Loading...
HomeMy WebLinkAboutWPO202100026 Review Comments WPO VSMP 2021-06-08V 401 McIntire Road, North Wing County of Albemarle Charlottesville, VA 22902-4579 Telephone:434-296-5832 COMMUNITY DEVELOPMENT DEPARTMENT WWW.ALBEMARLE.ORG VSMP Permit Plan Review Project title: Brook Hill River Park Phase 1 River Access Improvements Project file number: WPO202100026 Plan preparer: Anhold Landscape Architects David Anhold [david@anholdla.com] Owner or rep.: Albemarlte County Parks and Recreation Bob Crickenberger [bcricke@albemarle.org] Plan received date: 03 May 2021 Date of comments: 08 June 2021 Reviewer: Name County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is denied/approved. The rationale is given in the comments below. The VSMP application content requirements can be found in County Code section 17-401. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary. 1. Please provide a SWPPP. Ensure it includes the latest DEQ registration statement (attached to this comment letter for your use). Also, a SWPPP template can be found here: https://www.albemarle.org/home/showdocument?id=166 B. Pollution Prevention Plan (PPP) The PPP content requirements can be found in County Code section 17-404. 1. Please provide a PPP. C. Stormwater Management Plan (SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is denied, and the reasons are provided in the comments below. The stormwater management plan content requirements can be found in County Code section 17- 403. 1. Floodplain development permit, FDP202100006, must be approved before this WPO can be approved. 2. Provide Army Corps of Engineers approval for this work. 3. Cover sheet should say WPO202100026, not SDP201900080. 4. Professional seal should be signed and dated. Engineering Review Comments Page 2 of 3 5. Topographic information should be at least field verified within the past year. Date on the plans is from 2019. Also, site note #7 on the cover sheet says contour data is from County GIS. Please clarify. 6. Please show the stream buffer extending to the limits of the flood plain per county code 17-600-B. 7. Forest and open space must be recorded in an easement with a deed before this WPO plan can be approved. Please note that this will restrict future development in this area (See next comment). 8. Please add the following note on the plan and plat, "The SWM Forest and Open Space Easement is subject to the guidance set forth by DEQ in the Virginia Stormwater Management Program. The areas will remain undisturbed in a natural, vegetated state, except for activities as approved by the local program authority, such as forest management, control of invasive species, replanting and revegetating, passive recreation (e.g., trails), and limited bush hogging to maintain desired vegetative community (but no more than four times a year)." 9. Please provide a narrative which outlines compliance with 9VAC25-970-66. This plan does not comply with channel protection as it outfalls to a natural channel. 10. Please ensure the critical slopes are shown on all applicable sheets. 11. Handicap (ADA) spaces must be paved. 12. Critical slopes waiver is required for the final site plan. D. Erosion and Sediment Control Plan (ESCP) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is disapproved, and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17-402. 1. Please ensure the critical slopes are shown on all applicable sheets. Site plan does not appear to show them. 2. Per County Code 18-4.3.3, slopes shall not be steeper than a 2:1 (50 percent) slope. 3. Please show a stockpile location and laydown area. 4. Per VESCH 3.05, Please note that Extra -strength filter fabric shall be used for the proposed silt fence in the ditch application with a maximum 3-foot spacing of posts. Consider using check dams, VESCH 3.20 instead. The VSMP permit application and all plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a completed application form. Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Process: Engineering Review Comments Page 3 of 3 After approval, erosion and sediment control and stormwater management improvements must be bonded. The bonding process begins when the plan is approved, and the applicant submits a bond estimate request form and fee to the Department of Community Development. A plan reviewer will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted to the County, who will record the agreement. After bonding and agreements are complete, county staff enters project information in a DEQ database for state application processing, if a DEQ permit is required. DEQ reviews the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter, which must be posted at the construction site. After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Applicants must complete the request for a pre -construction conference form and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre - construction conference, should everything proceed satisfactorily, ajoint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; https://www.al bemarle.org/govern ment/community-development/apply-for/engineering-applications