HomeMy WebLinkAboutSUB201700117 Bond Reduction 2021-03-23 (2)COMMONWEALTH of VIRGINIA
Stephen C Brich, P.E.
Commissioner
Date: 2/26/2021
Developer:
Contact:
PRE -FINAL INSPECTION
General Notes:
DEPARTMENT OF TRANSPORTATION
1601 Orange Road
Culpeper, Virginia 22701
Subdivision: Brookhill
County: Albemarle
Attendance: Emily Cox, Doug McAvoy,
Ryan Tinder, Joe Simpson, Tucker Lloyd,
❑ Sweep the road of loose stones and debris prior to final inspection. Remove all trash and
unnecessary erosion control devices. Remove all advertising signs and construction
mailboxes.
❑ All reconstructed, repaired, and bare/denuded areas within right -of- way have been
seeded & stabilized. Fill in behind Curb
❑ Mow all areas within the right-of-way including all drainage easements. Cut back all
brush and trees within drainage easement areas.
®Complete All post larger than 4"x4" shall be drilled with a hole configuration equivalent to VDOT
standard 602.3.
❑ Grade all shoulders and ditch lines to the approved plan cross section.
- Ditch line at entrance holding water. Investigate and remediate
❑ Inlet and outlets of all culverts are to be graded and cleared of debris to provide positive
drainage.
- Clean debris from all DI's remove any unnecessary inlet protection. Visually
inspect pipe to ensure no construction debris has entered the pipes.
❑ Inlet and outlets have ladders and invert shaping per design standard. Lifting eyes
patched and all brick areas parged.
- These should be inspected, any issues should be remediated. All manholes
will be opened and inspected during the final inspection.
® Complete All bent or damaged culverts to be repaired or replaced.
❑ Utility In -Place -Permits and Quit claims of any companies with facilities in the right of
way. Contact the utility companies who will complete and submit forms to VDOT.
Recommend requesting copies for your files.
• Have: Century Telephone, Ting, Dominion
• Don't Have: Charlottesville Gas, ACSA
® Complete Ensure all valves and manholes are flush with the grade.
® Complete A video camera inspection is required for all storm sewers and culverts that are deemed
inaccessible to VDOT inspections and are to be accepted into VDOT's maintenance
program and ownership. The video inspection shall be conducted in accordance with
VDOT's video camera inspection procedure. Accepted based on VDOT review of
submitted materials and letter provided by Roudabush, Gale, & Associates.
❑ Under Drain Report
- I don't see this in the binder. Were any UD's or CD's installed/called for.
® Received Recorded subdivision plat for this section: two normal size paper copies and digital copy.
❑ As -built Plan: two normal size paper copies and digital copy.
- Need approved As -built from the County
❑ All agreements must be finalized and copies submitted prior to Final Acceptance:
- Landscape Maintenance Agreement and LUP
❑ All stop signs require 16" above for state route markers.
❑ Signing and Pavement Markers
- Replace all damaged signs
- Additional "No Parking" signs will be needed to make the no parking zone
clear
- Sign foundations should be < 4", STP-1
❑ CG-3 Curb in median should have a reveal <1". Curb reveal is not consistent along the
median. Pleas provide additional information about this issue.
❑ Reverse curb north of Roundabout will push water into the roadway and hold water over
top of the joint instead of in the gutter. Additionally, it appears there will be drainage
issues in this location with the commercial entrance pushing water into the center of the
intersection. See CG-11 Standard for location of flow line across a Commercial
Entrances. There is currently no DI to accept this drainage. Please investigate this area
and provide information regarding this concern. Until this concern is addressed this
segment will not be considered for acceptance.
El
■�
WE KEEP VIRGINIA MOVING
Material Testina:
All testing must be conducted by VDOT certified technician under the supervision of a Professional
Engineer licensed in the state of Virginia, per Land Development Inspection Manual.
® All density test for fills and trenches
® Subgrade CBR's
® Pavement Design to confirm originally planned
® Subgrade Proofroll and Density
❑ Underdrain and Cross Drain inspection report
® Stone Base Roller Patterns
® Stone Depth Checks and Density tests
® Asphalt inspection, thickness, and testing reports - base BM / intermediate IM
❑ Asphalt inspection, thickness, and testing reports - surface SM
Remarks:
1.
2.
3.
4.