VSMP Permit plan review
Project title: Starbucks— 2231 Seminole Lane
Project file number: WP0202100003
Plan preparer:
Timmons Group [Craig.Kotarski@timmons.com]
Owner or rep.:
Commercial Rentals LLC[Dhanvant.goradia@gde-inc.net]
Plan received date:
20 Jan 2021
Rev. 1 received:
15 April 2021
Date of comments:
26 Feb 2021
Rev. 1 comments:
18 May 2021
Reviewers:
Emily Cox
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is denied. The
rationale is given in the comments below. The application may be resubmitted for approval if all
of the items below are satisfactorily addressed. The VSMP application content requirements can
be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. A SWPPP was not provided with this submission. Please submit a SWPPP for review. Ensure it
has the newest registration statement (attached to this comment letter). Rev. 1: Comment
partially addressed. SWPPP provided, but registration statement not complete. Also,
Section 9, signed certification must be signed.
2. Please state where the debris from the existing building will be taken. Rev. 1: Please state
comment response on plans, "Debris must be taken to an approved landfill site".
3. The existing building appears to have a basement. Will fill material be brought to fill this in? Is
so, please specify where it will come from. Rev. 1: Please state the estimated required amount
of fill on the plans.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. A PPP was not provided with this submission. Please submit a PPP for review. Rev. 1: Comment
addressed.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is disapproved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-403.
Engineering Review Comments
Page 2 of 5
1. A stormwater management agreement needs to be executed before plan approval. Please contact
Ana Kilmer [akilmer@albemarle.org 434-296-5832 ext 32461 to complete this task. Rev. 1:
Comment not addressed.
2. Nutrient credits should be purchased before plan approval. Please contact Ana Kilmer
[akilmer@albemarle.org 434-296-5832 ext 3246] to complete this task. Rev. 1: Comment not
addressed.
3. Please add the WPO number (WP0202100003) on the cover sheet. Rev. 1: Comment addressed.
4. Topography should have been completed or field verified within the past year. Current date on
the cover sheet is April 2019. Rev. 1: Comment addressed.
5. Show the DB & PG for all existing easements and parcels. Rev. 1: Comment addressed.
6. Please provide signed and sealed retaining wall plans/details. Rev. 1: Comment not addressed.
Also, please ensure grading for the wall can occur within the limits of disturbance and the
property. Be sure to include wall tie -backs, etc.
7. [Sheet C6.0] Please review drainage divides. This line in the existing and proposed conditions
below does not appear to follow contours:
AREA = 0.413 AC
�- - _ = IMPERVIOUS = 0.08a AC
GRASS COVER = 0.325 AC
Rev. 1: Comment addressed.
8. Please provide a proposed cross section for the drainage behind the proposed wall. Rev. 1: Please
show the drainage divide used for this cross-section design.
9. Please show how the water behind the wall in the location shown below will be directed.
Concentrated water cannot be sent to the adjacent parcel.
TW —
..,. —
I3f- _
'\ BW
� eyn Rev. l
Comment addressed.
10. Please explain the note for the "2' curb cut for stormwater overflow". What overflow is it
referring to? Rev. 1: Comment addressed.
11. Please show where roof drains will be located. Rev. 1: Comment addressed.
12. Please show calculations for the existing inlet that goes to Ex-100(spread, etc). The drive thru
lane appears to drain to it through the existing channel. Rev. 1: Comment addressed.
13. The existing channel to the existing inlet that goes to Ex-100 is cracked and needs to be repaired.
Rev. 1: Comment addressed.
14. Please show the velocity of stormwater going through the channel referenced in the above
comment and shown below. Rev. 1: Comment addressed.
Engineering Review Comments
Page 3 of 5
15. Please provide more details for the proposed SWM facility. Ensure there is adequate access for
maintenance to the facility. Rev. 1: Comment partially addressed. Please show the manhole
maintenance access locations in plan view.
16. Since 9VAC25-870-66 C.2.b. was used for flood protection, please show that the existing
conveyance systems currently experience localized flooding. If they do not experience localized
flooding, C.1 & C.3 must be used. Rev. 1: Comment addressed.
17. The proposed sidewalk near the front of the site does not appear to drain to analysis point 2 as
shown in calculations (post area 2). Rev. 1: Comment addressed.
18. Please provide this checklist on the plans:
https://www.albemarle.org/home/showpubiisheddocument?id=212 Rev. 1: Comment addressed.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion
control plan content requirements can be found in County Code section 17-402.
1. Please clearly show the extent of the managed slopes. Rev. 1: Comment addressed.
2. Ensure temporary seeding, dust control and permanent seeding are shown on all phases of the
plan. Rev. 1: Comment addressed.
3. [Sheet C2.1] This tree
: removed however it appears to be within the clearing
limits. Please clarify. Oy- P' -' i °,,__ Rev. 1: Comment addressed.
4. [Sheet C2.1] Please locate and show which trees behind the building and near the proposed wall
are to remain and which are to be removed. The treeline shown on the plans does not appear to be
accurate. Rev. 1: Comment not addressed. Please show tree protection fencing to preserve
the trees you do not want to be removed.
5. [Sheet C3.0] Please specify the retaining wall area as a critical erosion area. Rev. 1: Comment
addressed.
6. [Sheet C 3.1] The limits of disturbance appear to go offsite on both adjacent parcels. Do you have
permission or an easement for this work? Rev. 1: Comment addressed.
7. Work and improvements appear to be proposed in the Virginia telephone and telegraph easement.
Engineering Review Comments
Page 4 of 5
Do you have permission for that? Rev. 1: Comment addressed.
8. Please show a stockpile, laydown/staging and parking area. Rev. 1: Comment addressed.
9. Ensure perimeter controls are sufficient. For example, how will sediment not leave the site at this
location? Rev. 1: Comment addressed.
10. Please show that silt fence is limited to areas of sheet flow with '/a acre per 100ft. Rev. 1:
Comment addressed.
11. Please consider adding an initial phase to address the removal of the existing wall and building,
and installation of the new wall as the I' step. A sediment trap may not be necessary for this
phase, especially if the existing pavement is preserved. Rev. 1: Comment addressed.
12. Please revise the sequence of construction to be site specific. Rev. 1: Comment addressed.
13. Sediment trap weir outfall cannot be directed as currently shown. Rev. 1: Comment addressed.
The VSMP permit application and all plans may be resubmitted for approval when all comments have
been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package
with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process:
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond
estimate request form and fee to the Department of Community Development. One of the plan reviewers
will prepare estimates and check parcel and easement information based on the approved plans. The
County's Management Analyst will prepare bond agreement forms, which will need to be completed by
the owner and submitted along with cash, certificates or sureties for the amounts specified. The
agreements will need to be approved and signed by the County Attorney and County Engineer. This may
take 2-4 weeks to obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emalls provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves
the application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the
remainder of the application fee. The form identifies the contractor and responsible land disturber, and
Engineering Review Comments
Page 5 of 5
the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;