HomeMy WebLinkAboutSUB202100070 Correspondence 2021-06-10Jordan Land Design, LLC
18267 Channel Ridge Ct. Leesburg, VA 20176
(571)233-5830 Fax(703) 9974444
June 8, 2021
Mr. Kevin McCollum, Planner
County of Albemarle, Department of Community Development
401 McIntire Road
Charlottesville, VA 22902
RE: SUB202100070 CARTER MOUNTAIN SUBDIVISION - RURAL SUBDIVISION
Dear Mr. McCollum:
In response to the comments received for Carter Mountain Subdivision — Rural Subdivision, please
find the comments addressed as follows.
1. [14-302 (A)(4), 14-302 (A)(5), and 14-303 (L)] Please include any instrument reference
for Carters Mountain Rd.
Response:
Deed reference added with this submission.
2. [14-302(B)] Please clarify the Zoning information in Note 2 to state that the property is zoned
"Rural Areas."
Response:
Rural Areas added to note with this submission.
3. [14-309 & 14-3101 Soil evaluations & Health director approval of septic systems. Please
provide the soils evaluations for the proposed lots. This information will be reviewed by the Health
Department and Health Director approval is required prior to fmal plat approval. Please provide
the location of the primary and reserve drainfield on each proposed lot to be submitted to the Health
Department for review.
Response:
To be submitted under separate cover.
4. [14-308.1] A Tier II Groundwater Assessment has been initiated for this application.
Results of the assessment will be forwarded to the applicant once it is completed.
Response:
Thank you.
5. [General Comment] Please revise the numbering of the notes on Sheet 1. Number 5 appears
twice on two separate notes.
Response:
Corrected with this submission.
6. [14-302(A)] According to the Plat recorded in Deed Book 4016 pages 674-679 this parcel
contains five (5) development rights. In order to create this subdivision each proposed lot will need
to be allocated at least one (1) development right. Since four (4) lots are being created that are all
less than 21 acres, four (4) development rights are being used. There are 5 development rights
total. So, the remaining or leftover development right needs to be allocated to one of these
proposed lots, or it can remain as unassigned and the future property owners can determine
CARTER MOUNTAIN SUBDIVSION
Page 2 of 2
where it gets allocated at a future date. This additional development right could theoretically
be used to add an additional dwelling or further divide one of these proposed parcels in the future.
Please update Note 9 on Sheet 1 accordingly.
Response:
Rights of second lot given to lot 4 with this submission,
7. [14-303(0)1 Please provide a signature panel for the "Agent for the Board of
Supervisors." Include a signature line, date, and a statement that this has been approved for
recordation.
Response:
Signature panel added with this submission.
8. [14-302(B)l Albemarle County GIS data suggests that the property is not within the Water
Protection Ordinance Stream Buffer or Flood Plain. Please revise Note 7 on Sheet 1.
Response:
Note 7 revised with this submission.
9. [14-302(8)1 Albemarle County GIS data indicates that this property is not within an Ag/For
District. Please revise Note 11 on Sheet 1.
Response:
Note 11 revised with this submission.
10. 114-302(B)l Please add a date of last revision.
Response:
Revision date added to revision block.
If you have any questions, please call me at (571) 233-5830.