VSMP Permit Plan Review
Project title:
Albemarle High School Modular Classroom Additions
Project file number.
WPO-2021-00028
Plan preparer:
Timmons Group
Bryan Cichocki, PE [bryan.cichocki@timmons.com]
Owner or rep.:
Albemarle County School Board
Joe Letteri Uletteri@k12albemarle.org]
Plan received date:
10 May 2021
Date of comments:
24 May 2021
Reviewer:
Matt Wentland
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is denied. The
rationale is given in the comments below. The VSMP application content requirements can be
found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. The DEQ Registration Statement will need to be completed and signed. This data may
have been lost when the plans were uploaded.
2. Section 9, Signed Certification, will need to be signed.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. The PPP appears adequate at this time.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is disapproved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-
403.
This plan cannot be approved until the 0.43 Ib/yr of nutrient credits have been
purchased. Please contact Ana Kilmer prior to purchasing credits. DEQ has also updated
their credit purchasing requirements, located in 9VAC25-900-91(B)3. Since this project
drains to impacted streams, the credits will need to be purchased from a bank located in
the same 8-digit HUC. The process goes upstream, then HUC12, HUC10, and HUC8, at
Engineering Review Comments
Page 2 of 3
which point the Ivy Creek credit bank is in the same HUC8. The credits for this project
and the other modular classroom projects can be purchased as one lump sum if desired,
just contact Ana before doing so.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is approved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. The ESC plan appears adequate at this time.
The VSMP permit application and all plans may be resubmitted for approval when all comments
have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete
permit package with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a
meeting to discuss this review.
Process:
After approval, erosion and sediment control and stormwater management improvements must
be bonded. The bonding process begins when the plan is approved, and the applicant submits a
bond estimate request form and fee to the Department of Community Development. A plan
reviewer will prepare estimates and check parcel and easement information based on the
approved plans. The County's Management Analyst will prepare bond agreement forms, which
will need to be completed by the owner and submitted along with cash, certificates or sureties
for the amounts specified. The agreements will need to be approved and signed by the County
Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and
forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and
recorded. The County's Management Analyst or other staff will prepare the forms and check for
ownership and signature information. The completed forms will need to be submitted to the
County, who will record the agreement.
After bonding and agreements are complete, county staff enters project information in a DEQ
database for state application processing, if a DEQ permit is required. DEQ reviews the
application information based on local VSMP authority approval. At this time, the DEQ portion
of the application fees will need to be paid directly to the state. For fastest processing, this is
done electronically with the emails provided on the application. DEQ should notify applicants
Engineering Review Comments
Page 3 of 3
with instructions on how to pay fees. When DEQ approves the application, they will issue a
permit coverage letter, which must be posted at the construction site.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction
conference. Applicants must complete the request for a pre -construction conference form and
pay the remainder of the application fee. The form identifies the contractor and responsible land
disturber, and the fee remaining to be paid. This will be checked by county staff, and upon
approval, a pre -construction conference will be scheduled with the County inspector. At the pre -
construction conference, should everything proceed satisfactorily, ajoint VSMP and grading
permit will be issued by the County so that work may begin.
County forms can be found on the county website forms center under engineering;
httDs://www.albemarle.ora/aovernment/com m un itv-develoDment/aDDIv-for/ena i neeri na-aDDl ications
File: WPO201900062 Southwood Village Amendment 1 review comments 05-03-21.docx