HomeMy WebLinkAboutSUB201700117 Bond Reduction 2021-03-23COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, North Wing
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
Dear Mr. Joe Simpson,
Date:3/23/21
We received your road bond inspection request with fees paid forth e SUB201700117 BrookhiII project. After
review and inspection, the bond can be reduced from $1,254,440.00to $881,640.00. Please see the attached
checklist for explanation.
Below are links to Albemarle County procedures for public road acceptance:
https://www.albemarle.org/home/showdocument?id=208
https://www.albemarle.orq/home/showdocument?id=204
https://www.albemarle.org/home/showdocument?id=318
Please contact me if you have any questions.
Sincerely,
Emily Cox, PE
County of Albemarle
(434) 296-5832 ext 3565
A COUNTY OF ALBEMARLE
sl: M Department of Community Development
=� 401 McIntire Road
��amea Charlottesville, Virginia 22902
Road Bond Inspection
Bond Title: Broolchill Road Improvement Plan for State Route 643 Polo Grounds Road Stella Lane and
Archer Avenue
File Number: SUB201700117
Date of inspection: 2/26//21 Original Bond Amount: $2,938,250.00
Reviewer: Emily Cox Current Bond Amount: $1,254,440.00
Phone: (434) 296-5832 Updated Bond Amount: $881,640.00
Your bond inspection request has been processed. This list contains an update on the items received and
approved.
Received Approved
Y
N Y
N
N/A vDoT
■
❑ Completed inspection request and fee ■
❑
❑
❑
■
❑ As -built plan, updated, sealed to current date, per As -built policy ❑
■
❑
❑
■
❑ Copies of recorded plats for right-of-way, easements ■
❑
❑
❑
■
❑ VDOT approval AM-4.3, or partial completion via punch]ist ❑
■
❑
❑
■
❑ Letter from P.E. certifying improvements are built to plan ❑
■
❑
❑
❑
■ Current certification form completed by owner/developer ❑
■
❑
❑
■
❑ CBR test reports for each road ■
❑
❑
❑
■
❑ Stone depth and material inspection reports (or core tests) ■
❑
❑
❑
■
❑ Pavement depth and material inspection reports (or core tests) ❑
■
❑
❑
■
❑ Compaction test reports for fill areas under road ■
❑
❑
❑
■
❑ Pipe trench inspection reports ■
❑
❑
❑
■
❑ Pipe interior inspections reports and video ■
❑
❑
❑
■
❑ Concrete test reports for structural concrete, curbing, aprons, etc. ■
❑
❑
❑
■
❑ Structural inspection reports for any bridges or box culverts ■
❑
❑
❑
■
❑ County road name signs and posts, or a sign agreement for alt. posts ■
❑
❑
To
achieve full bond release, will need the following:
1.
Updated certification letter from a PE.
2.
VDOT road acceptance.
3.
Certification form from owner/developer.
4.
Updated As-builts for final condition or letter that nothing has changed since the as-builts
dated 5/15/2020.
5.
Any remaining reports for surface/top coat, etc. No surface mix testing was provided for Archer and Stella.
Please note that surface coat has not been reduced since construction vehicles are still traversing the area
and reports were not sent.
6.
On -site inspection by county engineering, which may result in requested changes to fix
deficiencies
before
final bond release.
7.
Address drainage issue at entrance of Stella near Route 29 as discussed on site visit.