Megan,
RWSA has reviewed the Southwood Blocks 11 and 12 Initial Site plan dated 4/5/21 and has the following
comments.
General comments:
Was the water connection made for a previous plan already? I know we needed to close a valve before you made
a connection to the proposed waterline. I just want to make sure that was already taken care of or planned for in
the previous Southwood phase.
RWSA will require a sewer flow acceptance prior to final site plan approval.
The request will need to be sent to us by ACSA and will include the following:
• Estimated average daily dry weather sewage flow (ADDWF)
• Point of connection into RWSA system (which manhole)
• Number of units/square footage
• Estimated in-service date
Let me know if you have any questions.
Thanks,
Dyon Vega
Civil Engineer
VAN
WATER & SEVYERAIITHORITY �v
Rivanna Water & Sewer Authority
(434) 977-2970, Ext. 170
695 Moores Creek Lane
Charlottesville, VA 22902
wwwrivanna.org