HomeMy WebLinkAboutWPO201800066-58713-Full Inspection ReportV NOTICE TO COMPLY Hand delivered Project: WP0201800066 Old Trail Village, Block 22, Lots 1-43 Operator/Contractor: Craig Builders MARCH MOUNTAIN PROPERTIES LLC Issued Date: 5/3/2021 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 434 296-5832 Under section § 17-900 of the Albemarle County Code, this is your NOTICE TO COMPLY with the requirements of the Land Disturbance Permit (or Agreement in Lieu of a Plan) for the referenced project and to immediately take corrective measures to address erosion and sediment control deficiencies on this property. This Notice to Comply is being issued because of the following deficiencies: Deficiency: No SWPPP on site Corrective Action: SWPPP must be on site Deficiency: No coverage letter on site Corrective Action: Coverage letter must be post on site Deficiency: Inspection reports not on sitr Corrective Action: Inspection reports must be done every 4 day or 5 day and 48 hrs after rain event Deficiency: Inspection reports not on site Corrective Action: SWPPP Inspection must be keep on site Deficiency: stockpile not stabilized Corrective Action: All stockpiles must be stabilized Deficiency: Rear silt fence on Avondale Lane- down sediment can leave site Corrective Action: repair all down silt fence Deficiency: Inlet protection full of sediment Corrective Action: must Clean/maintain inlet protection Deficiency: concrete washout not being used and full of debris Corrective Action: Must install adequate concrete washout Unless subsequently amended in writing by this office, it is expected all of these corrective measures will be completed by. Re -inspection of this notice to verify corrective measures will incur a $150 for land disturbing under VESCP and single-family dwelling units (§ 17-207) or a $250 fee for land disturbing under VSMP (§ 17- 208). Failure to take effective corrective measures will result in a Stop Work Order upon re -inspection. County Inspector Name: John Yerby County Inspector Phone Number: (434) 296-5832 orA1.4 Inspection Result: Notice to Comply Ljk GI'.�ti� COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP/VESCP PERMIT SITE INSPECTION REPORT Project Name: Old Trail Village, Block 22, Lots 1-43 Project/WPO Number: WP0201800066 TMP: 055EO012200000 DEQ Permit Number (if applicable): n/a Project Operator: Craig Builders Operator Telephone #: (434) 973-3362 Project Contact: MARCH MOUNTAIN PROPERTIES LLC Contact Telephone #: Contact E-Mail: Qualified Personnel (QP): William D. Craig Inspector: John Yerby Weather (Wet/Dry/Rain): Light rain Disturbed Acreage: Inspection Date & Time: 5/3/2021 11:00:00 AM Single -Family: Stage of Construction: Other Re -Inspection: Yes COVERAGE & POSTING REQUIREMENTS Compliant? Reviewed during re -inspection? Yes Comments/Description 1 Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A) Yes (9VAC25-870-310)(Alb. Co. Code §17-300, 17-302) 2 A copy of the notice of coverage letter is posted conspicuously near the No No coverage letter on site main entrance of the construction activity? (CGP Part II.C) Notice of the location of the SWPPP is posted near the site's entrance, if No SWPPP not on site 3 applicable, and information for public access is provided? (9VAC25-870- 54.G)(CGP Part II D.2 & 3) SWPPP AVAILABILITY AND CONTENTS Compliant? Reviewed during re -inspection? No Comments/Description 4 The SWPPP is on -site or made available during the inspection? (CGP Part II D.1 & 2)(9VAC25-870-54.G) 5 The SWPPP contains a signed copy of the registration statement? (CGP Part II A.1.a) 6 The SWPPP includes, upon receipt, a copy of the notice of coverage letter and the CGP? (CGP Part II A.1.b & c) The SWPPP includes a narrative description of the nature of the 7 construction activity, including the function of the project? (CGP Part II A.1.d) The SWPPP includes a legible site plan identifying all appropriate 8 measures and that includes the locations of support activities and the onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7)) Page 1 of 4 9 The SWPPP contains the name, phone number and qualifications of "Qualified Personnel" conducting inspections? (CGP Part II A.6) 10 The SWPPP contains an approved erosion and sediment control plan? (9VAC25-870-54.B)(CGP Part II.A.2) The SWPPP contains an approved stormwater management plan or an 11 existing construction site has a stormwater management plan that ensures compliance with the water quality and quantity requirements? (9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ II.0 ❑ 12 The SWPPP contains an adequate pollution prevention plan? (9VAC25- 870-54.D)(CGP Part II.A.4) The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of 13 concern, exceptional waters and the additional controls measures applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b)) 14 Delegation of Authority is provided and signed in accordance with Part III K? (CGP Part 11 A.7) 15 The SWPPP is signed and dated in accordance with Part III K? (CGP Part 11 A.8) SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES Compliant? Reviewed during inspection? No Comments/Description Is the SWPPP being amended whenever there is a change in the design, 16 construction, operation, or maintenance that has a significant effect on the discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870- 54.G) Has the SWPPP been amended if inspections or investigations by the 17 operator's qualified personnel, or by local, state or federal officials find that existing control measures are ineffective in minimizing pollutants in discharges? (CGP Part II B(2))(9VAC25-870-54.G) 18 Contractor(s) that will implement and maintain each control measure are identified? (CGP Part 11 B(3))(9VAC25-870-54.G) Have there been updates to the SWPPP when any modifications to its implementation have occurred, including a record of dates when major 19 grading activities occur, construction activities temporarily or permanently cease on a portion of the site or stabilization measures are initiated? (CGP Part 11 B.4(a))(9VAC25-870-54.G) 20 Is there documentation in the SWPPP of replaced or modified controls? (CGP Part 11 B.4(b))(9VAC25-870-54.G) 21 Is the SWPPP updated to indicate areas that have reached final stabilization? (CGP Part 11 B.4(c))(9VAC25-870-54.G) Is the SWPPP updated to indicate properties that are no longer under the 22 legal control of the operator and the dates on which the operator no longer had legal control over each property? (CGP Part II B.4(d))(9VAC25-870- 54.G) Does the SWPPP identify the date of any prohibited discharges, the 23 volume released, actions taken to minimize the impact of the release and measures taken to prevent the recurrence of any prohibited discharge? (CGP Part 11 B.4(e-f)) (9VAC25-870-54.G) 24 mendments, modifications, or updates to the SWPPP are signed in accordance with Part III K? (CGP Part II B(5))(9VAC25-870-54.G) INSPECTIONS AND CORRECTIVE ACTIONS Compliant? Reviewed during inspection? Yes Comments/Description Inspections required by the SWPPP are conducted at the required 25 frequency, including a modified frequency for impaired water(s), approved No TMDL(s), and exceptional waters when applicable? (CGP Part II F (2)) (CGP Part II A.5.b.3) 26 Inspection reports are completed and signed in accordance with CGP No Part 11 F (3-4)? (CGP Part 11 F (3-4)) Page 2 of 4 27 Corrective actions are taken consistent with the requirements of the No CGP? (CGP Part II G(1-2)) ESC AND SWM PLAN IMPLEMENTATION Compliant? Reviewed during inspection? Yes Comments/Description 28 Have stream buffers and steep slopes been protected as shown on the yes plan? Sequencing of the project is implemented in accordance with the yes 29 approved erosion and sediment control plan and stormwater management plans? (9VAC25-870-54.B and C) Have all denuded areas requiring temporary or permanent stabilization been stabilized, and have stabilization requirements for impaired waters, 30 approved TMDL(s), pollutants of concern and exceptional waters, when N/A applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25- 880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8)) (CGP II E(1-2)) Are soil stockpiles adequately stabilized with seeding and/or protected No stockpile not stabilized 31 with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II A.2(c)) (9VAC25-870-54.B) A permanent vegetative cover has been established that is uniform, N/A 32 mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Have sediment trapping facilities been constructed as the first step in land N/A Rear silt fence on Avondale Lane- down sediment can 33 disturbance activities? (9VAC 25-840-40.4) (CGP Part 11 A.2(c)) (CGP II leave site E(1-2)) (9VAC25-870-54.B) Have earthen structures been stabilized immediately after installation? N/A 34 (9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.6) Are sediment traps and basins installed in accordance with MS-6 and the 35 approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Are finished cut and fill slopes adequately stabilized to prevent or correct N/A 36 excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1- 2)) (9VAC25-870-54.B) Is concentrated runoff down cut or fill slopes contained in an adequate N/A 37 permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is adequate drainage or other protection provided for water seeps? N/A 38 (9VAC 25-840-40.9) (CGP Part 11 A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Do all operational storm sewer inlets have adequate inlet protection? No Inlet protection full of sediment 39 (9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Are stormwater conveyance channels adequately stabilized with channel N/A 40 lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is in -stream construction conducted using measures to minimize channel N/A 41 damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are temporary stream crossings of non -erodible material installed where N/A 42 applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) 43 Is necessary restabilization of in -stream construction complete? (9VAC N/A 25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B) Are utility trench operations conducted and stabilized in accordance with N/A 44 MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are soil and mud kept off paved or public roads to minimize the transport yes 45 of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) 46 Have all temporary control structures that are no longer needed been N/A removed and disturbed soil resulting from their removal permanently Page 3 of 4 stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are properties and waterways downstream from development adequately 47 protected from erosion, sediment and damage in accordance with the N/A standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840- 40.19(a-n)) 48 Permanent control measures included in the SWPPP are in place? N/A (9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a)) POLLUTION PREVENTION PLAN IMPLEMENTATION Compliant? Reviewed during inspection? Yes Comments/Description Practices are in place to prevent and respond to leaks, spills, and other releases including (i) procedures for expeditiously stopping, containing, No 49 and cleaning up spills, leaks, and other releases; and (ii) procedures for reporting leaks, spills, and other releases in accordance with Part III G? (CGP Part II A.4.e(1))(9VAC25-870-56) Practices are in place to prevent the discharge of spilled and leaked fuels N/A 50 and chemicals from vehicle fueling and maintenance activities? (CGP Part II A.4.e(2))(9VAC25-870-56) Practices are in place to prevent the discharge of soaps, solvents, 51 detergents, and wash water from construction materials, including the N/A clean-up of stucco, paint, form release oils, and curing compounds? (CGP Part II A.4.e(3))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from vehicle N/A 52 and equipment washing, wheel wash water, and other types of washing? (CGP Part II A.4.e(4))(9VAC25-870-56) Concrete wash water is directed into a leak -proof container or leak -proof No concrete washout not being used and full of debris 53 settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from N/A 54 storage, handling, and disposal of construction products, materials, and wastes? (CGP Part II A.4.e(6))(9VAC25-870-56) Practices are in place to prevent the discharge of fuels, oils, and other N/A 55 petroleum products, hazardous or toxic wastes, and sanitary wastes? (CGP Part II A.4.e(7)(9VAC25-870-56) Practices are in place to minimize any other discharge from the potential N/A 56 pollutant -generating activities not addressed above, when applicable? (CGP Part II A.4.e(8))(9VAC25-870-56) Page 4 of 4 Construction General Permit Site Inspection Report Request for Correction Action Check Regulatory Citation/Legal Occur. Observation Recommended Corrective List # Requirement* Action 25 (CGP Part II F (2)) (CGP No SWPPP on site SWPPP must be on site Part II A.5.b.3) 2 (CGP Part II.C) No coverage letter on site Coverage letter must be post on site 26 (CGP Part II F (3-4)) Inspection reports not on sitr Inspection reports must be done every 4 day or 5 day and 48 hrs after rain event 27 (CGP Part II G(1-2)) Inspection reports not on site SWPPP Inspection must be keep on site 31 (9VAC 25-840-40.2) stockpile not stabilized All stockpiles must be (CGP Part II A.2(c)) stabilized (9VAC25-870-54.B) 33 (9VAC 25-840-40.4) Rear silt fence on Avondale repair all down silt fence (CGP Part II A.2(c)) Lane- down sediment can (CGP II E(1-2)) leave site (9VAC25-870-54.B) 39 (9VAC 25-840-40.10) Inlet protection full of must Clean/maintain inlet (CGP Part II A.2(c)) sediment protection (CGP II E(1-2)) (9VAC25-870-54.B) 53 (CGP Part II A.4.e(5)) concrete washout not being Must install adequate (9VAC25-870-56) used and full of debris concrete washout Recommended 5/6/2021 Corrective Action Deadline: Targeted Re- 5/6/2021 Inspection Date: Comments: This is your second Notice to Comly - All deficiencies must be corrected by Thursday May 6, 2021 2pm or third Notice to Comly will be issued *Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880). Construction General Permit Site Inspection Photo Log Photos for Item 2 Photos for Item 4 Photo Description: Photos for Item 10 Photo Description: Photos for Item 31 20210503_111853.jpg.jpg 660.47KB Photo Description: Dirt stockpile not stabilized Photo Description: Photos for Item 33 20210503_110725.jpg.jpg 660.33KB Photo Description: Rear silt fence 20210503_110734.jpg.jpg 294.96KB Photo Description: Rear silt fence Photos for Item 39 20210503_111901.jpg.jpg 743.18KB Q rl V �Y . •per yam, Ji� Photo Description: Inlet protection Photos for Item 53 20210503_111917.jpg.jpg 613.48KB Photo Description: Concrete washout 20210503_111213.jpg.jpg 528.15KB Photo Description: Concrete washout not being used 1 10210503_111252.jpg.jpg 470.08KB photo Description: COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road d Inspection Date: 5/3/2021 County Inspector Charlottesville, Virginia 22902 434 296-5832