement must be shown on the easement plat and recorded. Once the plat is recorded, update easement labels so they state the dimensions of the easements, identify whether they are public or private, and state the recorded instrument number. d. Any offsite construction easements will need to be shown on the easement plat. The final site plan will need to label all offsite construction easements prior to approval. See Engineering comments for further information. e. Update the source of title on the Cover sheet so that it states the recorded plat instrument, and any deeds of easements that are recorded separately from the actual easement plat. 16. [32.6.2 (e)] Prior to final site plan approval, WPO202000017 must be approved. See Engineering comments for additional information. 17. [32.7.2] Prior to final site plan approval, a Road Plan Application must be submitted, reviewed, and approved. All comments from Planning, Engineering, Fire Rescue, and VDOT must be addressed related to street improvements and design. 18. [General Comment] Please be aware that proffer #1 of ZMA2018-19 requires the right-of-way dedication along Proffit Road to occur at the time of the first final subdivision plat for this project. Please contact Cameron Langille at the Department of Community Development at blanig lle&albemarle.org or 296-5832 ext. 3432 for further information. Comments from Other Reviewers: Albemarle County Engineering Services (Engineer) — David James, diames2(c�r�albemarle.org — Requested changes, see attached. Albemarle County Information Services (E911) — Elise Kiewra, ekiewrakalbemarle.org — Requested changes, see attached. Albemarle County Architectural Review Board (ARB) — Margaret Maliszewski, mmaliszewski@albemarle.org — No objection, see attached. Albemarle County Building Inspections — Betty Slough, bslouglh@albemarle.org = No objection, see attached. Albemarle County Department of Fire Rescue — Howard Lagomarsino, hlaeomarsino@albemarle.org — Requested changes, see attached. Albemarle County Service Authority — Richard Nelson, melson(2serviceauthority.org — Requested changes, see attached. Virginia Department of Transportation — Max Greene — max. rg eenekvdot.vir ig nia.gov — Requested changes, see attached. SDP202100008 - PROFFIT ROAD TOWNHOMES SOUTH — FINAL Engineering comments (David James): 1. WP0202000017 for this project will need to be approved prior to FSP approval. 2. Show offsite improvement/construction areas in an easement. 3. Sheet 5 (etc.) — a. Show road stations at 50' (min). b. Provide 2' (min) clear zone back of curb before 5' sidewalks along road. [VDOT, Appx. B] c. Provide 7" (min) thick sidewalk near emergency access entrance. Buffer Spore W_ .5 ft. 3 ft rMh 6 ftmin.w/frees 3 ftWn. Plant line i 7 I& mia next to roll top curb 4 In min. elsewhere i i . ''•;sld9rWkl•�' (Caryaded svbyvedel - - - If the a Illy space is paved.consfructlon stall be on compacted subgrade and fta Mckness shall notch that of the sidewalk, towever,tta area will rut be considered part of the mMlmum wldth reipllred for sidewalk. If trees are planed In paved pedestrian areas.11W Stoll be planted In free wells mat lxlude a plarfty graMapproved by the District AdMldslrohr's Deslgnae. HowaW.the width of sldewalk pass/ng the free well stall be at least 4 feet In widfll FIGURE 6 — DETAIL BACK OF CURBS d. Label angle of intersections. Angle appear to be less than 80 here. I I 1 FIE 5355 1 $L o -- VEFLI If3 e. Streets and alleys must have temporary turnarounds. [14-410 C] f. Provide cul-de-sac design. T-type turnarounds are discontinued. [ACDSM, p.201 g. Provide minimum 30' R/W access for the roads. h. Confirm ADA requirements for parking & access are met. Show dumpster pad(s) & details. [18-4.12.19] 4. Sheet 10 —Show ex. san crossing separation between A9 & A9A and A9 & A8. 5. Sheet 11—Show station where streets intersect. 6. Sheet 12 —Tree near Al2 will need to be moved outside drainage easement. 7. Sheet 15 — Provide minimum 2.5" of BM-25. [VDOT Pavement Design Guide, Apx. III] 8. Easement plat recordation required prior to FSP approval. APPLICATION# County of Albemarle Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902 PLAN REVIEW COMMENTS - E911 SDP202100008 TMP: 03200000003500 DATE: 2/8/2021 FROM: Elise Kiewra ekiewra(o)albemarle.org Geographic Data Services (GDS) htti)s://www.albemarle.org/ (434) 296-5832 ext. 3030 Three (3) road names total will be required, one each for Road A, Road B, and Road C. This site will require a three (3) new private road names, once each for for Road "A", Road "B", and Road "C". Per Sec. 7-200-B of the County's Road Naming and Property Numbering Ordinance (Page 2 of PDF). "It is intended by this article that all roads within the county which serve or are designed to serve three (3) or more dwelling units or business structures shall be named." We recommend providing three (3) candidate names for each road to our office for review, in case your first choices are not acceptable. A PDF version of the Ordinance and Manual can be found here: https://(iisweb.albemarle.org/aisdata/Road Naming and Property Numbering Ordinanc e and Manual.pdf Please consult the County's Road Name Index to check your road names prior to submittal. The Index can be found here: https://Ifweb.albemarle.or(i/Forms/RoadNameIndex Parcel and mapping information can be found here: https://(iisweb.albemarle.org/aov 51/Viewer.aspxx If you should have any questions, please do not hesitate to contact our office. Review Comments for SDP202100008 Final Site Development Plan Project Name: PROFFIT ROAD TOWNHOMES SOUTH - FINAL- DIGITAL Date Completed:) Tuesday, January 26, l Depanment/DivisioNAgency: Review Status: Reviewer: Margaret Maliszewski CDD ARB [No Objection Pager County of Albemarle Printed On: 03/19/2021 Review Comments for SDP202100008 Final Site Development Plan Project Name: PROFFIT ROAD TOWNHOMES SOUTH - FINAL- DIGITAL Date Completed:) Monday, February 15, 2021 Department/DivisioNAgency: Review Status: Reviewer: tly Slough CDD Insoections [No Objection Page: 1� County of Albemarle Printed On: 03/19/2021 Review Comments for SDP202100008 Final Site Development Plan Project Name: PROFFIT ROAD TOWNHOMES SOUTH - FINAL- DIGITAL Date Completed: Tuesday, February1 , 2021 Department/DivisiorJAgency: Review Status: Reviewer: Howard Lagomarsino Fire Rescue Requested Changes Pager County of Albemarle Printed On: 33/1912 221 Cameron Langille From: Richard Nelson <rnelson@serviceauthority.org> Sent: Thursday, March 18, 2021 2:51 PM To: Keane Rucker Cc: Cameron Langille Subject: Profit Road Townhome South Attachments: SDP202100008 Plan - Other (not approved) 2021-01-22.pdf CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open attachments unless you are sure the content is safe. Hey Keane, Below are comments for Proffit Road TH South. I have included a PDF markup of my comments. C1— Include updated ACSA General Conditions https:Hserviceauthority.org/wp- content/u oloads/2019/09/G EN E RALWATE RSEW ERCON D ITI ONS062719-1. odf C6 — Callout bends and fittings. Move meters closer together to provide more separation from edge of driveways typ Add gate valves as shown on PDF. Private Road B water main can be 6" diameter. The west side of Private Road C water main should be 4" diameter. The west side of Private Road C water main should be 6" diameter. Add blow off assemblies at the ends of Private Road B and C. C10— Include water main profile. C12 — Ensure the tree along Proffit Road is 10' away from the sewer main going to the TH North site. There is a tree proposed on top of the sewer lateral serving Lot 8. Please submit 3 copies of the revised plan set and water/sewer data sheets for review. Thanks, Richard Nelson Civil Engineer Albemarle County Service Authority 168 Spotnap Road Charlottesville, Virginia 22911 (434) 977-4511 (Z) COMMONWEALTH of VIRGINIA DEPARTMENT OF TRANSPORTATION Stephen C. Brich, P.E. 1401 East Broad Street (804) 786-2701 Commissioner Richmond, Virginia 23219 Fax: (804) 786,2940 February 2, 2021 Cameron Langille County of Albemarle Department of Community Development 401 McIntire Road Charlottesville, VA 22902 Re: SDP-2021-00008 — Proffit Road Townhomes South Dear Mr. Langille: The Department of Transportation, Charlottesville Residency Transportation and Land Use Section, has reviewed the above referenced Proffit Road Townhomes South, as submitted by Shimp Engineering, dated January 22, 2021 and find the following: 1) Plan appears to show eye location 14.5 feet from centerline of Rte. 649. Please label EP for verification. Sight lines location of eye do not appear to be per RDM F-40 Intersection Sight Distance detail and table 2-5 and RDM B(1)19 Sight Distance. Eye location will be a minimum 14.5 feet from the edge of travel lane. 2) Mill and overlay is required for the entire length of work plus 2' either side of the proposed work for the full adjacent lane width. Please show mill and overlay on plans in accordance with WP-2. Show limits of mill and overlay to adjacent travel lane. Also, please add the WP-2 detail to the plans. 3) Please label the CG-12 locations. 4) Entrance design should be in accord with RDM F-108 — Commercial entrance design along highway with shoulders. 5) Provide turn lane warrants for Route 649. To include the development on the North side of Proffit Road in the calculations. 6) Note that the final plan must show conformance with the VDOT Road Design Manual Appendices B(1) and F, as well as any other applicable standards, regulations or other requirements. 7) Due to the level of items noted in this review, these comments may not be exhaustive. 8) Please provide a comment response letter with each submission after the initial. VirginiaDOT.org WE KEEP VIRGINIA MOVING A VDOT Land Use Permit will be required prior to any work within the right of way. The owner/developer must contact the Charlottesville Residency land Use Section at (434) 422-9399 for information pertaining to this process. If you have further questions please contact Max Greene at (434) 422-9894. Sincerely, Adam J. Moore, P.E. Area Land Use Engineer Charlottesville Residency