HomeMy WebLinkAboutWPO202000032 Correspondence 2021-05-20SHIMP ENGINEERING, P.C.
Design Focused Engineering
May 20, 2021
David James
County of Albemarle
Department of Community Development
401 McIntire Road, North Wing
Charlottesville, Virginia 22902
RE: Response Letter #4 for WP02020-321300 Richmond Road — Flow Automotive
Dear David,
Thank you for your review of the V SMP permit plan for 1300 Richmond Road — Flow Automotive. This
letter contains responses to County comments dated May 13, 2021. Our responses are as follows:
D. Stormwater Management Plan (SWMP)
4. Detention basin:
f. (Rev. 1/2) Provide seepage control: design anti -seep collars for barrel. (Rev. 3) Not
currently addressed: Provide something from DEQ that will allow this exception based
upon corrugations of the pipe used. Show the 4:1 paretic line from the riser weir. (Rev. 4)
Clarify placement dimension of anti -seep device.
RESPONSE: The profile has been updated to match the dimensions and a station of
10+20 is noted for the installation location.
It. (Rev. 3) Embankment width should be 8' min. See comment 4.a. (Rev. 4) Provide an 8'
embankment. Please submit a flood development permit (FDP) for minimal impact.
Minimal disturbance to floodplain is expected.
RESPONSE: We have reviewed the Zoning Ordinance and find that the fill in the
floodplain is not permitted as a by -right use for the purpose of constructing a stormwater
pond embankment. The purpose of the embankment width is to provide adequate
structural stability given the depth of water that may pond behind the structure. In this
instance, the actual amount of fill is approximately 2.6'. Given this minimal amount of
fill, the width of embankment is more than adequate structurally in this situation. Further,
Section A-3 of Appendix A of 2013 BMP Regulations states that the requirements are not
mandatory for embankments which have a fill height of less than 3' as measured from the
downstream toe of fill to top of dam which is the case here. Note that in this instance, the
pond does not span a stream or watercourse, therefore, the measurement would not be
from the pipe to the top of dam. Practically, the fill component of the embankment is only
subject to pressure from ponding to a depth of 5.5" for the 100-year storm. It is possible
that in my lifetime, the fill section of the embankment will never experience pressure
from the basin filling during a rainfall event. With all of the above taken into account, I
am certain that the fill portion of the structure will be more than adequate in width, and
have certified these drawings accordingly.
8. Contact Ana Kilmer regarding the Nutrient Credit Agreement.
(Rev. 1/2/3/4) Comment still valid. Nutrient credit purchase is needed prior to plan
approval.
912 E. High Sr. Charlottesville, VA 22902 1434.227.5140 1 shimp-engineering.com
RESPONSE: We are ready to purchase the credits. Please confirm that Ana Kilmer has approved
the nutrient credit purchase contract that was submitted on 04-14-2021.
11. (Rev. 3/4) Record the SWM facility easements with a deed & plat prior to approval.
RESPONSE: The SWM maintenance agreement has been recorded. We are waiting on the County to
provide us with the facility easement deed.
12. (Rev. 4) Sheet C10: Correct the profile detailidimensions.
a. Add flit compaction note for embankment.
RESPONSE: Note requiring 95% compaction has been added to the profile.
b. Add note to key in fill material to existing slope.
RESPONSE: As noted above, the embankment is very minimal in depth and keying in
the fill with a cut-off trench or similar measure would be unnecessary in this
circumstance. A note has been added to require the scarification of the existing surface
prior to placement of fill.
c. Str. A5a — Clarify what ex. standpipe? Show invert out connection.
RESPONSE: The existing outlet control located in the manhole originally aligns with the
15" concrete pipe that is to be removed. With the proposed utilities, the existing outlet
control needs to be rotated within the manhole to match the new outlet pipe alignment.
The existing outlet pipe ran in the northwest direction, while the new outlet pipe runs in
the northeast direction, so the standpipe will need to be rotated to match this new
direction.
13. (Rev. 4) Provide more information/analysis of the channel to stream [ACDSM, p. 7].
a. Verify report pre -flows (i.e. 16.70cfs vs. 27.97 cfs don't match).
RESPONSE: This table has been moved to sheet C15 to match the other stormwater
conveyance calculations. We updated the table based on current flows and channel
conditions.
b. Provide you are meeting Channel protection under Part IIB — Provide the stone
diameter lining required and what is provided for channel.
RESPONSE: The rip -rap channel is existing and is in sufficient condition to convey
stormwater per Part IIB regulations, specifically, by meeting the energy balance equation
at the point of outfall at the top of the man-made rip -rap channel in accordance with
9VAC25-870-66-B. Lb. Since run-off complies with energy balance rates, there is no
further required analysis for erosion at this manmade channel. However, we still
confirmed that the existing channel still met channel protection by analyzed this
downstream rip -rap channel in the Stormwater Conveyance Channel on C 15 to show that
the channel does not have erosive velocities. The 7.4 fps velocity within the channel is
not erosive for a rip -rap channel.
c. Provide that you are meeting flood protection under Part IIB — Show the 10-yr is
contained in the channel to the LOA, or floodplain.
RESPONSE: We meet downstream flood protection by discharging through a stable
channel into a mapped floodplain per 9VAC25-870-66-C-3.c. This known flooding is the
mapped 100-year Zone AE floodplain. Since the pipe outfall is within a mapped
floodplain, the outfall meets the limits of analysis for flood protection, and no further
analysis is required. However, in good practice, we confirmed that the existing rip -rap
912 E. High St. Charlottesville, VA 22902 1434.227,5140 1 shimp-engineering.com
channel into which the pond is discharged can convey the 10-yr flow without
overtopping. As shown on the calculation table on C15, it is adequate for this depth of
flow.
E. Erosion and Sediment Control Plan (ESCP)
11. (Rev. 4) Add to note that the device will have to outlet to bottom of slope if there's any
concentrated release.
RESPONSE: The design of the silt sacks is to allow for seepage out of the entire bag at a slow
rate, which would by design, not discharge in a concentrated form. We understand that over the
length of the slope, water seeping from the sack may become shallow concentrated flow down the
natural slope, however, that would match the current condition for any run-off over the slope,
even without development occurring. The slope in question is to remain undisturbed with native
vegetation, so we do not anticipate any erosion issues. Thus, no note was added. If the silt sack
discharge was released at the bottom of the slope, it would have to be piped, which would
concentrate the flow and cause more concern for runoff, and we cannot specify this in good
practice.
If you have any questions or concerns about these revisions, please feel free to contact me at
Justin @ shimp-en ing eering corn or by phone at 434-227-5140.
Regards,
Justin Shimp
Shimp Engineering, P.C.
912 E. High St.. Charlottesville, VA 22902 1434.227.51401 shlmp-engineenrig.rom