HomeMy WebLinkAboutWPO201900014 Plan - VSMP 2021-05-03Erosion and Sediment Control Narrative For:
FOOTHILL FARM
753 ROCKY HOLLOW RD.
TM 62 PARCEL 71
ALBEMARLE COUNTY, VA
HUC: Rivanno River - Meadow Creek 020802040401
LAT: 38' 03' 15"N LONG: 78' 24' 47"W
Project Description: The original proposed work involved the construction of a
new residence, driveway and associated site grading required to create a new
building pad for the house and to create open pasture. The current proposed
work will re-route a portion of the driveway. The total area of the parcel is
187.32 acres. The original total on -site disturbed area was approximately 3.79
acres. An additional 2.71 acres is added by the new driveway. Work is
anticipated to begin in Spring of 2021. The property is located on the north
side of Rocky Hollow Rd., about 0.25 mile east of Stony point Rd.
Erosion control measures shown will protect the stream and property below
from receiving silt -laden runoff.
Existing Site
Conditions: The project
site area
is in a mix open pasture and
fully wooded
hill side and generally
slopes to
the north at 10 to 25%. The pre
and post drainage patterns will be
nearly the
same, with about 0.41 acres
shifting from
a 638 acre drainage
area to a
160 acre drainage area.
Adjacent Property: The property is surrounded by other large acreage parcels
and wooded areas as well as small rural single-family lots.
Off -site Areas: No off -site areas will be involved in this project.
Soils: 236-Davidson clay loam, 0.28 K-Factor, Group B soil
71 B-Rabun clay loam, 0.24 K-Factor, Group B soil
71 C-Rabun clay loam, 0.24 K-Factor, Group B soil
71 D-Rabun clay loam, 0.24 K-Factor, Group B soil
Critical Erosion Areas: There are no critical erosion areas in the project area.
Soil Stockpiles: A temporary soil stockpile will be utilized during the excavation
to preserve topsoil for final grading around the house and driveway.
Erosion and Sediment Control Measures:
Unless otherwise indicated all vegetative and structural erosion and sediment
control practices will be constructed and maintained according to minimum
P 9
standards and specifications of the Virginia Erosion and Sediment Control
Handbook. Additional measures may be required during construction by the
Erosion Control Inspector, as needed.
Structural Practices:
Construction Entrance: (CE) 3.02 (To be installed where construction site traffic exits the project
area, to remove soil from tires prior to travel on public roads. The contractor shall clean and
maintain the travehvay as required to keep soil from washing into unprotected areas and to
provide a safe surface for pedestrian and vehicular access. The Construction Entrance will be
located at an existing cattel guard about 0.4 miles from the public right of way. Once the
building is erected, all adjacent areas will be stabilized and the construction entrance will no
longer be necessary.)
Sflt Fence: (SF) 3.05 Silt fence (wire -supported) shall be constructed along the lower limit of graded areas.
(To be installed as shown on the plan, down -gradient of disturbed areas created by the proposed
work, and above the proposed excavation to prevent up -gradient runofffrom crossing disturbed
areas.)
Culvert Inlet Protection: (CIP) 3.08 A sediment filter located at the inlet to storm sewer culverts which
prevents sediment from entering, accumulating in, and being transferred by the culvert It also provides
erosion control at culverts during the phase of a project where elevations and drainage patterns are
changing, causing original control measures to be ineffective. (To be installed at culvert inlets immediately
after installation)
Outlet Protection (OP) 3.18 The installation of riprap channel sections storm drain outlets to reduce
erosion and under -cutting from scouring at outlets and to reduce flow velocities before stormwater enters
receiving channels below these outlets. (To be installed at the new culverts.)
Rock Check Dann (CD) 3.20 Small temporary stone dams constructed across a drainage ditch to reduce
the velocity of concentrated flows, reducing erosion of the swale or ditch. Limited to use in small open
channels which drain 10 acres or less; should not be used in live streams. (To be installed along the natural
swales on either side of the grading area to minimize runoff velocity.)
Level S reader 3.21 An outlet for dikes and diversions consisting of an excavated depression
P (LS) g P
constructed at zero grade across a slope to convert concentrated, sediment free runoff to sheet flow and
release it into areas of undisturbed soil which is stabilized by existing vegetation. (To be installed at the end
of the roof drains to disperse concentrated runoff)
Permanent Seeding (PS) 3.32 Establishment of perennial vegetative cover by planting seed where
permanent, long-lived vegetative cover is needed on fine -graded areas. (Permanent seeding will be
provided on all disturbed areas designated to be landscaped on the site plan within 7 days of
final grading.)
Mulching (MU) 3.35 Application of plant residues to disturbed surfaces to prevent erosion and reduce
overland flow. Apply to all seeded areas. Refer to Table 3.35-A on Sheet C-3.3 for application rates. (To
be installed along with Permanent Seeding)
Blanketing/Matting (B/M) 3.36 Installation of soil stabilization matting on a prepared planting of a steep
slope. (To be installed along driveway ditch where shown on the plans)
Dust Control DC 3.39 Reducing surface and air movement of dust during land disturbance demolition
( ) g g
or construction activities in areas subject to dust problems in order to prevent soil loss and reduce the
presence of potentially airborne substances. (To be installed, if required by the County, where disturbed
soil is to remain un rotected or an extended eriod.
P .f P )
Vegetative Practices:
Temporary Seeding 3.31: All areas disturbed by construction that will not be
brought to final grade for a period of more than 14 days, will be stabilized
by establishing a good stand of grass.
Lime 3.31: Unless it is known that the site will remain undisturbed for
many months, lime is not necessary. If necessary, the amount will be
determined by Soil Test, or 3 tons per acre of pulverized agricultural
limestone, uniformly applied to surface to be seeded during seedbed
preparation and incorporated into the top 2-4 inches of soil.
Fertilizer 3.31: 600 pounds per acre of 10-20-10 or equivalent, uniformly
applied to the surface to be seeded during seedbed preparation and
incorporated into the top 2-4 inches of soil.
Surface roughening 3.31: Where disturbed soils have been compacted,
loosen soils by discing, raking, or whatever acceptable means available to
receive seed.
Seed 3.31: Seed shall be broadcast evenly and planted from t'A to titz inch
deep. Seasonal seed selection shall be as follows:
• Sept.
1 - Feb. 15:
50/50 Mix of Annual Rye and Winter Rye, 50-100
Ib/ac.
• Feb.
16 - April 30:
use Annual Rye,
60-100 Ib/ac.
• May
1 - Aug. 31:
use German Millet,
50 Ib/ac.
Areas which fail to establish
vegetative cover adequate to prevent rill erosion
will be
reseeded as soon as such areas
are identified.
Foothill Farm
AMENDMENT TO
VSMP/W P02019-00014
Management Strategies: Construction should be sequenced so that grading
operations can begin and end as quickly as possible. Areas that are not to
be disturbed shall be clearly marked by the placement of the erosion control
measures prior to construction. The job superintendent shall be responsible for
the installation and maintenance of all erosion and sediment measures.
Where construction vehicle access routes intersect paved public roads,
provisions shall be made to minimize the transport of sediment by vehicular
tracking onto the paved surface. Where sediment is transported onto a public
road surface, the road shall be cleaned thoroughly at the end of each day.
Sediment shall be removed from the roads by shoveling or sweeping and
transported to a sediment control disposal area. Street washing shall be
allowed only after sediment is removed in this manner.
Stabilization of Denuded Areas and Soil Stockpiles: Permanent or temporary
soil stabilization must be applied to denuded areas within 7 days after final
grade is reached on any portion of the site. Temporary soil stabilization shall
be applied within 7 days to denuded areas which may not be at final grade
but will remain dormant (undisturbed) for longer than 14 days. Permanent
stabilization shall be applied to areas that are to be left dormant for more
than one year.
Soil stabilization refers to measures that protect soil from the erosive forces
of raindrop impact and flowing water. Applicable practices include vegetative
establishment, mulching and the early application of gravel base on areas to
be paved. Soil stabilization measures should be selected to be appropriate for
P
the time of year, site conditions and estimated duration of use.
Timing and Stabilization of Sediment Trapping Measures:
Sediment barriers and traps, perimeter dikes, sediment barriers and other
measures intended to trap sediment shall be constructed as a first step in
an land disturbing activity and shall be made functional before u slo a land
Y 9 Y P P
disturbance takes place. Stabilization measures shall be applied to earthen
structures such as dams, dikes, and diversions immediately after installation.
Disposal of Temporary Measures: All temporary erosion and sediment control
measures shall be removed within 30 days after final site stabilization or after
the temporary measures are no longer needed, unless otherwise authorized by
the local program administrator.
Trapped sediment and the disturbed soil areas resulting from the disposition of
temporary measures shall be removed and replaced with suitably compacted
soils, or, where applicable, permanently stabilized to prevent further erosion and
sedimentation.
Maintenance: All erosion and sediment control structures and systems shall be
maintained, inspected, and repaired weekly and after each significant rainfall or
as needed to insure continued performance of their intended function. Any
damage to structural measures shall be repaired immediately.
Silt fence shall be inspected after every rainfall event and at least daily during
prolonged rainfall, as well as at the end of every working day, with any
necessary repairs made immediately. Accumulated sediment shall be removed
and disposed of as it becomes necessary, or when deposits have accumulated
to one-half of the above ground fence height. All undercutting or erosion shall
be repaired immediately. the contractor shall follow all manufacturers
recommendations for installation maintenance replacement, and air.
P repair.
damages caused by construction traffic or other activity must be repaired
before the end of each working day.
All seeded areas are to be checked to insure a good stand is maintained.
General construction notes for Erosion and Sediment Control plans
1. The plan approving authority must be notified one week prior to the
pre -construction conference, one week prior to the commencement of land
disturbing activity, and one week prior to the final inspection.
2. All erosion and sediment control measures will be constructed and
maintained according to minimum standards and specifications of the Virginia
Erosion and Sediment Control Handbook and Virginia Regulations VR 625-02-00
Erosion and Sediment Control Regulations.
3. All erosion and sediment control measures are to be placed prior to or as
the first step in clearing.
4. A copy of the approved erosion and sediment control plan shall be
maintained on the site at all times.
5. Prior to commencing land disturbing activities in areas other than indicated
on these plans (including, but not limited to, off -site borrow or waste areas),
the contractor shall submit a supplementary erosion control plan to the owner
for review and approval by the plan approving authority.
6. The contractor is responsible for installation of any additional erosion control
measures necessary to prevent erosion and sedimentation as determined by the
plan approving authority.
7. All disturbed areas are to drain to approved sediment control measures at
all times during land disturbing activities and during site development until final
stabilization is achieved.
8. During dewatering operations, water will be pumped into an approved filtering
device.
9. The contractor shall inspect all erosion control measures periodically and
after each runoff producing rainfall event. Any necessary repairs or cleanup to
maintain the effectiveness of the erosion control devices shall be made
immediately.
Y
10. All fill material to be taken from an approved, designated borrow area.
11. All waste materials shall be taken to an approved waste area. Earth fill
shall be inert materials only, free of roots, stumps, wood, rubbish, and other
debris.
12. Borrow, fill or waste activity involving industrial -type power equipment shall
be limited to the hours of 7:00am to 9:00pm.
13. Borrow, fill or waste activity shall be conducted in a safe manner than
maintains lateral support, or order to minimize any hazard to persons, physical
damage to adjacent land and improvements, and damage to any public street
because o slides, sinking, or collapse.
14. Temporary stabilization shall be temporary seeding and mulching. Seeding is
to be at 75lbs/acre, and in the months of September to February to consist a
50/50 mix of Annual Ryegrass and Cereal Winter Rye, or in March and April to
consist of Annual Rye, or May through August to consist of German Millet.
Straw mulch is to be applied at 8OIbs/100sf.
Alternatives are subject to approved by the erosion control inspector.
15. Permanent stabilization shall be lime and fertilizer, permanent seeding, and
mulch. Agricultural grade limestone shall be applied at 9OIbs/1000sf,
incorporated into the top 4-6 inches of soil. Fertilizer shall be applied at
1000lbs/acre and consist of a 10-20-10 nutrient mix. Permanent seeding shall
be applied at 180lbs/acre and consist of 95% Kentucky 31 or Tall Fescue and
0-5% Perennial Ryegrass or Kentucky Bluegrass. Straw mulch is to be
applied at 80lbs/100sf. Alternatives are subject to approved by the County
erosion control inspector.
16. Maintenance: All measures are to be inspected weekly and after each
rainfall. Any damage or clogging to structural measures is to be repair
immediately. Silt traps are to be cleaned when 50% of the wet storage volume
is filled with sediment. All seeded areas are to be reseeded when necessary to
achieve a good stand of grass. Silt fence and diversion dykes which are
collecting sediment to half their height must be cleaned and repaired
immediately.
17. All temporary erosion and sediment control measures are to be removed
within 15 days of final site stabilization, when measures are no longer needed,
subject to approval by the County erosion control inspector.
18. Permanent vegetation shall be installed on all denuded areas within nine (9)
months after the date the land disturbing activity commenced.
MINIMUM STANDARDS
MS-1 Permanent or temporary soil stabilization must be applied to denuded
areas within seven days after final grade is reached on any portion of the
site. Temporary soil stabilization shall be applied within seven days to
denuded areas that may not be at final grade but will remain dormant
(undisturbed) for longer than 15 days. Permanent stabilization shall be
applied to areas that are to be left dormant for more than one year. Soil
stabilization refers to measures which protect soil from the erosive forces of
raindrop impact and flowing water. Applicable practices include vegetative
establishment, mulching, and the early application of gravel base on areas to
be paved. Soil stabilization measures should be selected to be appropriate
for the time of year, site conditions and estimated duration of use.
MS-2 During construction of the project, soil stockpiles and borrow areas shall
be stabilized or protected with sediment trapping measures. The applicant is
responsible for the temporary protection and permanent stabilization of all
P P rY P
soil stockpiles on site as well as borrow areas and soil intentionally
transported from the project site.
MS-3 A permanent vegetative cover shall be established on denuded areas not
otherwise permanently stabilized. Permanent vegetation shall not be
considered established until a ground cover is achieved that, is uniform,
mature enough to survive and will inhibit erosion.
MS-4 Sediment basins and traps, perimeter dikes, sediment barriers and other
measures intended to trap sediment shall be constructed as a first step in
any land -disturbing activity and shall be made functional before upslope land
disturbance takes place.
MS-5 Stabilization measures shall be applied to earthen structures such as
dams, dikes, traps, basins and diversions immediately after installation.
MS-6 Surface runoff from disturbed areas that is comprised of flow from
drainage areas greater than or equal to three acres shall be controlled by a
sediment basin. The sediment basin shall be designed and constructed to
accommodate the anticipated sediment loading from the land disturbing
activity. The outfall device or system design shall take into account the
total drainage area flowing through the disturbed area to be served by the
basin.
MS-7 Cut and fill slopes shall be constructed in a manner that will minimize
erosion. Slopes that are found to be eroding excessively within one year of
permanent stabilization shall be provided with additional slope stabilizing
measures until the problem is corrected.
MS-8 Concentrated runoff shall not flow down cut or fill slopes unless
contained within an adequate temporary or permanent channel, flume, or
slope drain structure.
MS-9 Whenever water seeps from a slope face, adequate drainage or other
protection shall be provided.
MS-10 All storm
sewer inlets that are made operable
during
construction shall
be protected
P
so that sediment -laden
water cannot
enter
conveyance
the conve Y
system without
first being filtered or
otherwise treated to
remove sediment.
MS-11 Before newly constructed stormwater conveyance channels are made
operational, adequate outlet protection and any required temporary or
permanent channel lining shall be installed in both the conveyance channel
and receiving channel.
MS-12 through 15 - Not applicable, no live watercourses.
MS-16 Underground utility lines shall be installed in accordance with the
following standards in addition to other applicable criteria:
a. No more than 500 linear feet of trench may be opened at one
time.
b. Excavated material shall be P
laced on the uphill side of trenches.
P
c. Effluent from dewatering operations shall be filtered or passed through an
approved sediment trapping device, or both, and discharged in a manner
that does not adversely affect flowing streams or off -site property.
d. Restabilization shall be accomplished in accordance with these regulations.
e. Applicable safety regulations shall be complied with.
MS-17 Where construction vehicle access routes intersect paved public roads,
provisions shall be made to minimize the transport of sediment by vehicular
tracking onto the paved surface. Where sediment is transported onto a
public road surface, the road shall be cleaned thoroughly every four hours.
Sediment shall be removed from the roads by shoveling or sweeping and
transported to a sediment control disposal area. Street washing shall be
allowed only after sediment is removed in this manner.
MS-18 All temporary erosion and sediment control measures shall be removed
within 30 days after final site stabilization or after the temporary measures
are no longer needed, unless otherwise authorized by the local program
administrator. Trapped sediment and the disturbed soil areas resulting from
the disposition of temporary measures shall be permanently stabilized to
prevent further erosion and sedimentation.
MS-19 Drainage Area A is 160 acres. The increase in impervious area is less than
1% of the total watershed area. (9VAC25-870-66 C-3-a).
Drainage Area B is 638 acres and slightly B is reduced in size by 0.4 acres.
Concentrated flows at the driveway ditch and roof drains are routed to level
spreaders to create sheetflow condition. The increase in impervious area is less
than 1 % of the total watershed area. (9VAC25-870-66 C-3-a).
u
VICINITY MAP
SCALE: 1 "=2,000 FT.
GENERAL EROSION AND SEDIMENT CONTROL NOTES
ES-1: UNLESS OTHERWISE INDICATED, ALL VEGETATIVE AND STRUCTURAL
EROSION AND SEDIMENT CONTROL PRACTICES WILL BE CONSTRUCTED AND
MAINTAINED ACCORDING TO MINIMUM STANDARDS AND SPECIFICATIONS OF
THE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK AND VIRGINIA
REGULATIONS VR 625-02-00 EROSION AND SEDIMENT CONTROL
REGULATIONS.
ES-2: THE PLAN APPROVING AUTHORITY MUST BE NOTIFIED ONE WEEK
PRIOR TO THE PRE- CONSTRUCTION CONFERENCE, ONE WEEK PRIOR TO
THE COMMENCEMENT OF LAND DISTURBING ACTIVITY, AND ONE WEEK
PRIOR TO THE FINAL INSPECTION.
ES-3: ALL EROSION AND SEDIMENT CONTROL MEASURES ARE TO BE
PLACED PRIOR TO OR AS THE FIRST STEP IN CLEARING.
ES-4: A COPY OF THE APPROVED EROSION AND SEDIMENT CONTROL
PLAN SHALL BE MAINTAINED ON THE SITE AT ALL TIMES.
ES-5: PRIOR TO COMMENCING LAND DISTURBING ACTIVITIES IN AREAS
OTHER THAN INDICATED ON THESE PLANS (INCLUDING, BUT NOT LIMITED
TO, OFF -SITE BORROW OR WASTE AREAS), THE CONTRACTOR SHALL
SUBMIT A SUPPLEMENTARY EROSION CONTROL PLAN TO THE OWNER FOR
REVIEW AND APPROVAL BY THE PLAN APPROVING AUTHORITY.
ES-6: THE CONTRACTOR IS RESPONSIBLE FOR INSTALLATION OF ANY
ADDITIONAL EROSION CONTROL MEASURES NECESSARY TO PREVENT
EROSION AND SEDIMENTATION AS DETERMINED BY THE PLAN APPROVING
AUTHORITY.
ES-7: ALL DISTURBED AREAS ARE TO DRAIN TO APPROVED SEDIMENT
CONTROL MEASURES AT ALL TIMES DURING LAND DISTURBING ACTIVITIES
AND DURING SITE DEVELOPMENT UNTIL FINAL STABILIZATION IS ACHIEVED.
ES-8: DURING DEWATERING OPERATIONS, WATER WILL BE PUMPED INTO
AN APPROVED FILTERING DEVICE.
ES-9: THE CONTRACTOR SHALL INSPECT ALL EROSION CONTROL
MEASURES PERIODICALLY AND AFTER EACH RUNOFF -PRODUCING RAINFALL
EVENT. ANY NECESSARY REPAIRS OR CLEANUP TO MAINTAIN THE
EFFECTIVENESS OF THE EROSION CONTROL DEVICES SHALL BE MADE
IMMEDIATELY.
THE RLD IS RESPONSIBLE FOR ONGOING MAINTENANCE AND OPERATION
OF THE E&SC PLAN.
FOR THE PURPOSES OF PLAN SUBMITTAL, REVIEW AND APPROVAL, THE
RLD IS B. CLARK GATHRIGHT, P.E.
SEQUENCE OF CONSTRUCTION
1. Install Construction Entrance and silt fence where shown on the
plan.
2. Excavate and grade driveway as shown. Utilize cut material for fill
as required. Install culvert inlet and outlet protection and level
spreaders as culvert are installed.
3. If the site will remain dormant for more than 15 days, provide
temporary seeding measures to stabilize the surface.
4. When road grading is complete, install check dams in ditches.
5. Apply mulching and permanent seeding on all permanently stabilized
areas.
6. Remove silt fence and check dams after all disturbed areas are
stabilized, with County Inspector approval.
DRAWING INDEX
SITE
SITE DATA:
OWNER/DEVELOPER:
TOBIAS A & LYNN T DENGEL TRUST
540 PARK ST.
CHARLOTTESVILLE, VA 22902
LOCATION:
753 ROCKY HOLLOW RD.
TM 62 PARCEL 71
ALBEMARLE COUNTY, VA
PLAN PREPARED BY:
B. CLARK GATHRIGHT, P.E.
100 10TH ST NE SUITE 200
CHAR LOTTESVI LLE, VA 22902
TOTAL SITE AREA: 187.32
ZONING: RA
DATUM REFERENCE FOR ELEVATION: NAVD88
SOURCE OF TOPOGRAPHY:
ROGER W. RAY & ASSOC.,INC. - NOV. 12, 2018
NEW RESIDENCE AND DRIVEWAY
SETBACKS: FRONT: 75 FT.
SIDE: 25 FT.
REAR: 35 FT.
ORIGINAL DISTURBED AREA: 3.79 AC.
PROPOSED ADDITIONAL DISTURBED AREA: 2.71 AC.
TOTAL DISTURBED AREA: 6.50 AC.
EXISTING IMPERVIOUS SURFACE: 1.33 AC.
NEW IMPERVIOUS SURFACE: 0.64 AC. (APPROVED)
NEW IMPERVIOUS SURFACE: 0.36 AC. (AMENDMENT)
TOTAL NEW IMPERVIOUS AREA: 1.00 AC.
TOTAL IMPERVIOUS AREA: 2.33 AC.
WATER QUANTITY: LESS THAN 1 % OF THE TOTAL
WATERSHED (9VAC25-870-66 C-3-A)
INCREASE IN SHEETFLOW VOLUME WILL NOT CAUSE
OR CONTRIBUTE TO EROSION, SEDIMENTATION, OR
FLOODING OF DOWN GRADIENT (9VAC25-870-66 D)
WATER QUALITY: ORIGINAL1.42 LB./YR NUTRIENT
CREDIT PURCHASE.
NEW NUTRIENT CREDIT PURCHASE: 0.59 LB./YR
NUTRIENT CREDIT PURCHASE
TOTAL NUTRIENT CREDIT PURCHASE: 2.01 LB.YR
CRITICAL SLOPES: NO CRITICAL SLOPES IN THE
PROJECT AREA.
TIMING OF CONSTRUCTION: SPRING 2021
VIRGINIA OUTDOORS FOUNDATION EASEMENT
-
1
T-1.0
TITLE SHEET & EROSION AND SEDIMENT CONTROL NARRATIVE
-
2
C-1.0
OVERALL PROPERTY PLAN - EXISTING CONDITIONS & SWM PLAN
-
3
C-1.1
NEW LOWER DRIVEWAY PLAN & DRAINAGE AREAS
-
4
C-1.1A
DRIVEWAY EROSION & SEDIMENT CONTROL PLAN
-
5
C-1
.1 B
DRIVEWAY EROSION & SEDIMENT CONTROL PLAN
-
C-1.2
- SEE APPROVED PLAN
6
C-1.3
EROSION AND SEDIMENT CONTROL DETAILS
-
C-1.4
- SEE APPROVED PLAN
-
7
C-1.5
WATER QUALITY CALCULATIONS
-
8
C-1.6
STORMWATER CALCULATIONS
N
O
O
N
N
U
Q
J
z
J
O
(D
O
+-+
N
C_
W
J
J
C6
LU
U j
Z
LU
i
U
O
0
U
Q
m
O
o
=
U
H
of
oB.
Z
CLARK GATHRIGHT
Lic. No. 630
r�
.0
o --
-
o Z)
��SS03 InhTA
L\U
Q
L
Z
O
�
O
rn
J
0
O
N
N
0!�
Z
0
Na;
_>
U
OIn
Z
O
L
LU
(10
L
U
Q
L
01-1
V)
LIMti
O
i
O
=
UJ
Z
_SeLu
0
�o N
O
C�
O
W
cn
O
LI
LO
121!�
UJ
REVISIONS:
DATE:
03-16-21
DRAWING NUMBER:
T-1
*0
SHEET
1
OF 8
REMOVE SH
DITCH 4A
O.A:0.99 AC.
Q10 FLOW:3.28 CFS
/ /�'
Qio v OC17a CFS
NEW LOWER DRIVEWAY PLAN & DRAINAGE AREAS
SCALE: 1" = 100'
STONE CONSTRUCTION ENTRANCE
70' MIN. EXISTING
A PAVEMENT
3'
5:1 Y
' I_t�111-1Lp11-111� I_I-1Ti-
I I m)II�I I I�jjj���-JJJ I II;
J FILTER CLOTH 6" MIN. AT MOUNTABLE BERM
SIDE ELEVATION
GROUND
70' MIN.
B WASHRACK
I f- <OPTIONAL>
�IIIIIIIII1�'���
L VDOT #1 I I -\ POSITIVE DRAINAGE
COURSE AGGREGATE B TO SEDIMENT
TRAPPING DEVICE
+ MUST EXTEND FULL WIDTH PLAN VIEW
OF INGRESS AND EGRESS
OPERATION
RE,L�.,R..�,. �.urv,.rta
SECTION A —A
1F IN.
EXISTING
PAVEMENT
1N.�
LRNIIV Jr NI.L
SECTION B—B
SOURCE: ADAPTED from 1983 Maryland Standards for Soil erosion and Sediment Control, and Va. DSWC Plate 3.02-1
STONE 70' MIN.
CONSTRUCTION
C 5S 3" SM-2A ASPHALT TOP
/ COURSE EXISTING
27
?%PAVEMENT
6" M,N. 21A AGGREGATE BASE
PROFILE
70' MIN
STONE
CONSTRUCTION
ASPHALT PAVED
ACCESS -
A
WASHRACK
EXISTING
2%,
2%
PAVEMENT
MH
2%
12' MIN.•
"MUST EXTEND FULL WIDTH
L o
POSITIVE DRAINAGE
TO SEDIMENT
OF INGRESS AND EGRESS
TRAPPING DEVICE
OPERATION
PLAN
POSITIVE DRAINAGE
12' MIN.
2%
TO SEDIMENT
TRAPPING DEVICE
FILTER CLOTHS
SECTION A -A
A n»ninmun water tap of 1 inch must be installed with a mininnuu 1 inch Uallcock
slmtoff vahve supplying a wash hose with a diameter of 1.5 inches for adequate
constant pressure. Wash water must be carried away from the entrance to an
approved settling area to remove sediment. All sediment shall be prevented fi-om
entering stoma drains, ditches or watercourses.
PAVED WASH RACK
NO S, - I
ALT: PAVED WASH RACK, IF REQUIRED BY COUNTY E&SC INSPECTOR
%j
TOPO SOURCE: COUNTY GIS 4' CONTOUR INTERVAL
LINETYPE & SYMBOL LEGEND
EXISTING CONTOUR LINE
PROPOSED CONTOUR LINE
PROPERTY BOUNDARY — — — —
DRAINAGE DIVIDE
LIMIT OF GRADING —
SOILTYPEBOUNDARY
SOIL TYPE XXX
N
I
� � W
W
Ln
W
W
CV
O
O
N
N
J
z
J
O
q
(5
+-+
N
CD
LIJ
c—
CO
J
M
Lu
U)
v
z
LJJ
i
U)
�
�
U
CD
'q'-
Q
m
O
o
=
U
H
of
oB.
Z
CLARK GATHRIGHT
� N o. 6
la
/Lic�.
73��%0/J`�
I b
oZl
�SSIONAL
lysv�
��Gl
r
O
a,
O
N
O
Q
Z
CD
N
=
p4-1
>�
O
Q
N
C/)
U
C
Lu
Q
uJ
L
-0
E
fY
Q
Q
U [`
0
,,LJtJJ
(a)O
Lu
V
i
=
3:Q
■
3e
Z
CN
UO
J
Q
O
Luu,
�M
LL
Z
Wy
REVISIONS:
DATE:
03-16-21
DRAWING NUMBER:
C-1
01
SHEET
3
OF 8
/ r Z/ /
DRAINAGE DIVIDE, TYP.----____., \ \ \— / / / / /
EXISTING HOUSE
640
DITCH
DRAINAGE GE DIVIDE, TYP.CONSTRUCTION
PER APPROVED PLAN ENTRANCE LOCATION—�` �E OVE GRAVELROAD
CIP P — CULVERT 7 / \
INV IN: 607.5
INV OUT: 606.5
EXISTING D IVEWAY _ CULVERT j 6
/ / W 6�.5 \
12" HDPE 0 14.58% 16' L.
ROCK CHECK DAM \ L=48'
I ® 100' SPACING, TYPE /� INV IN: 616.0
\ / / INV OUT: 6o9.0— / iHEADWALL LS 0
15.5
\\ --__— -- s
L - J APPRO
LOCAX� i CIE
TIddN OF i /
o _CRITIC L 51-9-RE / 1
SF
/ — — — — -CULVERT 5 \
12" HDPE 02% � PERMANENTLY SEED &MULCH � 1
/ L=24' ALL GRADES SLOPES, TYP.
INV IN: 596.5 \ —
C INV OUT: 596.0 r l I \ l
LIMIT OF GRADING
NEW DISTURBED AREA: 2.71 AC. — — — _ — I / \ \ \ \ \\ \ 1 1 ` — / / / / / \ \ 1 \ \ \\ \ �_ / a
— CULVERT 4 \ �
\ i 12" HDPE 0 2% / I\
U
- - — L=24' 588 \ / /04
INV IN: / w
INV OUT:: 596 596.0 \ \ �- � � / s°° \ \ � w
NEW LOWER DRIVEWAY EROSION & SEDIMENT CONTROL PLAN 2' CONTOUR INTERVAL
C-1 .l A SCALE: 1" = 40' SOURCE OF TOPOGRAPHY: ROGER W. RAY & ASSOC.,INC.
SEE SHEET C-1.18
I
1
I
U \
LLI
LLI
/-W604.5
1
� �20'
�`� - r
/ I H�ADWALL LS r
I % �
�j
2 NEW LOWER DRI
-l.lA SCALE: 1"=40'
DRAINAGE DIVIDE, TYP.--,,,..
8
�CULVERT
12' HDPE 0 8.33%
L=50'
INV IN: 603.5
INV OUT: 601.5
l
�P
1 I
60 / �
PERMANENTLY SEED & MULCH
ALL GRADES SLOPES, TYP.
DITCH DRAINAGE DIVIDE, TYP.
CIP
/ TW611. LS
20' L.
STONE
HEADWALL
l I CRITICAL SLOPES
(PER COUNTY GIS)
VEWAY EROSION & SEDIMENT CONTROL PLAN
ROCK CHECK DAM z—
® 100' SPACING, TYP. ®_
61,
CULVERT 9
15" HDPE 0 6.33%
L=30'
INV IN: 610.6
INV OUT: 607.7
m
� • o
m �
• m
m
LINETYPE & SYMBOL LEGEND
EXISTING CONTOUR LINE
CONSTRUCTION ENTRANCE 3.02
C
E
PROPOSED CONTOUR LINE
PROPERTY BOUNDARY — — — — —
— CONSTRUCTION ROAD STABILIZATION 3.03
DRAINAGE DIVIDE
—
LIMIT OF GRADING
SILT FENCE 3.05
C C
J r
CULVERT INLET PROTECTION 3.08
CIP
OUTLET PROTECTION 3.18
O P
ROCK CHECK DAM 3.20
C D
LEVEL SPREADER3.21
LS
TEMPORARY SEEDING 3.31
TS
PERMANENT SEEDING 3.32
P S
MULCHING 3.35
SWPPP NOTE:
THE USE OF CHEMICALS/SOLVENTS IS
SOIL BLANKETS &MATTING 3.36
/
NOT ANTICIPATED. PAINTS, STAINS AND
POLYURETHANE FINISH MATERIALS WILL
BE STORED INSIDE THE BUILDING.
DUST CONTROL 3.39
DC
CV
O
N
N
J
z
J
o
q
O
fY
ui
c—
Cl)
J
J
m
Lu
U)
v
Z
L1J
U
O
U
'q'_
<
Q
m
o
U
Q
o
o
N
Q
z
O
\
5W
N
a/
.�
p
O
LU
a)
c)
a--�
0
i
W
z
00
E
L
Oz
0
LL
—
w
OL
�_ U
=
1
QO
^
LL
3e
OQorrwz
0
co
_
�O
LL
pU
REVISIONS:
DATE:
03-16-21
DRAWING NUMBER:
C-1
A
ol
SHEET
4
OF 8
CV
0
N
N
J
z
J
o
C�
..
(5
+r
N
LLj
U)
J
co
w
U)
z
W
i
U)
H
Co
o
U
�
Q
m
o
o
=
U
H
OF
oB.
Z
CLARK GATHRIGHT
No. 6
/Li/icc.
�SSIONAL
E�Cl
O
a,
O
N
�
O
Q
z
r
>
w
N
p
0
a)
cn
o
z
O
0z
ca�Q
LL
o
wJ
f2
U
=
� J
�
U
� fY
}� N
O co
z
O
�
�O
LL
C)U
REVISIONS:
DATE:
03-16-21
DRAWING NUMBER:
C-1
J B
SHEET
5
OF 8
DITCH 4A
DITCH 4B
CULVERT 4
LEVEL SPREADER 4
34850 SF
0.80 AC.
8312 SF
0.19 AC.
43162 SF
0.99 AC.
43162 SF
0.99 AC.
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
IMP AREAS
11530
0.26
0.9
0.24
IMP AREAS
385
0.01
0.9
0.01
IMP AREAS
11915
0.27
0.9
0.25
IMP AREAS
11915
0.27
0.9
0.25
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
GRAVEL
0.00
0.7
0.00
OTHER
23320
0.54
0.3
0.16
Ditch 4A
OTHER
7927
0.18
0.3
0.05
Ditch 413
OTHER
31247
0.72
0.3
0.22
Culvert 4
OTHER
31247
0.72
0.3
0.22
0.80
0.40
Lt Side Slope: 3.00:1(H:V)
Velocity: 2.25 fps
0.19
0.06
Lt Side Slope:
3.00:1(H:V)
Velocity: 1.84 fps
0.99
0.46
Diameter:
1.00 ft
Velocity: 7.76 fps
0.99
0.46
Cp.t=
0.50
Rt Side Slope: 3.00:1(H:V)
Flow Area: 1.26 sf
CpW=
0.33
Rt Side Slope:
3.00:1(H:V)
Flow Area: 0.24 sf
Cp.=
0.47
Slope:
0.0200 ft/ft
Flow Area: 0.42 sf
Cp„t=
0.47
Manning's n: 0.030
Flow Top Width: 3.88 ft
Manning's n:
0.030
Flow Top Width: 1.70 ft
Manning's n:
0.011
Critical Slope: 0.0068 ft/ft
t=
5 min.
Channel Slope: 0.0100 ft/ft
Wetted Perimeter: 4.09 ft
t=
5 min.
Channel Slope:
0.0200 ft/ft
Wetted Perimeter: 1.79 ft
t=
5 min.
Discharge:
3.28 cfs
Critical Depth: 0.78 ft
t=
5 min.
STORM
i in/hr
A
C
O cfs
Depth: 0.65 ft
Critical Depth: 0.56 ft
STORM
i in/hr
A
C
O cfs)
Depth: 0.28 ft
Critical Depth: 0.27 ft
STORM
i in/hr
A
C
O(CIS)
Depth:
0.53 ft
Percent Full: 52.97 %
STORM
i in/hr
A
C
O (cfs)
Discharge: 2.83 cfs
Critical Slope: 0.0215 ft/ft
Discharge: 0.44 cfs
Critical Slope: 0.0276 ft/ft
Full Capacity:
5.95 cfs
QMAX @.94D: 6.41 cfs
10 7.1 0.80 0.50 2.83
10 7.1 0.19 0.33 0.44
10 7.1 0.99 0.47 3.28
1.0 0.99 0.47
0.46
DITCH 5A
DITCH 513
CULVERT 5
LEVEL SPREADER 5
13154 SF
0.30 AC.
58538 SF
1.34 AC.
71692 SF
1.65 AC.
71692 SF
1.65 AC.
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
IMP AREAS
2945
0.07
0.9
0.06
IMP AREAS
5027
0.12
0.9
0.10
IMP AREAS
7972
0.18
0.9
0.16
IMP AREAS
7972
0.18
0.9
0.16
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
GRAVEL
0.00
0.7
0.00
OTHER
10209
0.23
0.3
0.07
Ditch 5A
OTHER
53511
1.23
0.3
0.37
Ditch SB
OTHER
63720
1.46
0.3
0.44
Culvert 5
OTHER
63720
1.46
0.3
0.44
0.30
0.13
Lt Side Slope: 3.00:1(H:V)
Velocity: 2.21 fps
1.34
0.47
Lt Side Slope:
3.00:1(H:V)
Velocity: 4.30 fps
1.65
0.60
Diameter:
1.00 ft
Velocity: 8.25 fps
1.65
0.60
CPWt=
0.43
Rt Side Slope: 3.00:1(H:V)
Flow Area: 0.42 sf
Cpost=
0.35
Rt Side Slope:
3.00:1(H:V)
Flow Area: 0.78 sf
Cpost=
0.37
Slope:
0.0200 ft/ft
Flow Area: 0.52 sf
Cp..t=
0.37
Manning's n: 0.030
Flow Top Width: 2.25 ft
Manning's n:
0.030
Flow Top Width: 3.06 ft
Manning's n:
0.011
Critical Slope: 0.0094 ft/ft
t=
5 min.
Channel Slope: 0.0200 ft/ft
Wetted Perimeter: 2.37 ft
t=
5 min.
Channel Slope:
0.0500 ft/ft
Wetted Perimeter: 3.22 ft
t=
5 min.
Discharge:
4.29 cfs
Critical Depth: 0.87 ft
t=
5 min.
STORM
i iNhr
A
C
O (cfs)
Depth: 0.37 ft
Critical Depth: 0.36 ft
STORM
i in/hr
A
C
O cfs
Depth: 0.51 ft
Critical Depth: 0.60 ft
STORM
i in/hr
A
C
O cfs
Depth:
0.63 ft
Percent Full: 62.85 %
STORM
i in/hr
A
C
q cfs
Discharge: 0.93 cfs
Critical Slope: 0.0250 ft/ft
Discharge: 3.35
cfs
Critical Slope: 0.0210 ft/ft
Full Capacity:
5.95 cfs
QMAX @.94D: 6.41 cfs
10 7.1 0.30 0.43 0.93
10 7.1 1.34 0.35 3.35
10 7.1 1.65 0.37 4.29
1.0 1.65 0.37
0.60
DITCH 6
CULVERT 6
LEVEL SPREADER 6
28585 SF
0.66 AC.
28585 SF
0.66 AC.
28585 SF
0.66 AC.
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
IMP AREAS
1529
0.04
0.9
0.03
IMP AREAS
1529
0.04
0.9
0.03
IMP AREAS
1529
0.04
0.9
0.03
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
GRAVEL
0.00
0.7
0.00
OTHER
27056
0.62
0.3
0.19
Ditch 6
OTHER
27056
0.62
0.3
0.19
Culvert 6
OTHER
27056
0.62
0.3
0.19
0.66
0.22
Lt Side Slope: 3.00:1 H:V
P ( )
Velocity: 3.10 fps
tY� P
0.66
0.22
Diameter:
1.00 ft
Velocity: 12.93 fps
tY� P
0.66
0.22
Cp.t=
0.33
Rt Side Slope: 3.00:1 (H:V)
Flow Area: 0.50 sf
Cpw=
0.33
Slope:
0.1450 ft/ft
Flow Area: 0.12 sf
CpW=
0.33
Manning's n: 0.030
Flow Top Width: 2.45 ft
Manning's n:
0.011
Critical Slope: 0.0045 ft/ft
t=
5 min.
Channel Slope: 0.0350 ft/ft
Wetted Perimeter: 2.58 ft
t=
5 min.
Discharge:
1.55 cfs
Critical Depth: 0.53 ft
t=
5 min.
STORM
i (in/hr)
A
C
O (cfs)
Depth: 0.41 ft
Critical Depth: 0.44 ft
STORM
i in/hr
A
C
O (cfs)
Depth:
0.21 ft
Percent Full: 21.00 %
STORM
i (in/hr)
A
C
q cfs
10
7.1
0.66
0.33
1.55
Discharge: 1.55 cfs
Critical Slope: 0.0233 ft/ft
10
7.1
0.66
0.33
1.55
Full Capacity:
16.03 cfs
QMAX @.94D: 17.25 cfs
1.0
0.66
0.33
0.22
DITCH 7A
DITCH 7B
CULVERT 7
LEVEL SPREADER 7
68201 SF
1.57 AC.
10097 SF
0.23 AC.
159431 SF
3.66 AC.
159431 SF
3.66 AC.
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
IMP AREAS 1226.5 0.03 0.9 0.03
IMP AREAS 665.5 0.02 0.9 0.01
IMP AREAS 2134 0.05 0.9 0.04
IMP AREAS 2134 0.05 0.9
0.04
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
GRAVEL
0.00
0.7
0.00
OTHER
66975
1.54
0.3
0.46
Ditch 7A
OTHER
9432
0.22
0.3
0.06
Ditch 7B
OTHER
157297
3.61
0.3
1.08
Culvert 7
OTHER
157297
3.61
0.3
1.08
1.57
0.49
Lt Side Slope: 3.00:1(H:V)
Velocity: 4.91 fps
0.23
0.08
Lt Side Slope:
3.00:1(H:V)
Velocity: 3.20 fps
3.66
1.13
Diameter:
1.00 ft
Velocity: 12.42 fps
3.66
1.13
Cpo =
0.31
Rt Side Slope: 3.00:1(H:V)
Flow Area: 0.70 sf
CPM=
0.34
Rt Side Slope:
3.00:1(H:V)
Flow Area: 0.18 sf
Cpm=
0.31
Slope:
0.0416 ft/ft
Flow Area: 0.64 sf
Cp0s,=
0.31
Manning's n: 0.030
Flow Top Width: 2.90 ft
Manning's n:
0.030
Flow Top Width: 1.45 ft
Manning's n:
0.011
Critical Slope: 0.0327 ft/ft
t=
5 min.
Channel Slope: 0.0700 ft/ft
Wetted Perimeter: 3.06 ft
t=
5 min.
Channel Slope:
0.0750 ft/ft
Wetted Perimeter: 1.53 ft
t=
5 min.
Discharge:
8.00 cfs
Critical Depth: 0.99 ft
t=
5 min.
STORM
i in/hr
A
C
q(CIS)
Depth: 0.48 ft
Critical Depth: 0.61 ft
STORM
i m/hr
A
C
O cfs
Depth: 0.24 ft
Critical Depth: 0.29 ft
STORM
i in/hr
A
C
q(CIS)
Depth:
0.76 ft
Percent Full: 76.42 %
STORM
i in/hr
A
C
q Cfs
Discharge: 3.45 cfs
Critical Slope: 0.0210 ft/ft
Discharge: 0.56
cfs
Critical Slope: 0.0267 ft/ft
Full Capacity:
8.59 cfs
QMAX @.94D: 9.24 cfs
10 7.1 1.57 0.31 3.45
10 7.1 0.23 0.34 0.56
10 7.1 3.66 0.31 8.00
1.0 3.66 0.31
1.13
DITCH 8A
DITCH 813
CULVERT 8
LEVEL SPREADER 8
101864 SF
2.34 AC.
125726 SF
2.89 AC.
227590 SF
5.22 AC.
227590 SF
5.22 AC.
C
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
IMP AREAS
1166
0.03
0.9
0.02
IMP AREAS
1342
0.03
0.9
0.03
IMP AREAS
2508
0.06
0.9
0.05
IMP AREAS
2508
0.06
0.9
0.05
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
GRAVEL
0.00
0.7
0.00
OTHER
100698
2.31
0.3
0.69
Ditch 8A
OTHER
124384
2.86
0.3
0.86
Ditch 8B
OTHER
225082
5.17
0.3
1.55
Culvert 8
OTHER
225082
5.17
0.3
1.55
2.34
0.72
Lt Side Slope: 3.00:1(H:V)
Velocity: 4.39 fps
2.89
0.88
Lt Side Slope:
3.00:1(H:V)
Velocity: 4.63 fps
5.22
1.60
Diameter:
1.00 ft
Velocity: 17.59 fps
5.22
1.60
Cp..t=
0.31
Rt Side Slope: 3.00:1(H:V)
Flow Area: 1.16 sf
Cp"t=
0.31
Rt Side Slope:
3.00:1(H:V)
Flow Area: 1.36 sf
Cpmi=
0.31
Slope:
0.0833 ft/ft
Flow Area: 0.65 sf
CpM=
0.31
Manning's n: 0.030
Flow Top Width: 3.73 ft
Manning's n:
0.030
Flow Top Width: 4.04 ft
Manning's n:
0.011
Critical Slope: 0.0693 ft/ft
t=
5 min.
Channel Slope: 0.0400 ft/ft
Wetted Perimeter: 3.93 ft
t=
5 min.
Channel Slope:
0.0400 ft/ft
Wetted Perimeter: 4.25 ft
t=
5 min.
Discharge:
11.37 cfs
Critical Depth: 1.00 ft
t=
5 min.
STORM
i (in/hr)
A
C
q(CIS)
Depth: 0.62 ft
Critical Depth: 0.71 ft
STORM
i in/hr
A
C
Q cfs
Depth: 0.67 ft
Critical Depth: 0.77 ft
STORM
i in/hr
A
C
O(CIS)
Depth:
0.77 ft
Percent Full: 76.72 %
STORM
i iNhr
A
C
O Cfs
Discharge: 5.09 cfs
Critical Slope: 0.0199 ft/ft
Discharge: 6.28 cfs
Critical Slope: 0.0193 ft/ft
Full Capacity:
12.15 cfs
QMAX @.94D: 13.07 cfs
10 7.1 2.34 0.31 5.09
10 7.1 2.89 0.31 6.28
10 7.1 5.22 0.31 11.37
1.0 5.22 0.31
1.60
DITCH 9A
DITCH 913
CULVERT 9
LEVEL SPREADER 9
47028 SF
1.08 AC.
241105 SF
5.54 AC.
288133 SF
6.61 AC.
288133 SF
6.61 AC.
C
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
IMP AREAS
995.5
0.02
0.9
0.02
IMP AREAS
3272.5
0.08
0.9
0.07
IMP AREAS
4268
0.10
0.9
0.09
IMP AREAS
4268
0.10
0.9
0.09
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
GRAVEL
0.00
0.7
0.00
OTHER
46033
1.06
0.3
0.32
Ditch 9A
OTHER
237833
5.46
0.3
1.64
Ditch 913
OTHER
283865
6.52
0.3
1.95
Culvert 9
OTHER
283865
6.52
0.3
1.95
1.08
0.34
Lt Side Slope: 3.00:1(H:V)
Velocity: 3.64 fps
5.54
1.71
Lt Side Slope:
3.00:1 (H:V)
Velocity: 4.89 fps
6.61
2.04
Diameter:
1.25 ft
Velocity: 17.20 fps
6.61
2.04
Cpwt=
0.31
Rt Side Slope: 3.00:1(H:V)
Flow Area: 0.66 sf
CpW=
0.31
Rt Side Slope:
3.00:1(H:V)
Flow Area: 2.47 sf
Cpos,=
0.31
Slope:
0.0633 ft/ft
Flow Area: 0.84 sf
CpW=
0.31
Manning's n: 0.030
Flow Top Width: 2.81 ft
Manning's n:
0.030
Flow Top Width: 5.45 ft
Manning's n:
0.011
Critical Slope: 0.0330 ft/ft
t=
5 min.
Channel Slope: 0.0400 ft/ft
Wetted Perimeter: 2.97 ft
t=
5 min.
Channel Slope:
0.0300 ft/ft
Wetted Perimeter: 5.74 ft
t=
5 min.
Discharge:
14.51 cfs
Critical Depth: 1.23 ft
t=
5 min.
STORM
i in/hr
A
C
q(CIS)
Depth: 0.47 ft
Critical Depth: 0.52 ft
STORM
i in/hr
A
C
q cfs
Depth: 0.91 ft
Critical Depth: 1.00 ft
STORM
i in/hr
A
C
q (cfs)
Depth:
0.81 ft
Percent Full: 64.94 %
STORM
i in/hr
A
C
q cfs)
Discharge: 2.40 cfs
Critical Slope: 0.0220 ft/ft
Discharge: 12.11 cfs
Critical Slope: 0.0177 ft/ft
Full Capacity:
19.21 cfs
QMAX @.94D: 20.66 cfs
10 7.1 1.08 0.31 2.40
10 7.1 5.54 0.31 12.11
10 7.1 6.61 0.31 14.51
1.0 6.61 0.31
2.04
DITCH 10
CULVERT 10
LEVEL SPREADER 10
28016 SF
0.64 AC.
28016 SF
0.64 AC.
28016 SF
0.64 AC.
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
IMP AREAS
2112
0.05
0.9
0.04
IMP AREAS
2112
0.05
0.9
0.04
IMP AREAS
2112
0.05
0.9
0.04
PERM PAVER
0.00
0.3
0.00
PERM PAVER
0.00
0.3
0.00
GRAVEL
0.00
0.7
0.00
OTHER
25904
0.59
0.3
0.18
Ditch 10
OTHER
25904
0.59
0.3
0.18
Culvert 10
OTHER
25904
0.59
0.3
0.18
0.64
0.22
Lt Side Slope: 3.00:1 (H:V)
Velocity: 4.79 fps
0.64
0.22
Diameter:
1.00 ft
Velocity: 6.41 fps
0.64
0.22
Cpwt=
0.35
Rt Side Slope: 3.00:1 (H:V)
Flow Area: 0.33 sf
Cps=
0.35
Slope:
0.0200 ft/ft
Flow Area: 0.25 sf
Cppt=
0.35
Manning's n: 0.030
Flow Top Width: 1.99 ft
Manning's n:
0.011
Critical Slope: 0.0045 ft/ft
t=
5 min.
Channel Slope: 0.1100 ft/ft
Wetted Perimeter: 2.10 ft
t=
5 min.
Discharge:
1.58 cfs
Critical Depth: 0.53 ft
t=
5 min.
STORM
i in/hr
A
C
q cfs
Depth: 0.33 ft
Discharge: 1.58 cfs
Critical Depth: 0.44 ft
Critical Slope: 0.0233 ft/ft
STORM
i inmr
A
C
q cfs
Depth:
Full Capacity:
0.35 ft
5.95 cfs
Percent Full: 35.17 %
QMAX @.94D: 6.41 cfs
STORM
i in/hr
A
C
O cfs
10 7.1 0.64 0.35 1.58
10 7.1 0.64 0.35 1.58
1.0 0.64 0.35
0.22
DITCH 11
LEVEL SPREADER 11
23330 SF
0.54 AC.
23330 SF
0.54 AC.
LOCATION
S.F.
AC.
C
CA
LOCATION
S.F.
AC.
C
CA
IMP AREAS
2249.5
0.05
0.9
0.05
IMP AREAS
2249.5
0.05
0.9
0.05
PERM PAVER
0.00
0.3
0.00
GRAVEL
0.00
0.7
0.00
OTHER
21081
0.48
0.3
0.15
Ditch 11
OTHER
21081
0.48
0.3
0.15
0.54
0.19
Lt Side Slope: 3.00:1 (H:V)
Velocity: 4.76 fps
0.54
0.19
Cp0st=
0.36
Rt Side Slope: 3.00:1 (H:V)
Flow Area: 0.29 sf
C+post=
0.36
Manning's n: 0.030
Flow Top Width: 1.85 ft
t=
5 min.
Channel Slope: 0.1200 ft/ft
Wetted Perimeter: 1.95 ft
t=
5 min.
STORM
i in/hr
A
C
q cfs
Depth: 0.31 ft
Discharge: 1.36 cfs
Critical Depth: 0.42 ft
Critical Slope: 0.0237 ft/ft
STORM
i iN
A
C
q (cfs)
10 7.1 0.54 0.36 1.36
1.0
.0 0.54 0.36
0.19
N
O
N
N
J
z
J
O
C�
O
fY
+-+
N
00
Lli
C-
CO
J
J
ui
W
Z
UJ
O
U
Ir-
Q
m
O
o
=
U
H
of
oB.
Z
CLARK GATHRIGHT
No. 630
/Li/icc.
�SSIONAL
��Cl
r
O
rn
N
/O
V +
Q
>
CD
z
N
O
O
�Qa --I
4-1
0
L
U
J
i
Q
U
LLMti
0
_
LJJ
U
=
�
Q
■ (a
}� N
0
O(_0rr�
0
co
0
LL
[`
~
REVISIONS:
DATE:
03-16-21
DRAWING NUMBER:
C-1
*6
SHEET
8
OF 8