RE: UVA Discovery Drive — Final Site Plan Review — SDP202000009 - Comment Response
Letter
Dear Ms. Kanellopoulos:
We have reviewed all of your comments from June 4, 2021 and made the applicable revisions.
Please find our responses to your comments below in bold lettering.
Planning (Tori Kanellopoulos):
All comments are based on the revise submittal showing a revised 55,220 SF building on TMP
32-6R (the 10,745 SF building addition on TMP 32-19E remained the same):
1. [18-4.20/18-4.6.3] Front setback. The upper right corner of the proposed 55,200 SF building
does not appear to meet the 10' minimum front setback requirement. It appears to be approx.
9.5' from the sidewalk. Either the building or sidewalk must be adjusted so that the building is at
least 10' from the sidewalk (as the sidewalk is outside the ROW). A determination request has
been made to Zoning, to ensure the front setback requirement shown on Sheet C0.0 of this site
plan is consistent with previous approvals under ZMA2005-3. A determination will be forwarded
once received.
a. Rev. 1: Addressed. Building has been shifted to be at least 10' setback.
2. [18-32.5.2 and 18-32.6.2] Contents of a final site plan.
a. Include the following requirement on Sheet C0.0 (Planning acknowledges that this note
is on Sheets C4.0 and C4.1, however it does not appear to be on C0.0): All water and
sewer facilities to be dedicated to public use and the easements for those facilities and
shall be identified by a statement that the facilities are to be dedicated to the Albemarle
County Service Authority.
i. Rev. 1: Addressed.
b. Include the owners/zoning of all abutting parcels. It does not appear that TMP 32-9G
was included.
I. Rev. 1: Addressed.
ENGINEERING I DESIGN I TECHNOLOGY
c. Consistently label the required 150' and 50' buffers (per ZMA2005-3) on each sheet,
including the existing conditions and demo plan sheets.
i. Rev. 1: Addressed.
d. More clearly label (arrows pointing to each side) the access easement for Discovery
Drive.
i. Rev. 1: Addressed.
e. Revise the phasing plan to show the proposed phasing with the completed site (that is,
show the building addition, new building, and new parking). Keep the existing conditions
in grey and show the proposed building/parking with darker lines.
i. Rev. 1: Addressed.
f. Add a note to sheet C0.0 that the site will be developed in two phases.
i. Rev. 1: Addressed.
g. The 'Research Park Total Buildout' table on Sheet C0.0 Should only show approved SF,
plus the SF that will be approved with this site plan. It does not appear that Encompass
is approved (no final site plan approved). Additionally, it appears 65,965 SF is added
with this site plan (not 87,455). Please clarify.
i. Rev. 1: Addressed.
3. [18-4.12.5 and 18-4.12.6] Parking location and required spaces.
a. All parking must be on the same lot unless a request per 18-4.12.8 is made. Therefore,
the parking calculations should reflect the number of spaces shown on each lot (32-19E,
6R, and 19H). For example, 39 spaces are shown on TMP 32-6R, so the new 55,220 SF
building should show a parking calculation of 39 spaces.
i. Rev. 1: Addressed.
b. Clarify the number of spaces for TMP 32-19H. The site plan indicates 134 spaces are
existing. It appears 3-4 are being lost with emergency access/site changes. However, the
total proposed parking for this site is listed as 100 spaces.
i. Rev. 1: Addressed.
c. Clarify the required spaces for TMP 32-6R and the office/laboratory new building. For
Industrial uses, one space per employee should be provided. The rezoning for this site
allows for other parking calculations to be considered and used. Additional information
should be provided to indicate why no parking should be allocated for the laboratory
use. Alternatively, some of the 39 spaces not being used for the office (18) could count
toward this use.
i. Rev. 1: Addressed.
4. [18-4.17] Lighting. The Light Loss Factor must be 1.00. Also, include the required 3,000
lumens/full cutoff note on the lighting plan (not just on Sheet C4.0).
a. Rev. 1: Addressed.
5. [18-32.7.9.4] Contents of a landscape plan. Include a completed and signed conservation
checklist.
a. Rev. 1: Addressed.
6. [Advisory Comment: ZMA2005-3 Proffers] Per Proffer 5.4(A) approved with ZMA2005-3,
the required Phase I road improvements must be completed prior to build -out of phase I
(with some exceptions). Based on this submittal, 488, 151 sq. ft. have been constructed,
and 718,130 will be approved after this site plan and the UVA Encompass Site Plan
(SDP201900047) are approved. The build -out square footage of Phase 1, per Proffer 5.3,
is 635,000 sq. ft. for uses with access to Lewis and Clark Drive and 980,000 sq. ft. total.
Many of the proffers per 5.4(A) have been completed. This is an advisory comment only.
Acknowledged.
7. [Future Application Comments]
a. WPO2019-60 will need to be approved prior to final site plan approval.
i. Rev. 1: Comment remains.
ii. Rev. 2: Comment addressed. WP02019-60 has been approved by Engineering.
b. 18-32.5.2 and 18-32.6.2 and 18-32.7.4.2 Easements. Any new or adjusted
easements will require an approved easement plat prior to final site plan
approval. Based on this submittal, there appear to only be ACSA easements
proposed. However, if any other easements are required (such as per the WPO),
they will need to be recorded and approved with an easement plat prior to site
plan approval.
i. Rev. 1: Comment remains. Planning defers to Engineering on whether there is
need for new/revised easements.
ii. Rev. 2: Addressed.
Engineering (David James):
1. No objection.
Inspection (Betty Slough):
1. Number 29 General notes, wrong code edition, change to 2015 edition and 09 edition of
ANSI.
This note has been updated to reflect the correct edition years.
Comment partially remains. General note 29: 2015 Virginia Construction Code, note
2009.
This note has been updated.
Fire/Rescue (Shawn Maddox):
1. No objection.
ACSA (Richard Nelson):
1. The 2" threaded plug for the 1" service should be removed.
This plug has been removed.
2. The proposed FHA should be 2' behind the curb.
The FHA has been shifted to be 2' behind the curb.
3. Attached is the water/sewer date sheets from previous submissions. We have since
updated the sheets, now on our website. Can you have this updated on the new sheets?
Looking through my email, it looks like the hydraulic capacity was missing from the
water sheet.
Water and Sewer Data Sheets have been updated and provided directly to Richard Nelson at
ACSA.
VDOT Comments:
1. No objection.
Acknowledged.
We have included PDF copies of the plans and wall design for your review. If you have any
questions or comments, please feel free to give me a call at 434.295.5624.
Sincerely,
Anna Fontaine, P.E.