HomeMy WebLinkAboutSDP201900062 Correspondence 2021-04-30Kevin McCollum
From: Riki Van-Niekerk <Riki@roudabush.com>
Sent: Thursday, April 29, 2021 3:12 PM
To: Kevin McCollum
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC
PROFESSIONAL OFFICES - FINAL Tax Map/Parcel #060F0000000300
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
That would be great. I can drop them off right after Sam.
One thing, I just showed my supervisor the plan and he said the "6" in the triangles should be "1" since this is the first
letter of revision. He asked that I change them all. I also put the triangle with a "1" in the boarder. I hope that is okay for
everyone?
From: Kevin McCollum <kmccollum@albemarle.org>
Sent: Thursday, April 29, 2021 2:39 PM
To: Riki Van-Niekerk <Riki@roudabush.com>
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Tax Map/Parcel #0601`0000000300
Thank you. All comments have been addressed. Please drop off 4 hard copies for approval. Also, Riki, do you know what
time you can drop them off? I'm leaving around lunchtime tomorrow and will be out of town all next week. So, if they
are dropped off in the morning I can get them signed by the time I leave. Thanks so much.
Kevin
From: Riki Van-Niekerk <Riki@roudabush.com>
Sent: Thursday, April 29, 2021 2:19 PM
To: Kevin McCollum <kmccollum@albemarle.ore>
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Tax Map/Parcel #0601`0000000300
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Kevin,
Thank you very much for highlighting that. It would be embarrassing if you knew how many engineers missed that.
Please see attached updated revised plan sheet.
I changed the red numbers to #6. Let me know if this sheet looks good and I can drop off the 4 hardcopies tomorrow
morning on my way to work.
Thanks for your help,
Riki
From: Kevin McCollum <kmccollum@albemarle.ors>
Sent: Thursday, April 29, 2021 1:54 PM
To: Riki Van-Niekerk <Riki@roudabush.com>
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Tax Map/Parcel #0601`0000000300
Hey Riki,
I was referring to the tree canopy provided in the box highlighted below. I believe this should reflect the calculation of
9,987 SF and the percentage should be updated as well. Let me know if this makes sense.
Kevin
STREET TRU REQUIREMENTS
I LARGE TREE PER 40' STREET FRONTAGE (ENTRANCE CORRIDOR-
248.5 LF OF FRONTAGE
TREES REQUIRED = (248-5/40)= 6.2 TREES REQUIRED
TREES PROVIDED = 8
I MEDIUM TREE PER 40' ST'REEI' FRONTAGE (GEORGErOWN)
79.8 LF OF FRONTAGE
TREES REQUIRED - (78.8/40)- 2 TREES REQUI
TREES PROVIDED = 2
TREE CANOPY CALCULATIONS
TOTAL SITE AREA - 1.05 AC (45,747 SF)
PRESERVATION AREA = 0.27 AC (11.648 SF)
NET SITE AREA = 0.78 AC (34,099 SF)
10% TREE CANOPY REQUIRED = 3,410 SF
TREE CANOPY PROVIDED = 7,979 SF (23.4%)
REQUIRED 5%/1 TREE PER 10 PARKING SPACES
AREA REQUIRED = 13,304 SF PARKING AREA • 5% = 885.2 SF
AREA PROVIDED = 1.164 SF (8.7%)
TREES REQUIRED - 35 SURFACE PARKING SPACES / 10- 3.5 TREES
TREES PROVIDED = 4 TREES (2-EP, 1-INN AND 1-AB)
NOTES & MINIMU
1. TREES SHOWN HEREON
PLANT LIST. SUBSTITU
DEPARTMENT OF COMMI
2. IF A SUBSTITUTION BE(
3. PLANT LIST TOTALS AEI
BIDDING.
4. TREES SHALL BE 2.5.1
PLANTED.
5- TIMING OF INSTAL[ATIO�
PLANTING SEASON FOU
OCCUPANCY WITHIN THI
8- ALL TREES TO BE PIAD
ASSOCIATION OF NURSE
THE STANDARDIZED W
NURSERYMEN'S ASSOCIA
VIRGINIA CHAPTER OF '
ROAD AND BRIDGE SPD
7. CONTRACTOR SHALL AS(
PRIOR TO COMMENCING
8. ALL PLANT MATERIAL T
PROJECT ACCEPTANCE.
OR IS UNHEALTHY AND
CONTRACTOR'S NEGLIGE
EXPENSE.
9. MAINTAINING AND REPL
IN A HEALTHY CONDITU
REPLACEMENT MATEEIAI
10. ALL SITE PLANTINGS 01
MAINTAINED AT MATURE
TREES SHALL BE PRUN
THE PLANT.
CONSERVATION AREA PLANTINGS
2A REPLANTING RATIO R r
TREES REQUIRES `- TREES REMOVED • 2 = '-'TREES
TREES PROVIDED TREED
1
d
II
5 2,50
GDi
Lert4A
From: Riki Van-Niekerk <Riki@roudabush.com>
Sent: Thursday, April 29, 2021 1:46 PM
To: Kevin McCollum <kmccollum@albemarle.ore>
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Tax Map/Parcel #0601`0000000300
9
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Good afternoon Kevin,
Thank you for your email. Could you be more specific on what number you want to be changed in your comment? The
total tree canopy calculation in the table on sheet 10 changed from 7,979 sf (approved plan) to 9.987 sf due to the
addition of 4 poplars. I apologize in advance if I am being ignorant, but I can't find the mistake.
Thank you,
Rik! van-Niekerk, EIT
Roudabush, Gale & Assoc., Inc.
Office: (434)979-8121
Direct: (434)260-6983
Mail: 435 Merchant Walk sq., Suite 300-159, Charlottesville, VA 22902
Location: 999 Second St. SE, Suite 201, Charlottesville, VA 22902
From: Kevin McCollum <kmccollum@albemarle.org>
Sent: Monday, April 26, 2021 11:12 AM
To: Riki Van-Niekerk <Riki@roudabush.com>
Subject: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL Tax
Map/Parcel#0601`0000000300
Good Morning,
Please see the attached review comments for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES -
FINAL.
There is only one minor comment to be addressed. Once you have made the applicable changes you can either send the
plans back to me for confirmation or you can just go ahead and submit four (4) hard copies of the full LOR plan set to the
Community Development Department for final approval. All you need to do is update the total tree canopy calculation
that is provided on the Landscape Plan. All other reviewers had no objection. Let me know if you have any questions.
Thanks!
Kevin McCollum
Planner, Certified Zoning Official
Community Development Department
Planning Division
Albemarle County
(434) 296-5832 ext. 3141
401 McIntire Rd, Charlottesville VA 22902
Kevin McCollum
From: Kevin McCollum
Sent: Thursday, April 29, 2021 2:39 PM
To: Riki Van-Niekerk
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC
PROFESSIONAL OFFICES - FINAL Tax Map/Parcel #060F0000000300
Attachments: SDP201900062 LOR 1 Review Comment Letter 4-29-2021.pdf
Thank you. All comments have been addressed. Please drop off 4 hard copies for approval. Also, Riki, do you know what
time you can drop them off? I'm leaving around lunchtime tomorrow and will be out of town all next week. So, if they
are dropped off in the morning I can get them signed by the time I leave. Thanks so much.
Kevin
From: Riki Van-Niekerk <Riki@roudabush.com>
Sent: Thursday, April 29, 2021 2:19 PM
To: Kevin McCollum <kmccollum@albemarle.org>
Subject: RE: Review Comments LOR#1 for SDP-2019-00062—GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Tax Map/Parcel#060F0000000300
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Kevin,
Thank you very much for highlighting that. It would be embarrassing if you knew how many engineers missed that.
Please see attached updated revised plan sheet.
I changed the red numbers to #6. Let me know if this sheet looks good and I can drop off the 4 hardcopies tomorrow
morning on my way to work.
Thanks for your help,
Riki
From: Kevin McCollum <kmccollum@albemarle.org>
Sent: Thursday, April 29, 2021 1:54 PM
To: Riki Van-Niekerk <Riki@roudabush.com>
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Tax Map/Parcel #060F0000000300
Hey Riki,
I was referring to the tree canopy provided in the box highlighted below. I believe this should reflect the calculation of
9,987 SF and the percentage should be updated as well. Let me know if this makes sense.
Kevin
STREET TRU REQUIREMENTS
I LARGE TREE PER 40' STREET FRONTAGE (ENTRANCE CORRIDOR-
248.5 LF OF FRONTAGE
TREES REQUIRED = (246-5/40)= 6.2 TREES REQUIRED
TREES PROVIDED = 6
I MEDIUM TREE PER 40' ST'REEI' FRONTAGE (GEORGErOWN)
79.8 LF OF FRONTAGE
TREES REQUIRED - (78.6/40)- 2 TREES REQUI
TREES PROVIDED = 2
TREE CANOPY CALCULATIONS
TOTAL SITE AREA - 1.06 AC (45,747 SF)
PRESERVATION AREA = 0.27 AC (11.648 SF)
NET SITE AREA = 0.78 AC (34,099 SF)
10% TREE CANOPY REQUIRED = 3,410 SF
TREE CANOPY PROVIDED = 7,979 SF (23.4%)
REQUIRED 5%/1 TREE PER 10 PARKING SPACES
AREA REQUIRED = 13,304 SF PARKING AREA • 5% = 665.2 SF
AREA PROVIDED = 1.164 SF (8.7%)
TREES REQUIRED - 35 SURFACE PARKING SPACES / 10- 3.5 TREES
TREES PROVIDED = 4 TREES (2-EP, 1-INN AND 1-AB)
NOTES & MINIMU
1. TREES SHOWN HEREON
PLANT LIST. SUBSTITU
DEPARTMENT OF COMMI
2. IF A SUBSTITUTION BE(
3. PLANT LIST TOTALS AEI
BIDDING.
4. TREES SHALL BE 2.5.1
PLANTED.
5- TIMING OF INSTAL[ATIO�
PLANTING SEASON FOU
OCCUPANCY WITHIN THI
8- ALL TREES TO BE PIAD
ASSOCIATION OF NURSE
THE STANDARDIZED W
NURSERYMEN'S ASSOCIA
VIRGINIA CHAPTER OF '
ROAD AND BRIDGE SPD
7. CONTRACTOR SHALL AS(
PRIOR TO COMMENCING
8. ALL PLANT MATERIAL T
PROJECT ACCEPTANCE.
OR IS UNHEALTHY AND
CONTRACTOR'S NEGLIGE
EXPENSE.
9. MAINTAINING AND REPL
IN A HEALTHY CONDITU
REPLACEMENT MATEEIAI
10. ALL SITE PLANTINGS 01
MAINTAINED AT MATURE
TREES SHALL BE PRUN
THE PLANT.
CONSERVATION AREA PLANTINGS
2A REPLANTING RATIO R r
TREES REQUIRES `- TREES REMOVED • 2 = '-'TREES
TREES PROVIDED TREED
1
d
II
5 2,50
GDi
Lert4A
From: Riki Van-Niekerk <Riki@roudabush.com>
Sent: Thursday, April 29, 2021 1:46 PM
To: Kevin McCollum <kmccollum@albemarle.ore>
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Tax Map/Parcel #0601`0000000300
6
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Good afternoon Kevin,
Thank you for your email. Could you be more specific on what number you want to be changed in your comment? The
total tree canopy calculation in the table on sheet 10 changed from 7,979 sf (approved plan) to 9.987 sf due to the
addition of 4 poplars. I apologize in advance if I am being ignorant, but I can't find the mistake.
Thank you,
Rik! van-Niekerk, EIT
Roudabush, Gale & Assoc., Inc.
Office: (434)979-8121
Direct: (434)260-6983
Mail: 435 Merchant Walk sq., Suite 300-159, Charlottesville, VA 22902
Location: 999 Second St. SE, Suite 201, Charlottesville, VA 22902
From: Kevin McCollum <kmccollum@albemarle.org>
Sent: Monday, April 26, 2021 11:12 AM
To: Riki Van-Niekerk <Riki@roudabush.com>
Subject: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL Tax
Map/Parcel#0601`0000000300
Good Morning,
Please see the attached review comments for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES -
FINAL.
There is only one minor comment to be addressed. Once you have made the applicable changes you can either send the
plans back to me for confirmation or you can just go ahead and submit four (4) hard copies of the full LOR plan set to the
Community Development Department for final approval. All you need to do is update the total tree canopy calculation
that is provided on the Landscape Plan. All other reviewers had no objection. Let me know if you have any questions.
Thanks!
Kevin McCollum
Planner, Certified Zoning Official
Community Development Department
Planning Division
Albemarle County
(434) 296-5832 ext. 3141
401 McIntire Rd, Charlottesville VA 22902
Kevin McCollum
From: Riki Van-Niekerk <Riki@roudabush.com>
Sent: Thursday, April 29, 2021 2:19 PM
To: Kevin McCollum
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 - GEORGETOWN HYDRAULIC
PROFESSIONAL OFFICES - FINAL Tax Map/Parcel #060F0000000300
Attachments: 19.0125 GeorgetownHydraulic-FSP-Revision 1-10-LANDSCAPE.pdf
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Kevin,
Thank you very much for highlighting that. It would be embarrassing if you knew how many engineers missed that.
Please see attached updated revised plan sheet.
I changed the red numbers to #6. Let me know if this sheet looks good and I can drop off the 4 hardcopies tomorrow
morning on my way to work.
Thanks for your help,
Riki
From: Kevin McCollum <kmccollum@albemarle.org>
Sent: Thursday, April 29, 2021 1:54 PM
To: Riki Van-Niekerk <Riki@roudabush.com>
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 - GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Tax Map/Parcel #060F0000000300
Hey Riki,
I was referring to the tree canopy provided in the box highlighted below. I believe this should reflect the calculation of
9,987 SF and the percentage should be updated as well. Let me know if this makes sense.
Kevin
=REET TREE REQUIREMENTS
1 LARGE TREE PER 40' STREET FRONTAGE (ENTRANCE CORRIDOR-
248.5 LF OF FRONTAGE
TREES REQUIRED = (248.5/40)= 6.2 TREES REQUIRED
TREES PROVIDED = 6
I MEDIUM TREE PER 40' STREET FRONTAGE (GEORGETOWN)
79.6 LF OF FRONTAGE
TREES REQUIRED - (76.6/40)- 2 TREES REQUI
TREES PROVIDED = 2
TREE CANOPY CALCULATIONS
TOTAL SITE AREA - 1.05 AC (45.747 SF)
PRESERVATION AREA - 0.27 AC (11,648 SF)
NET SITE AREA = 0,78 AC (34.099 SF)
10% TREE CANOPY REQUIRED = 3,410 SF
TREE CANOPY PROVIDED = 7,979 SF (=A%)
REQUIRED 5%/1 TREE PER 10 PARKING SPACES
AREA REQUIRED = 13.304 SF PARKING AREA • 5% = 665.2 SF
AREA PROVIDED = 1,164 SF (6.7%)
TREES REQUIRED - 35 SURFACE PARTING SPACES / 10- 3.5 TREES
TREES PROVIDED = 4 TREES (2-IP. 1-INN AND 1-AB)
CONSERVATION AREA PLANTINGS
2:1 REPLANTING RATIO R r Y
TREES REQUIRES 5 TREES REMOVED • 2 = -TREES _
TREES PROVIDED 1G TREES
d
'r4.
NOTES & MINIMA
1, TREES SHOWN HEREON
PLANT LIST. SUBSTITIT
DEPARTMENT OF COMMI
2. IF A SUBSTITUTION BE(
3. PLANT LLYT TOTALS ARI
BIDDING,
4. TREES SHALL BE 2.5" I
PLANTED.
5. TIMING OF INSTALLATIOI
PLANTING SEASON roll
OCCUPANCY •Tn$N THI
6. ALL TREES TO BE PLO
ASSOCIATION OF NURSE
THE STANDARDMED LAN
NURSERYMEN'S ASSDCIA
VIRGINIA CHAPTER OF '
ROAD AND BRIDGE SPD
7. CONTRACTOR SHALL AM
PRIOR TO COMMENCING
S. ALL PLANT MATF,RLU, T
PROJECT ACCEPTANCE
OR IS UNHEALTHY AND
CONTRACTOR'S NEGUGE
EXPENSE,
9. MAINTAINING AND REPL
IN A HEALTHY CONDTnI
REPLACEMENT KATERIAI
10. ALL SITE PLANTINGS OI
MAINTAINED AT MATURE
TREES SHALL BE PRUN
THE PLANT.
From: Riki Van-Niekerk <Riki@roudabush.com>
Sent: Thursday, April 29, 2021 1:46 PM
To: Kevin McCollum <kmccollum@albemarle.ore>
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Tax Map/Parcel#060F0000000300
9
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Good afternoon Kevin,
Thank you for your email. Could you be more specific on what number you want to be changed in your comment? The
total tree canopy calculation in the table on sheet 10 changed from 7,979 sf (approved plan) to 9.987 sf due to the
addition of 4 poplars. I apologize in advance if I am being ignorant, but I can't find the mistake.
Thank you,
Rik! van-Niekerk, EIT
Roudabush, Gale & Assoc., Inc.
Office: (434)979-8121
Direct: (434)260-6983
Mail: 435 Merchant Walk sq., Suite 300-159, Charlottesville, VA 22902
Location: 999 Second St. SE, Suite 201, Charlottesville, VA 22902
From: Kevin McCollum <kmccollum@albemarle.org>
Sent: Monday, April 26, 2021 11:12 AM
To: Riki Van-Niekerk <Riki@roudabush.com>
Subject: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL Tax
Map/Parcel#0601`0000000300
Good Morning,
Please see the attached review comments for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES -
FINAL.
There is only one minor comment to be addressed. Once you have made the applicable changes you can either send the
plans back to me for confirmation or you can just go ahead and submit four (4) hard copies of the full LOR plan set to the
Community Development Department for final approval. All you need to do is update the total tree canopy calculation
that is provided on the Landscape Plan. All other reviewers had no objection. Let me know if you have any questions.
Thanks!
Kevin McCollum
Planner, Certified Zoning Official
Community Development Department
Planning Division
Albemarle County
(434) 296-5832 ext. 3141
401 McIntire Rd, Charlottesville VA 22902
10
Kevin McCollum
From: Riki Van-Niekerk <Riki@roudabush.com>
Sent: Thursday, April 29, 2021 1:46 PM
To: Kevin McCollum
Subject: RE: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC
PROFESSIONAL OFFICES - FINAL Tax Map/Parcel #060F0000000300
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Good afternoon Kevin,
Thank you for your email. Could you be more specific on what number you want to be changed in your comment? The
total tree canopy calculation in the table on sheet 10 changed from 7,979 sf (approved plan) to 9.987 sf due to the
addition of 4 poplars. I apologize in advance if I am being ignorant, but I can't find the mistake.
Thank you,
Riki van-Niekerk, EIT
Roudabush,Gale & Assoc., Inc.
Office: (434)979-8121
Direct: (434)260-6983
Mail: 435 Merchant Walk sq., Suite 300-159, Charlottesville, VA 22902
Location: 999 Second St. SE, Suite 201, Charlottesville, VA 22902
From: Kevin McCollum <kmccollum@albemarle.org>
Sent: Monday, April 26, 2021 11:12 AM
To: Riki Van-Niekerk <Riki@roudabush.com>
Subject: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINALTax
Map/Parcel#0601`0000000300
Good Morning,
Please see the attached review comments for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES -
FINAL.
There is only one minor comment to be addressed. Once you have made the applicable changes you can either send the
plans back to me for confirmation or you can just go ahead and submit four (4) hard copies of the full LOR plan set to the
Community Development Department for final approval. All you need to do is update the total tree canopy calculation
that is provided on the Landscape Plan. All other reviewers had no objection. Let me know if you have any questions.
Thanks!
11
Kevin McCollum
Planner, Certified Zoning Official
Community Development Department
Planning Division
Albemarle County
(434) 296-5832 ext. 3141
401 McIntire Rd, Charlottesville VA 22902
12
Kevin McCollum
From: Kevin McCollum
Sent: Monday, April 26, 2021 11:12 AM
To: riki@roudabush.com
Subject: Review Comments LOR#1 for SDP-2019-00062 — GEORGETOWN HYDRAULIC
PROFESSIONAL OFFICES - FINAL Tax Map/Parcel #060F0000000300
Attachments: SDP201900062 LOR 1 Review Comment Letter 4-26-2021.pdf
Good Morning,
Please see the attached review comments for SDP-2019-00062 — GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES -
FINAL.
There is only one minor comment to be addressed. Once you have made the applicable changes you can either send the
plans back to me for confirmation or you can just go ahead and submit four (4) hard copies of the full LOR plan set to the
Community Development Department for final approval. All you need to do is update the total tree canopy calculation
that is provided on the Landscape Plan. All other reviewers had no objection. Let me know if you have any questions.
Thanks!
Kevin McCollum
Planner, Certified Zoning Official
Community Development Department
Planning Division
Albemarle County
(434) 296-5832 ext. 3141
401 McIntire Rd, Charlottesville VA 22902
13
Kevin McCollum
From:
Betty Slough
Sent:
Monday, April 26, 2021 10:37 AM
To:
Kevin McCollum
Subject:
RE: Transmittal of LOR #1 for SDP201900062 GEORGETOWN HYDRAULIC
PROFESSIONAL OFFICES - FINAL
Kevin,
I entered no objection.
Betty R Slough
Commercial Plan Reviewer/ Deputy Building Official
Albemarle County
https://www.albemarle.orci
bsloughCa)albemarle.org
office 434-296-5832 x3362
cell 434-872-3793
401 McIntire Road, Charlottesville, VA 22902
From: Kevin McCollum <kmccollum@albemarle.org>
Sent: Monday, April 26, 20219:53 AM
To: Betty Slough <bslough@albemarle.org>
Subject: FW: Transmittal of LOR #1 for SDP201900062 GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Good Morning Betty,
Did you have any comments on this Letter of Revision? If not, I believe we can go ahead and approve it. Planning,
Engineering, and VDOT all have no objection, but I was waiting Inspections OK, or comments, whichever, before we
finalize it. Thanks!
Kevin
From: Kevin McCollum
Sent: Monday, March 22, 20214:20 PM
To: Adam Moore <Adam.Moore@vdot.virginia.gov>; Brenda Loving <brenda.loving@vdot.virginia.gov>; Matthew
Wentland <mwentland@albemarle.org>; Emily Cox <ecox2@albemarle.org>; David James <d0ames2@albemarle.org>;
John Anderson <0anderson2@albemarle.org>; Betty Slough <bslough@albemarle.org>
Cc: Cameron Langille <blangille@albemarle.org>; Frank Pohl <fpohl@albemarle.org>; Carla Harris - CDD
<CHARRIS@albemarle.org>
Subject: Transmittal of LOR #1 for SDP201900062 GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Good Afternoon,
This email is to serve as the transmittal of Letter of Revision #1 for SDP201900062 GEORGETOWN HYDRAULIC
PROFESSIONAL OFFICES - FINAL. Attached you will find a copy of the Application and the applicable Site Plan pages that
have been amended. Please have comments to me by Tuesday, April 13, 2021. Let me know if you have any questions.
14
Thanks,
Kevin MCCO11Um, Certified Zoning Official
Planner
Community Development Department
Zoning Division
Albemarle County
(434) 296-5832 ext. 3141
401 McIntire Rd, Charlottesville VA 22902
15
Kevin McCollum
From: Kevin McCollum
Sent: Monday, April 26, 2021 9:53 AM
To: Betty Slough
Subject: FW: Transmittal of LOR #1 for SDP201900062 GEORGETOWN HYDRAULIC
PROFESSIONAL OFFICES - FINAL
Attachments: SDP201900062 LOR # 1 Plan 3-15-2021.pdf, SDP201900062 LOR #1 Application
3-15-2021.pdf
Good Morning Betty,
Did you have any comments on this Letter of Revision? If not, I believe we can go ahead and approve it. Planning,
Engineering, and VDOT all have no objection, but I was waiting Inspections OK, or comments, whichever, before we
finalize it. Thanks!
Kevin
From: Kevin McCollum
Sent: Monday, March 22, 20214:20 PM
To: Adam Moore <Adam.Moore@vdot.virginia.gov>; Brenda Loving <brenda.loving@vdot.virginia.gov>; Matthew
Wentland <mwentland@albemarle.org>; Emily Cox <ecox2@albemarle.org>; David James <djames2@albemarle.org>;
John Anderson <janderson2@albemarle.org>; Betty Slough <bslough@albemarle.org>
Cc: Cameron Langille <blangille@albemarle.org>; Frank Pohl <fpohl@albemarle.org>; Carla Harris - CDD
<CHARRIS@albemarle.org>
Subject: Transmittal of LOR #1 for SDP201900062 GEORGETOWN HYDRAULIC PROFESSIONAL OFFICES - FINAL
Good Afternoon,
This email is to serve as the transmittal of Letter of Revision #1 for SDP201900062 GEORGETOWN HYDRAULIC
PROFESSIONAL OFFICES - FINAL. Attached you will find a copy of the Application and the applicable Site Plan pages that
have been amended. Please have comments to me by Tuesday, April 13, 2021. Let me know if you have any questions.
Thanks,
Kevin MCCOIIUm, Certified Zoning official
Planner
Community Development Department
Zoning Division
Albemarle County
(434) 296-5832 ext. 3141
401 McIntire Rd, Charlottesville VA 22902
16
Kevin McCollum
From: Andy Reitelbach
Sent: Thursday, April 8, 2021 5:56 PM
To: Kevin McCollum
Subject: FW: SDP-2019-00062 - Georgetown Hydraulic Professional Offices - Final Site Plan -
LOR #1
Attachments: SDP-2019-00062 - Georgetown Hydraulic Professional Offices - LOR #1 to Final Site
Plan - Dated 03-03-2021.pdf
Hey Kevin,
Looking at CountyView, I believe this comment letter is for you. It appears you're reviewing this LOR.
Sorry for not sending it to you earlier. I was out last Friday, and I must have overlooked it among my other emails.
Thanks,
Andy
Andrew Reitelbach
Senior Planner
Albemarle County
areitelbach@albemarle.ore
434.296.5832 x3261
401 McIntire Road
Charlottesville, VA 22902
From: Greene, Max <max.greene@vdot.virginia.gov>
Sent: Friday, April 2, 20218:00 AM
To: Andy Reitelbach <mreitelbach@albemarle.org>
Cc: Adam Moore <Adam.Moore@vdot.virginia.gov>; Jim Taggart <JTaggart@roudabush.com>
Subject: SDP-2019-00062 - Georgetown Hydraulic Professional Offices - Final Site Plan - LOR #1
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Please find the attached review comment letter.
Max Greene
Land Development Engineer - Land Use
Charlottesville Residency
Virginia Department of Transportation
701 VDOT Way
Charlottesville, Va. 22911
Cell: 434-906-6415
max.greeneoVDOT. Virginia.gov
17
18
Kevin McCollum
From: Matthew Wentland
Sent: Thursday, April 8, 2021 11:06 AM
To: Kevin McCollum
Subject: Planning Application Review for SDP201900062 GEORGETOWN HYDRAULIC
PROFESSIONAL OFFICES - FINAL.
The Review for the following application has been completed:
Application Number = SDP201900062
Reviewer = Matthew Wentland
Review Status = No Objection
Completed Date = 04/08/2021
This email was sent from County View Production.
19
Kevin McCollum
From: Kevin McCollum
Sent: Monday, March 22, 2021 4:20 PM
To: Adam Moore; Brenda Loving; Matthew Wentland; Emily Cox, David James; John
Anderson; Betty Slough
Cc: Cameron Langille; Frank Pohl; Carla Harris - CDD
Subject: Transmittal of LOR #1 for SDP201900062 GEORGETOWN HYDRAULIC PROFESSIONAL
OFFICES - FINAL
Attachments: SDP201900062 LOR # 1 Plan 3-15-2021.pdf, SDP201900062 LOR #1 Application
3-15-2021.pdf
Good Afternoon,
This email is to serve as the transmittal of Letter of Revision #1 for SDP201900062 GEORGETOWN HYDRAULIC
PROFESSIONAL OFFICES - FINAL. Attached you will find a copy of the Application and the applicable Site Plan pages that
have been amended. Please have comments to me by Tuesday, April 13, 2021. Let me know if you have any questions.
Thanks,
Kevin MCCOIIUm, Certified Zoning official
Planner
Community Development Department
Zoning Division
Albemarle County
(434) 296-5832 ext. 3141
401 McIntire Rd, Charlottesville VA 22902
20
Kevin McCollum
From: Scott Kirby <SKirby@roudabush.com>
Sent: Monday, March 22, 2021 3:30 PM
To: Riki Van-Niekerk; Kevin McCollum
Cc: Robby Noll; Jim Taggart
Subject: RE: Georgetown Hydraulic SDP2019-62 Letter of Revision
Attachments: GEORGETOW N_HYDRAU LIC_pages_1-10.pdf
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Kevin,
Here is the PDF for the Georgetown/Hydraulic Revision. Please email me if you need anything else or have any
questions.
Thanks,
Scott Kirby, EIT
Roudabush, Gale & Associates, Inc
skirbv@roudabush.com
Physical Address:
999 Second Street SE
Suite 201
Charlottesville, VA 22902
R(N'nAltl Nil, GALr.
&ANxI%I1.\
From: Riki Van-Niekerk
Mailing Address:
435 Merchant Square
Suite 300-159
Charlottesville, VA 22902
Sent: Monday, March 22, 20213:15 PM
To: Kevin McCollum <kmccollum@albemarle.org>
Cc: Robby Noll <Robby@tbmcom.com>; Scott Kirby <SKirby@roudabush.com>; Jim Taggart <JTaggart@roudabush.com>
Subject: RE: Georgetown Hydraulic 5DP2019-62 Letter of Revision
Hello Kevin,
I am copying my colleague, Scott Kirby, who can provide you with the PDF of the plan.
Please let us know if you require anything else to expedite the review.
Thank you,
Riki van Niekerk
Roudabush, Gale & Associates, Inc.
(434)260-6983
21
From: Kevin McCollum <kmccollum@albemarle.org>
Sent: Monday, March 22, 2021 1:16 PM
To: Riki Van-Niekerk <Riki@roudabush.com>
Cc: Robby Noll <Robby@tbmcom.com>
Subject: Georgetown Hydraulic SDP2019-62 Letter of Revision
Good Afternoon,
My name is Kevin McCollum and I am the review coordinator for the Site Plan Application SDP201900062 GEORGETOWN
HYDRAULIC PROFESSIONAL OFFICES - FINAL (Letter of Revision). I am in the process of reviewing this application and was
wondering if you all could provide a digital copy of the plan? Some reviewers are still working from home and
distributing the Plans by email (pdf) is often the easiest. The application itself I was able to scan, so I just need the Plans.
Thanks so much.
Kevin McCollum, Certified Zoning Official
Planner
Community Development Department
Zoning Division
Albemarle County
(434) 296-5832 ext. 3141
401 McIntire Rd, Charlottesville VA 22902
22
Kevin McCollum
From: Kevin McCollum
Sent: Monday, March 22, 2021 1:16 PM
To: riki@roudabush.com
Cc: Robby Noll
Subject: Georgetown Hydraulic SDP2019-62 Letter of Revision
Good Afternoon,
My name is Kevin McCollum and I am the review coordinator for the Site Plan Application SDP201900062 GEORGETOWN
HYDRAULIC PROFESSIONAL OFFICES - FINAL (Letter of Revision). I am in the process of reviewing this application and was
wondering if you all could provide a digital copy of the plan? Some reviewers are still working from home and
distributing the Plans by email (pdf) is often the easiest. The application itself I was able to scan, so I just need the Plans.
Thanks so much.
Kevin MCCOIIUm, Certified Zoning official
Planner
Community Development Department
Zoning Division
Albemarle County
(434) 296-5832 ext. 3141
401 McIntire Rd, Charlottesville VA 22902
23