HomeMy WebLinkAboutWPO202100018 Review Comments WPO VSMP 2021-04-29�r County of Albemarle
m COMMUNITY DEVELOPMENT DEPARTMENT
VSMP Permit Plan Review
Project title: Dripps-Phinney Driveway - VSMP
Project file number: WPO-202100018
Plan preparer: Connie Liou [cl@rieleyandassociates.com]
Owner or rep.: Dripps, Robin [RDD9A@virginia.edu]
Plan received date: 22 March 2021
Date of comments: 29 April 2021
Reviewer: Frank Pohl, PE
401 McIntire Road, North Wing
Charlottesville, VA 22902-4579
Telephone:434-296-5832
WWW.ALBEMARLE.ORG
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any
VSMP application by issuing a project approval or denial. This application is denied. The rationale is given
in the comments below. The VSMP application content requirements can be found in County Code
section 17-401.
A. General Comments
1. All sheets where applicable, clearly show and identify the following:
a. Plank Road (limits, name, route number, etc.)
b. Property lines, TMP, existing structure(s), address.
c. Critical slopes and stream buffer.
d. Limits of land disturbance and area (so.
2. The project area should only include parcels where land disturbance is proposed. Parcels
owned by the same owner but where land disturbance is not proposed should not be
included with this application. Please revise the cover page to show only those parcels
where disturbance is proposed.
B. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. SWPPP not received. Please provide a SWPPP.
C. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. Pollution Prevention Plan was not received. Please submit a PPP.
D. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is denied, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-
403.
Engineering Review Comments
Page 2 of 3
1. Permanent level spreaders must be sized based on the BMP clearinghouse design
specifications. Please confirm where the level spreaders are draining to (e.g. to grassed
areas or to forests?).
2. Discharge to the level spreaders should include a recessed area where the stormwater
can dissipate and spread evenly over the level spreader. I realize the flows are low, but
please provide a depressed area behind the level spreaders to ensure short circuiting
does not occur.
3. Registration Statement — confirm the total land area of development to be disturbed.
Area stated is 22.87 acres. This should only include the single parcel where the land
disturbance activity occurs.
E. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved and the reasons are provided in the comments below. The erosion
control plan content requirements can be found in County Code section 17-402.
There are several locations where SF is proposed to be installed up/down a slope. SF
should be installed along contours, please revise, replace with DDs, or propose
something else that meets VESCH standards.
F. Additional Comments unrelated to WPO review but provided for information:
1. Retaining walls require a building permit when the height exceeds 36-inches. Please
submit retaining wall applications to the Building Division.
2. VDOT permitting may be required for the driveway upgrades. Please contact VDOT for
confirmation.
The VSMP permit application and all plans may be resubmitted for approval when all comments
have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete
permit package with a completed application form or make a digital submittal though the
County website.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a
meeting to discuss this review.
Process:
After approval, erosion and sediment control and stormwater management improvements (if
applicable) must be bonded. The bonding process begins when the plan is approved, and the
applicant submits a bond estimate request form and fee to the Department of Community
Development. A plan reviewer will prepare estimate(s) and check parcel and easement
information based on the approved plans. The County's Management Analyst will prepare bond
agreement forms, which will need to be completed by the owner and submitted along with cash,
certificates, or sureties for the amounts specified. The agreements will need to be approved and
Engineering Review Comments
Page 3 of 3
signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the
correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and
recorded when applicable. The County's Management Analyst or other staff will prepare the
forms and check for ownership and signature information. The completed forms will need to be
submitted to the County, who will record the agreement.
After bonding and agreements are complete, county staff enters project information in a DEQ
database for state application processing, if a DEQ permit is required. DEQ reviews the
application information based on local VSMP authority approval. At this time, the DEQ portion
of the application fees will need to be paid directly to DEQ who will notify applicants with
instructions on how to pay fees. When DEQ approves the application, they will issue a permit
coverage letter, which must be posted at the construction site.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction
conference. Applicants must complete the request for a pre -construction conference form and
pay the remainder of the application fee. The form identifies the contractor and responsible land
disturber, and the fee remaining to be paid. This will be checked by county staff, and upon
approval, a pre -construction conference will be scheduled with the County inspector. At the pre -
construction conference, should everything proceed satisfactorily, ajoint VSMP and grading
permit will be issued by the County so that work may begin.
County forms can be found on the county website forms center under engineering;