NOTICE TO COMPLY
Hand delivered
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
434 296-5832
Project: WP0201400087
The Lofts at Meadowcreek
Operator/Contractor: PINNACLE CONSTRUCTION & DEVELOPMENT CORP.
BLUESTONE LAND LLC
Issued Date: 3/24/2021
Under section § 17-900 of the Albemarle County Code, this is your NOTICE TO COMPLY with
the requirements of the Land Disturbance Permit (or Agreement in Lieu of a Plan) for the
referenced project and to immediately take corrective measures to address erosion and sediment
control deficiencies on this property. This Notice to Comply is being issued because of the
following deficiencies:
Deficiency: Not onsite at time of visit
Corrective Action: Have on site and available as required by program
Deficiency: Could not verify at time of visit
Corrective Action: See note item 4
Deficiency: Could not verify at time of visit
Corrective Action: See note item 4
Deficiency: Could not verify at time of visit
Corrective Action: See note item 4
Deficiency: Could not verify at time of visit
Corrective Action: See note item 4
Deficiency: Not posted at time of visit
Corrective Action: Postings must remain on site and easily accessible until permit termination
Deficiency: Not posted at time of visit
Corrective Action: See note item 2
Deficiency: Fertilize and overseed as needed in common areas
Corrective Action:
Deficiency: Fertilize and stabilize as needed
Corrective Action:
Deficiency: Silt fence remaining in bio filter
Corrective Action: Remove as required
Deficiency: Failing bio filter
Corrective Action: Remove existing and replace with new bio media, stone, underdrain as
needed to repair failed BMP.
Unless subsequently amended in writing by this office, it is expected all of these corrective
measures will be completed by.
Re -inspection of this notice to verify corrective measures will incur a $150 for land disturbing under
VESCP and single-family dwelling units (§ 17-207) or a $250 fee for land disturbing under VSMP (§ 17-
208). Failure to take effective corrective measures will result in a Stop Work Order upon re -inspection.
County Inspector Name: Geoff Elsie
County Inspector Phone Number: (434) 296-5832
OF Al.,& Inspection Result: Notice to Comply
r
L�eo��P
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
VSMP/VESCP PERMIT SITE INSPECTION REPORT
Project Name:
The Lofts at Meadowcreek
Project/WPO Number:
WP0201400087
TMP:
061A0000001500
DEQ Permit Number (if
applicable):
VAR10E747
Project Operator:
PINNACLE CONSTRUCTION &
DEVELOPMENT CORP.
Operator Telephone #:
(434) 979-2000
Project Contact:
BLUESTONE LAND LLC
Contact Telephone #:
(434) 979-2900
Contact E-Mail:
wpark@pinnacleconstructionva.com
Qualified Personnel (QP):
VESS EXCAVATING, LTD.
Inspector:
Geoff Elsie
Weather (Wet/Dry/Rain):
Disturbed Acreage:
2.48
Inspection Date & Time:
3/23/2021
Single -Family:
Stage of Construction: Final Stabilization
Re -Inspection: No
COVERAGE & POSTING REQUIREMENTS
Compliant?
Reviewed during re -inspection? Yes
Comments/Description
1
Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A)
Yes
(9VAC25-870-310)(Alb. Co. Code §17-300, 17-302)
2
A copy of the notice of coverage letter is posted conspicuously near the
No
Not posted at time of visit
main entrance of the construction activity? (CGP Part II.C)
Notice of the location of the SWPPP is posted near the site's entrance, if
No
Not posted at time of visit
3
applicable, and information for public access is provided? (9VAC25-870-
54.G)(CGP Part II D.2 & 3)
SWPPP AVAILABILITY AND CONTENTS
Compliant?
Reviewed during re -inspection? Yes
Comments/Description
4
The SWPPP is on -site or made available during the inspection? (CGP
No
Part II D.1 & 2)(9VAC25-870-54.G)
5
The SWPPP contains a signed copy of the registration statement?
Yes
(CGP Part II A.1.a)
6
The SWPPP includes, upon receipt, a copy of the notice of coverage
No
letter and the CGP? (CGP Part II A.1.b & c)
The SWPPP includes a narrative description of the nature of the
Yes
7
construction activity, including the function of the project? (CGP Part II
A.1 A)
The SWPPP includes a legible site plan identifying all appropriate
No
8
measures and that includes the locations of support activities and the
onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7))
Page 1 of 4
9
The SWPPP contains the name, phone number and qualifications of
No
"Qualified Personnel" conducting inspections? (CGP Part II A.6)
10
The SWPPP contains an approved erosion and sediment control plan?
Yes
(9VAC25-870-54.B)(CGP Part II.A.2)
The SWPPP contains an approved stormwater management plan or an
11
existing construction site has a stormwater management plan that
Yes
ensures compliance with the water quality and quantity requirements?
(9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ II.0 ❑
12
The SWPPP contains an adequate pollution prevention plan? (9VAC25-
Yes
870-54.D)(CGP Part II.A.4)
The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of
Yes
13
concern, exceptional waters and the additional controls measures
applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b))
14
Delegation of Authority is provided and signed in accordance with Part III
No
K? (CGP Part 11 A.7)
15
The SWPPP is signed and dated in accordance with Part III K? (CGP Part
Yes
11 A.8)
SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES
Compliant?
Reviewed during inspection? No
Comments/Description
Is the SWPPP being amended whenever there is a change in the design,
16
construction, operation, or maintenance that has a significant effect on the
discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870-
54.G)
Has the SWPPP been amended if inspections or investigations by the
17
operator's qualified personnel, or by local, state or federal officials find that
existing control measures are ineffective in minimizing pollutants in
discharges? (CGP Part II B(2))(9VAC25-870-54.G)
18
Contractor(s) that will implement and maintain each control measure are
identified? (CGP Part 11 B(3))(9VAC25-870-54.G)
Have there been updates to the SWPPP when any modifications to its
implementation have occurred, including a record of dates when major
19
grading activities occur, construction activities temporarily or permanently
cease on a portion of the site or stabilization measures are initiated? (CGP
Part 11 B.4(a))(9VAC25-870-54.G)
20
Is there documentation in the SWPPP of replaced or modified controls?
(CGP Part 11 B.4(b))(9VAC25-870-54.G)
21
Is the SWPPP updated to indicate areas that have reached final
stabilization? (CGP Part 11 B.4(c))(9VAC25-870-54.G)
Is the SWPPP updated to indicate properties that are no longer under the
22
legal control of the operator and the dates on which the operator no longer
had legal control over each property? (CGP Part II B.4(d))(9VAC25-870-
54.G)
Does the SWPPP identify the date of any prohibited discharges, the
23
volume released, actions taken to minimize the impact of the release and
measures taken to prevent the recurrence of any prohibited discharge?
(CGP Part 11 B.4(e-f)) (9VAC25-870-54.G)
24
mendments, modifications, or updates to the SWPPP are signed in
accordance with Part III K? (CGP Part II B(5))(9VAC25-870-54.G)
INSPECTIONS AND CORRECTIVE ACTIONS
Compliant?
Reviewed during inspection? No
Comments/Description
Inspections required by the SWPPP are conducted at the required
25
frequency, including a modified frequency for impaired water(s), approved
TMDL(s), and exceptional waters when applicable? (CGP Part II F (2))
(CGP Part II A.5.b.3)
26
Inspection reports are completed and signed in accordance with CGP
Part 11 F (3-4)? (CGP Part 11 F (3-4))
Page 2 of 4
27
Corrective actions are taken consistent with the requirements of the
CGP? (CGP Part II G(1-2))
ESC AND SWM PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? Yes
Comments/Description
28
Have stream buffers and steep slopes been protected as shown on the
Yes
plan?
Sequencing of the project is implemented in accordance with the
Yes
29
approved erosion and sediment control plan and stormwater management
plans? (9VAC25-870-54.B and C)
Have all denuded areas requiring temporary or permanent stabilization
been stabilized, and have stabilization requirements for impaired waters,
30
approved TMDL(s), pollutants of concern and exceptional waters, when
Yes
applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25-
880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8))
(CGP II E(1-2))
Are soil stockpiles adequately stabilized with seeding and/or protected
NIA
31
with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II
A.2(c)) (9VAC25-870-54.B)
A permanent vegetative cover has been established that is uniform,
Fertilize and overseed as needed in common areas
32
mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3)
Yes
(CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Have sediment trapping facilities been constructed as the first step in land
NIA
33
disturbance activities? (9VAC 25-840-40.4) (CGP Part 11 A.2(c)) (CGP II
E(1-2)) (9VAC25-870-54.B)
Have earthen structures been stabilized immediately after installation?
N/A
34
(9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.6)
Are sediment traps and basins installed in accordance with MS-6 and the
35
approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Are finished cut and fill slopes adequately stabilized to prevent or correct
No
Fertilize and stabilize as needed
36
excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1-
2)) (9VAC25-870-54.B)
Is concentrated runoff down cut or fill slopes contained in an adequate
N/A
37
permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Is adequate drainage or other protection provided for water seeps?
N/A
38
(9VAC 25-840-40.9) (CGP Part 11 A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Do all operational storm sewer inlets have adequate inlet protection?
N/A
39
(9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Are stormwater conveyance channels adequately stabilized with channel
Yes
40
lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c))
(CGP II E(1-2)) (9VAC25-870-54.B)
Is in -stream construction conducted using measures to minimize channel
N/A
41
damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are temporary stream crossings of non -erodible material installed where
N/A
42
applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
43
Is necessary restabilization of in -stream construction complete? (9VAC
N/A
25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B)
Are utility trench operations conducted and stabilized in accordance with
N/A
44
MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are soil and mud kept off paved or public roads to minimize the transport
Yes
45
of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
46
Have all temporary control structures that are no longer needed been
No
Silt fence remaining in bio filter
removed and disturbed soil resulting from their removal permanently
Page 3 of 4
stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B )
Are properties and waterways downstream from development adequately
47
protected from erosion, sediment and damage in accordance with the
N/A
standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840-
40.19(a-n))
48
Permanent control measures included in the SWPPP are in place?
No
Failing bio filter
(9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a))
POLLUTION PREVENTION PLAN IMPLEMENTATION
Compliant?
Reviewed during inspection? No
Comments/Description
Practices are in place to prevent and respond to leaks, spills, and other
releases including (i) procedures for expeditiously stopping, containing,
49
and cleaning up spills, leaks, and other releases; and (ii) procedures for
reporting leaks, spills, and other releases in accordance with Part III G?
(CGP Part II A.4.e(1))(9VAC25-870-56)
Practices are in place to prevent the discharge of spilled and leaked fuels
50
and chemicals from vehicle fueling and maintenance activities? (CGP Part II
A.4.e(2))(9VAC25-870-56)
Practices are in place to prevent the discharge of soaps, solvents,
51
detergents, and wash water from construction materials, including the
clean-up of stucco, paint, form release oils, and curing compounds? (CGP
Part II A.4.e(3))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from vehicle
52
and equipment washing, wheel wash water, and other types of washing?
(CGP Part II A.4.e(4))(9VAC25-870-56)
53
Concrete wash water is directed into a leak -proof container or leak -proof
settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from
54
storage, handling, and disposal of construction products, materials, and
wastes? (CGP Part II A.4.e(6))(9VAC25-870-56)
Practices are in place to prevent the discharge of fuels, oils, and other
55
petroleum products, hazardous or toxic wastes, and sanitary wastes?
(CGP Part II A.4.e(7)(9VAC25-870-56)
Practices are in place to minimize any other discharge from the potential
56
pollutant -generating activities not addressed above, when applicable?
(CGP Part II A.4.e(8))(9VAC25-870-56)
Page 4 of 4
Construction General Permit Site Inspection Report
Request for Correction Action
Check
Regulatory Citation/Legal
Occur.
Observation
Recommended Corrective
List #
Requirement*
Action
4
(CGP Part II D.1 &
Not onsite at time of visit
Have on site and available as
2)(9VAC25-870-54.G)
required by program
6
(CGP Part II A.1.b &
Could not verify at time of visit
See note item 4
c)
8
(CGP Part 11 A.1.e(1-7))
Could not verify at time of visit
See note item 4
9
(CGP Part 11 A.6)
Could not verify at time of visit
See note item 4
14
(CGP Part 11 A.7)
Could not verify at time of visit
See note item 4
2
(CGP Part II.C)
Not posted at time of visit
Postings must remain on site
and easily accessible until
permit termination
3
(9VAC25-870-54.G)
Not posted at time of visit
See note item 2
(CGP Part 11 D.2 &
3)
32
(9VAC 25-840-40.3)
Fertilize and overseed as
(CGP Part 11 A.2(c))
needed in common areas
(CGP 11 E(1-2))
(9VAC25-870-54. B )
36
(9VAC 25-840-40.7)
Fertilize and stabilize as
(CGP Part 11 A.2(c))
needed
(CGP 11 E(1-2))
(9VAC25-870-54.B)
46
(9VAC 25-840-40.18)
Silt fence remaining in bio
Remove as required
(CGP Part 11 A.2(c))
filter
(CGP 11 E(1-2))
(9VAC25-870-54.B)
48
(9VAC25-870-54.C)
Failing bio filter
Remove existing and replace
(9VAC25-880-60) (CGP
with new bio media, stone,
Part 11 F.1(a))
underdrain as needed to
repair failed BMP.
Recommended 4/2/2021
Corrective Action
Deadline:
Targeted Re- 4/2/2021
Inspection Date:
Comments: Biofilter has failed, all media, plants, and stone must be removed and replaced with
new to ensure proper drainage. Filter must dewater within 48 hours of a rain event.
As BMP is currently, measure does not drain and holds water for extended periods
of time. All outfalls must be free of sediment and debris. A thought as to why the
filter has failed, if the higher clay content 2013 spec bio mix was used, rather then
the 2011 approved mix, a settle line of impervious clay may have formed. Consult
your spec sheet from supplier to confirm what specifications were used in the
manufacturing of the bio mix.
*Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control
Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from
Construction Activities (9VAC25-880).
Construction General Permit Site Inspection Photo Log
Photos for Item 2
Photos for Item 4
Photo Description:
Photos for Item 10
Photo Description:
Photos for Item 36
20210323_105202.jpg.jpg 2.14MB
3
Photo Description: Example of poor vegetative ground cover
Photos for Item 40
20210323_104927.jpg.jpg 2.76MB
Photo Description: Outlet needs sediment and debris removed
Photos for Item 46
20210323_105232.jpg.jpg 413.89KB
Photo Description: Silt fence remains in failing biofilter
Photos for Item 48
20210323_105043.jpg.jpg 2.26MB
Photo Description: Failed bio filter. Dead plants and retained water.
20210323_105232.jpg.jpg 413.89KB
Photo Description: Biofilter retaining water longer then the 48hr maximum drawdown, see water marks
up to the low flow trashrack.
x
County Inspector
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
434 296-5832
Inspection Date: 3/24/2021