HomeMy WebLinkAboutZMA200700006 Staff Report 2007-09-130 ALg�
JRGINZP
COUNTY OF ALBEMARLE
PLANNING STAFF REPORT SUMMARY
Project Name: ZMA 2007-006 Three Notch'd
Staff: Rebecca Ragsdale
Center
Critical Slopes Waiver & Waiver of 20 Foot Buffer
Planning Commission Public Hearing:
Board of Supervisors Public Hearing:
September 18, 2007
December 12, 2007
Owners: Jeffrey Sprouse
Applicant: Jo Higgins, Project Development Ltd.
Acreage: approx. 2.3 acres
Rezone from: LI Light Industrial
TMP: TMP 56A3-9 and 56A3-11
By -right use: Industrial, office, and limited commercial
uses (no residential use)
Magisterial District: White Hall
Proffers: Yes
Proposal: Rezone to PDSC Planned District
Requested # of Dwelling Units: None
Shopping Center to redevelop the property into
two buildings, a total of 40,460 square feet.
DA (Development Area): Community of Crozet
Comp. Plan Designation: CT 5 Urban Center in the
Crozet Master Plan
Character of Property: Currently developed
Use of Surrounding Properties: Music Today, self
with a 11/2 story frame house as a restaurant and
storage, and undeveloped
a two-story cinder block building with
service/office uses
Factors Favorable:
Factors Unfavorable:
1. The rezoning is consistent with the Crozet
1. A conceptual grading plan has not yet been
Master Plan recommendations.
provided but the applicant is working to respond to
this request.
2. The applicant has provided an application
2. Minor revisions and notes are needed to proffers
plan that meets Neighborhood Model
and the application plan.
design expectations.
However, the applicant has indicated they intend to
provide revised proffers and an application plan to
address these outstanding issues listed.
RECOMMENDATION:
Staff can recommend approval only after conceptual grading is provided that satisfactorily addresses
Entrance Corridor and critical slopes considerations and minor revisions to the application plan and
proffers are made.
STAFF PERSON:
PLANNING COMMISSION:
BOARD OF SUPERVISORS
REBECCA RAGSDALE
SEPTEMBER 18, 2007
DECEMBER 12, 2007
ZMA 07-06 THREE NOTCH'D CENTER
Critical Slopes Waiver & Section 21.7.3 20 Waiver of 20 Foot Buffer Zone Adjacent to
Residential/Rural Districts
PETITIONS
PROJECT: ZMA 2007-006 Three Notch'd Center
PROPOSAL: Rezone 2.3 from LI Light Industrial, which allows industrial, office, and limited
commercial uses (no residential use)to PD -SC Planned Development Shopping Center, which
allows for shopping centers, retail sales and service uses; and residential by special use permit
(15 units/ acre). The proposal is to redevelop the site with two office/commercial buildings with a
total of 40,500 square feet.
PROFFERS: Yes
EXISTING COMPREHENSIVE PLAN LAND USE/DENSITY: CT5 Neighborhood Center in the
Crozet Master Plan which allows for a mix of uses and residential types at net densities of up to
12 units per acre; up to 18 units per acre if in a mixed use setting.
ENTRANCE CORRIDOR: Yes
LOCATION: 5368, 5374, and 5382 Three Notch'd Road, located on the northside of Three
Notch'd Road approx 500 feet west of its intersection with Parkview Drive.
TAX MAP/PARCEL: Tax Map 56A3, Parcels 9 and 11
MAGISTERIAL DISTRICT: White Hall
CHARACTER OF THE AREA
The site is approximately 2.3 acres in size and is zoned LI Light Industrial. It is located in
Community of Crozet along Route 240/Three Notch'd Road. There are currently two
aging structures, a 1928 house that is currently occupied by Teresa's cafe, and a two-
story cinderblock building with uses such as video rental, laundermat, and some offices
above. Adjoining the site to the west is the Crozet Self Storage recently constructed and
Music Today and Star Hill occupy the former Con -Agra complex across Route 240. Most
surrounding properties are zoned industrial, with the exception of the Rural Area zoned
undeveloped property to the east. (Attachment A -Aerial, Attachment B -Zoning Map)
SPECIFICS OF PROPOSAL
The applicant has provided an application plan (dated August 15, 2007) which shows
two buildings, including one three-story building and one two-story building totaling a
maximum of 40,500 square feet, with 140 surface parking spaces located to the side
and rear, along with green space and outdoor gathering areas surrounding the buildings.
(Attachment E -Application Plan) Existing buildings on the site will be demolished.
The proposal as shown on the plan is with the approval of a parking reduction by the
Zoning Administrator, in accordance with Section 4.12.2 c (1) of the Zoning Ordinance.
This approval constitutes an 8.5% reduction in required parking based on the following:
o Within'/4 mile, there are customers who may walk to this site rather than drive.
ZMA 07 -Go Three Notcn u t_enLer
Planning Commission 9/18/07 Board of Supervisors December 12, 2007
o They will be providing a sidewalk with this development that will link to other
properties as well as will link the buildings onsite.
o There is an expectation that the employees who work in the offices will also be
customers of the proposed retail establishments on the property, thereby
reducing some of the need for parking for both uses.
APPLICANT'S JUSTIFICATION FOR THE REQUEST
The applicant has indicated that redevelopment of this site will enhance the Route 240
corridor, allow for neighborhood services near employment centers, and will provide for
better consistency between zoning on the site and the Crozet Master Plan, while better
accommodating the existing uses that are already occurring on the site.
PLANNING AND ZONING HISTORY
The site has been zoned LI Light Industrial since the adoption of the 1980 Zoning
Ordinance. Prior to 1980, it was zoned R2 Residential. LI districts are primarily intended
to permit industries, offices and limited commercial uses which are compatible with and
do not detract from surrounding districts. Supporting commercial uses are allowed by
special use permit and are limited in terms of expansion opportunities and must bear a
direct relationship to the industrial uses.
COMPREHENSIVE PLAN:
Conformity with the Crozet Master Plan
The Crozet Master Plan (CMP) designates this property as CT 5 Urban Center in a
Neighborhood. CT5 areas are intended to serve as focal points with a mix of uses,
residential types and amenities. Office, service, and retail uses are supported by the
CMP in these areas. The master plan recognizes the existing Neighborhood Center and
supports, with additional areas designated CT5, the retention and expansion of that
Neighborhood Center. This center serves the nearby employment uses such as Music
Today and Star Hill, along with existing and anticipated future residential uses in the
area.
ZMA 07-06 Three Notch'd Center
Planning Commission 9/18/07 Board of Supervisors December 12, 2007
Location
of subject
site
Open Space Plan/Green Infrastructure Map: The Green Infrastructure
Map does not identify any significant environmental resources on the site. A stream
buffer is shown for protection on the adjoining property to the north, TMP 56A3-7.
Neighborhood Model
The Neighborhood Model describes the more "urban" form of development desired for
the Development Areas. The following is an assessment of this proposal's consistency
with the Neighborhood Model's 12 principles:
Pedestrian
Pedestrian connections have been well provided both internal to the
Orientation
site, connecting buildings and parking areas, and to the external
sidewalk along Three Notch'd Road. Staff has recommended an
additional pedestrian connection to the applicant as a minor revision to
the plan, reflecting a central pedestrian way through the center of the
parking lot at the rear of the building, which the applicant has
addressed. This principle is met.
Neighborhood
The applicant is proposing improvements along the frontage of the
Friendly Streets
property adjacent to Route 240, including a planting strip with
and Paths
landscaping and street tress. This principle is met.
Interconnected
The applicant has provided for a shared entrance and interconnection
Streets and
to the adjoining property to the east. The property to the west is the self
Transportation
storage facility and a place where a connection can occur has been
Networks
provided should the property redevelop in to a use without security
concerns. This principle is met.
Parks and Open
Outdoor green space and gathering spaces appropriate for the
Space
proposed use have been provided on the application plan. This
principle is met.
ZMA 07-06 Three Notch'd Center
Planning Commission 9/18/07 Board of Supervisors December 12, 2007
Neighborhood
This site is designated as a neighborhood focal point in the master plan
Centers
and the neighborhood service uses proposed are appropriate. This
principle is met.
Buildings and
Buildings are proposed for 2 -stories and 3 -stories in height, consistent
Spaces of
with the Crozet Master Plan recommendations in CT 5 for buildings at
Human Scale
1.5-3.5 stories from street level. The ARB has no objection to the height
of the buildings either. This principle is met.
Relegated
The majority of the parking on the plan is located behind the building,
Parking
with the exception of 23 spaces located to the side of the building,
behind the fagade, to the west of the site. This principle is met.
Mixture of Uses
The Crozet Master Plan anticipates a range of uses in the CT 5 areas
of this neighborhood, including all attached, detached, and mixed use
residential, along with hotels, corporate & neighborhood offices, shop,
and civic uses. Since this rezoning will allow for a range of
neighborhood scale shops and offices, and allows for an SP for
residential in the future, this principle is met.
Mixture of
No residential uses are proposed and the Crozet Master Plan supports
Housing Types
buildings with entirely non-residential uses. Staff did suggest to the
and Affordability
applicant that apartments above the retail should be considered and
although they are not proposed with this rezoning, the special use
permit for residential has not been excluded from the permitted uses on
the property.
Redevelopment
This project represents redevelopment of an older site to accommodate
existing businesses better and allow for additional square footage. The
applicant has indicated that redevelopment of this site will bring the
project into conformity with current ordinance requirements for parking
areas, landscaping, and stormwater management.
Site Planning
The project area does have some small areas of critical slopes and a
that Respects
waiver has been submitted and approval is recommended by the
Terrain
County Engineer. However, conceptual grading has not been provided.
The County Engineer does not anticipate issues but staff has asked the
applicant to provide the grading plan so that it can be verified that there
are no unexpected concerns with the Engineer and ARB.
The applicant has indicated, the existing grading on Sheet 2 of 3
reflects the preliminary grading. The existing grades across the front of
the site are consistent with the elevation of Rt. 240, to the west the
grades match the existing new self storage facility, and with the sewer
line across the rear of the site - it prevents any significant lowering of
the grades.
ZMA 07-06 Three Notch'd Center
Planning Commission 9/18/07 Board of Supervisors December 12, 2007
Clear Boundaries This property is located within the Crozet Development area and does
with the Rural not border the boundary with the Rural Area, which is located 1/4 mile to
Areas the north and east of this property. This principle is met.
Relationship between the application and the purpose and intent of the requested
zoning district
The Zoning Ordinance indicates PD -SC districts are created and may hereafter be
established by amendment of the zoning map to permit the development of
neighborhood, community and regional shopping centers in accordance with standards
set forth in the comprehensive plan. PD -SC districts are intended to serve areas not
conveniently and adequately provided with a broad range of commercial and service
facilities. Regulations provided are intended to encourage planned commercial centers
with carefully organized buildings, service areas, parking areas and landscaped areas.
PD -SC districts shall be located in areas served by both public water and sewer
systems; provided that neighborhood shopping centers may be permitted in areas not
served by public water and/or public sewer systems where adequate alternative water
supply and/or sewerage disposal systems are available. PD -SC districts shall have
direct access to public streets adequate to accommodate traffic generated by the
development.
Staff believes that the intent and expectations listed here for PDSC districts are met with
this rezoning proposal as it is serving an employment area with commercial services.
Anticipated impact on public facilities and services
Streets — The development will generate approximately 2,800 vehicle trips per day as
provided in the applicant's trip generation estimates. (Attachment E) VDOT and the
County Engineer have reviewed the information and the applicant has provided for a
right turn lane into the site. VDOT has indicated that a left turn lane is not necessary with
the rezoning. The layout provided is adequate and the details and other comments we
provided on the rezoning request can be handled with the site plan. (See VDOT
comments -Attachment D)
Schools — No residential uses are proposed so no impacts to schools are anticipated.
Fire, Rescue, Police — The Crozet Volunteer Fire Station and the Western Albemarle
Rescue Station provide fire and rescue services to the area. The planned Ivy Area
Station will also augment services provide by the two existing fire and rescue stations
Crozet. Albemarle County Fifth Street Office Building is contains the County's Police
Department, although the police patrol all areas of the County. Current policy of police
services recommends an average response time of 10 minutes for all Development
Areas. To this end, police satellite offices are recommended within a service sector to
help achieve these desired response times to all police emergency calls. The possibility
of an additional fire/rescue/police station is under consideration for the area in 2012.
ZMA 07-06 Three Notch'd Center
Planning Commission 9/18/07 Board of Supervisors December 12, 2007
Utilities — Albemarle County Service Authority indicates that water and sewer service is
available to the site. Comments are provided as Attachment E)
Stormwater Management — The County Engineer has not indicated any concerns with
the proposed stormwater management concepts provided and has suggested that there
are opportunities, through proffers, to provide enhanced stormwater on the site through
the applicant proffering to provide at -the -source treatment in addition to the end -of -pipe
treatment currently on the plan, such as a depressed parking island with biofilter
plantings, or to proffer removal rate targets 20% better than might otherwise be required.
Staff is still discussing this with the applicant as to what they are willing to provide in
proffers.
Anticipated impact on cultural and historic resources
Existing buildings on the site will be demolished with this proposal. The submittal has
been reviewed for possible impact to known historic (fifty years old or older) architectural
resources and known or potential archaeological resources with the following comments
provided by the Historic Preservation Planner:
The Virginia Department of Historic Resources' (DHR) has not surveyed the
property under review for the presence of historic resources.
2. County Real Estate records indicate the presence of a single family dwelling,
located on TMP 56A3-9, and built c. 1928. Since this building is more than fifty
(50) years old, it is considered historic. A second building is also located on the
property, but no build date was found. Both buildings are currently used for
commercial businesses.
Based upon the proposed plan and the information, documentation of the existing
buildings is desired, but as this will occur with the Crozet Historic Resources Survey, it is
not necessary for the applicant to proffer this. The comments have been satisfied.
Entrance Corridor Impacts
The applicant presented this proposal informally to the ARB on March 5, 2007 and the
design planner has reviewed the rezoning application for impacts to the Entrance
Corridor, considering the input received from the ARB. The applicant submitted revisions
addressing these comments and the Design Planner has indicated that the treatment
along the EC appears to be acceptable and specific comments have been provided.
(Attachment F) most of which can be addressed at the site plan stage as they relate to
building materials and architecture or specific site plan details. The following revisions to
the application plan are necessary prior to approval of the rezoning:
o Conceptual grading
o Clarify the "Evergreen screening trees for EC Corridor" note or delete it from the
plan.
o Revise the plan to indicate that landscaping will be provided along the east side
of the shared driveway, to the satisfaction of the ARB, with a landscape
easement provided by the adjacent owner.
o Add the following note to the plan: "Landscaping shown on this conceptual plan
does not meet ARB Guidelines and will be redesigned at preliminary and final
ZMA 07-06 Three Notch'd Center
Planning Commission 9/18/07 Board of Supervisors December 12, 2007
site plan review to meet the Guidelines, as required by the ARB, with additional
planting area provided, as necessary, to accommodate ARB requirements."
Anticipated impact on nearby and surrounding properties
Adjacent properties are industrial in character and intended to continue as employment
uses. The property to the east that is undeveloped is shown as CT 5 also in the Crozet
Master Plan so no detrimental impacts are anticipated to surrounding properties.
Public need and justification for the change
The change in zoning is consistent with the CT5 designation of the Land Use Plan and
provides neighborhood scale uses within walking distance of existing employment uses
and anticipated future residential.
PROFFERS
The applicant provided proffers to exclude undesired land uses on the site. There are no
substantive issues with the proffers and minor format revisions are needed by the
County Attorney. (Attachment G) Additional proffers to address storm water are
recommended by staff and the applicant has indicated a willingness to include that in the
proffers.
WAIVERS
CRITICAL SLOPES WAIVER
The critical slope waiver request has been reviewed. The engineering analysis of the
request follows:
Description of critical slope area and proposed disturbance:
The slopes in question are at the edges of the proposed site where the existing site
slopes down to a wooded drainage swale. It is assumed that the applicant will be
placing more constructed slopes in this area at the edges of the proposed parking area
and travelways. However, there is no proposed grading on the application plan.
The applicant has indicated, the existing grading on Sheet 2 of 3 reflects the preliminary
grading. The existing grades across the front of the site are consistent with the elevation
of RT240, to the West the grades match the existing new self storage facility, and with
the sewer line across the rear of the site - it prevents any significant lowering of the
grades.
Areas
Acres
Total site
2.3 acres on two parcels
Critical slopes
0.09
4% of site
Critical slopes disturbed
0.09
100% of critical
slopes
Exemptions to critical slopes waivers for driveways, roads and utilities without
reasonable alternative locations:
This disturbance is not exempt.
Compliance with Zoning Ordinance 18-4.2:
ZMA 07-06 Three Notch'd Center
Planning Commission 9/18/07 Board of Supervisors December 12, 2007
"movement of soil and rock"
Proper slope construction, control of drainage, and vegetative stabilization will
prevent any movement of soil.
"excessive stormwater runoff"
Stormwater runoff will be controlled by the stormwater management plan as required
by the Water Protection Ordinance.
"siltation
Inspection and bonding by the County will ensure siltation control during
construction. Proper stabilization and maintenance will ensure long term stability.
"loss of aesthetic resource"
This area is visible from the surrounding businesses and Rt.240. Much of these
slopes appear to be from prior site disturbances.
"septic effluent"
This neighborhood is serviced by public sewer.
Based on the review above, there do not appear to be any engineering concerns which
prohibit the disturbance of the critical slopes as shown. However, the application plan
should be updated to show conceptual grading that satisfactorily addresses critical slope
considerations before the waiver is approved.
WAIVER OF SECTION 21.7.3-20 FOOT BUFFER ZONE ADJACENT TO
RESIDENTIAL/RURAL DISTRICTS
Section 21.7.3 of the Ordinance requires a 20 foot undisturbed buffer adjacent to
residential zoning districts:
21.7.3 Buffer zone adjacent to residential and rural areas districts: No construction
activity including grading or clearing of vegetation shall occur closer than twenty (20) feet
to any residential or rural areas district. Screening shall be provided as required in
section 32.7.9. Except, the commission may waive this requirement in a particular case
where it has been demonstrated that grading or clearing is necessary or would result in
an improved site design, provided that:
a. Minimum screening requirements are met; and
b. Existing landscaping in excess of minimum requirements is substantially
restored. (Added 7-10-85)
The concept plan submitted with the special use permit requires a modification of
Section 21.7.3 to allow for the shared entrance and interconnection to the adjoining
property to the east. This property is currently zoned RA Rural Areas and this ordinance
section is still applicable. Staff does not believe that a buffer or screening requirements
are needed for the proposed development against this property. It is anticipated that this
adjoining property will be rezoned, according to the Crozet Master Plan which
designates it CT 5 as well.
Addressing sections 27.1.3 of the Zoning Ordinance, minimum screening requirements
noted in Section 21.7.3(a) are those that would be established by the Commission in
granting this modification. Staff does not recommend screen but supports the ARB
recommendation that the eastern portion of the shared drive be landscaped with its initial
construction. There is minimal existing landscaping in need of restoration (Section
21.7.3(b)) and the applicant will be providing additional landscaping and working with the
ZMA 07-06 Three Notch'd Center
Planning Commission 9/18/07 Board of Supervisors December 12, 2007
ARB at the time of site plan review and approval.
SUMMARY:
Staff has identified the following factors favorable to this rezoning and special use
permits requested:
1. The rezoning is consistent with the Crozet Master Plan recommendations.
2. The applicant has provided an application plan that meets Neighborhood Model
design expectations.
Staff has not identified factors unfavorable to this request:
1. A conceptual grading plan has not yet been provided but the applicant is working to
respond to this request.
2. Minor revisions and notes are needed to proffers and the application plan.
However, the applicant has indicated they intend to provide revised proffers and an
application plan to address these outstanding issues listed.
RECOMMENDED ACTIONS:
ZMA 2007-006
Staff can recommend approval only after the applicant provides conceptual
grading that satisfactorily addresses Entrance Corridor and critical slopes
considerations and provides the following revisions to the application plan and
proffers:
o Clarify the "Evergreen screening trees for EC Corridor" note or delete it from the
plan.
o Provide conceptual grading.
o Provide for the additional pedestrian way central to the parking lot.
o Revise the plan to indicate that landscaping will be provided along the east side
of the shared driveway, to the satisfaction of the ARB, with a landscape
easement provided by the adjacent owner.
o Add the following note to the plan: "Landscaping shown on this conceptual plan
does not meet ARB Guidelines and will be redesigned at preliminary and final
site plan review to meet the Guidelines, as required by the ARB, with additional
planting area provided, as necessary, to accommodate ARB requirements."
o Minor format revisions are needed by the County Attorney to the proffers.
o Additional proffers to address storm water are recommended by staff and the
applicant has indicated a willingness to include that in the proffers.
Critical Slopes Waiver
Staff cannot recommend approval of the critical slopes waiver until conceptual
grading has been provided with the application plan and satisfactorily addresses
critical slopes considerations. The applicant has responded to this request and
will be providing this information.
ZMA 07-06 Three Notch'd Center 10
Planning Commission 9/18/07 Board of Supervisors December 12, 2007
WAIVER OF SECTION 21.7.3-20 FOOT BUFFER ZONE ADJACENT TO
RESIDENTIAL/RURAL DISTRICTS
Recommended Action:
Staff recommends approval of the waiver of Section 21.7.3 to allow construction activity
including, grading or clearing of vegetation closer than twenty (20) feet to the adjoining
Rural Area zoned property line to the east, in accordance with the concept plan provided
as Attachment H. Provided that:
1. A landscape easement is obtained by the adjoining property owner and
landscaping is provided to the satisfaction of the ARB on the adjoining
property to the east.
ATTACHMENTS
A. Location Map -Aerial
B. Zoning Map
C. Traffic Impact Analysis
D. VDOT comments
E. Albemarle County Service Authority comments via e-mail from Gary
Whelan
F. Entrance Corridor comments provided by Margaret Maliszewski, dated
August 29, 2007
G. Proffers
H. Application Plan titled Three Notch'd Center, dated August 15, 2007,
and prepared by NP Engineering
I. Crozet Master Plan Place Type & Built Infrastructure Map
ZMA 07-06 Three Notch'd Center 11
Planning Commission 9/18/07 Board of Supervisors December 12, 2007