HomeMy WebLinkAboutARB202000035 Review Comments 2020-09-23 •
Margaret Maliszewski
From: Margaret Maliszewski
Sent: Wednesday, September 23, 2020 1:29 PM
To: Jeff Carter
Cc: Jessica Hood
Subject: RE:W4 Car Wash ARB submittal
Jeff,
Thanks for this information. It looks like you've addressed the outstanding items. I can schedule this for ARB review on
November 2. It will be a virtual meeting. Does that date work for you?
Regarding the canopies,the length really depends on the location and relationship to the building, so eliminating one or
more may not be required. We'll make a recommendation on this in our staff report. My first concerns were the height
of the canopy and the size of the fascia.The drawing you submitted shows that those proposed sizes meet the
guidelines, so that is a good start.
Margaret
From: Margaret Maliszewski
Sent:Thursday,September 17, 2020 5:20 PM
To:Jeff Carter<jeff@carterengineering.net>
Cc:Jessica Hood <jessica@carterengineering.net>
Subject: RE: W4 Car Wash ARB submittal
Thanks,Jeff. I will take a look and get back to you.
Margaret
From:Jeff Carter<ieff@carterengineering.net>
Sent:Wednesday, September 16, 2020 4:04 PM
To: Margaret Maliszewski<MMaliszewski@albemarle.org>
Cc:Jessica Hood<jessica@carterengineering.net>
Subject: RE: W4 Car Wash ARB submittal
CAUTION:This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Margaret,
I have finally obtained the information requested below. Please review and let me know if you need anything
further.
Sincerely,
Je Car,ter,
:- jefffff ^�ineerirt4.net
Carter Engineering Consultants Inc.
3651 Mars Heil Road. Suite 2000
Watlonsville,GA 30677
CARTER office 770-725-1200ext 204
ENGINEERING cell 706'255'3766
7^N5JITAP.T c xnvw carterenoineerina.net
From: Margaret Maliszewski <MMaliszewski@albemarle.org>
Sent:Tuesday, August 25, 2020 2:12 PM
To:Jeff Carter<jeff@carterengineering.net>
Cc:Jessica Hood <jessica@carterengineering.net>
Subject: RE: W4 Car Wash ARB submittal
Jeff,
A few things are outstanding:
1. Can you confirm that the canopies, vacuum equipment, auto entry and gate all have a black finish?Yes, I can
confirm they all have a black finish
2. Manufacturer's cut sheets for the proposed light fixtures are still needed. Please see attached files marked
Canopy Lights and outdoor light fixtures for cut sheets
3. The canopy photograph suggests that the canopies are more substantial than I had imagined.They look much
like fuel pump canopies,for which the ARB has design guidelines (see last 2 pages of attached document). We
will need line drawing elevations of the canopies, with dimensions, for review. Please see attached file named
canopy detail. It looks like the maximum length of a canopy is 66 feet per the county requirements so we
removed the canopy closest to the building and also shortened one other one to the maximum length. The car
wash looks much better with the canopies but if the county would rather not have them we can remove as
needed.
4. Dimensioned line drawings are also needed for the auto entry and gate.This should be available from the
manufacturer, right? Please see attached file named equipment cut sheets
5. Can you provide manufacturer's cut sheets showing dimensions for the vacuum equipment? Please see attached
file named equipment cut sheets
If you'd like to discuss, please let me know.
Thanks.
Margaret
From:Jeff Carter<jeff@carterengineering.net>
Sent:Thursday, August 20, 2020 7:36 AM
To: Margaret Maliszewski<MMaliszewski@albemarle.org>
Cc:Jessica Hood <jessica@carterengineering.net>
Subject: RE: W4 Car Wash ARB submittal
CAUTION:This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Margaret,
2
Good morning. I think we are finally in a position to respond to your email below from April 10th regarding the
W4 car wash development. In your previous email you had the attached "missing items" highlighted from our
last submittal. The attached "ARB response comments" document reflects where the missing items are
addressed. Will you please take a look and let me know if we can proceed to the next meeting? If not, I would
request a conference call or zoom meeting so that we can discuss what is left. Thanks for your help.
Sincerely,
Fr- --411 Jeff Carter,PE
1eff carterer, lneeriro net
0
Carter Engineering Consultants Inc.
L A 3651 Mars Hill Road Suite 2000
Watiunsville GA 30677
CARTER office 7-723 6�� 204
ENGINEERING
CONSULTANTS W►W carterenaineenna net
From: Margaret Maliszewski <MMaliszewski@albemarle.org>
Sent: Friday, April 10, 2020 2:09 PM
To:Jessica Hood <jessica@carterengineering.net>;gdb@fbglaw.com
Cc:Jeff Carter<jeff@carterengineering.net>
Subject: RE:W4 Car Wash ARB submittal
Good afternoon, everyone.
Although we have not yet confirmed an ARB meeting schedule for the near future, I have been reviewing your recent
submittal and drafting the staff report that will eventually go to the ARB for review. I have found that a number of items
requested by the ARB were not included in your submittal. I think it would be unproductive to move forward to the ARB
without this information having been provided and considered in the staff report. I have outlined the items that are
missing below and in the attached document. If I've overlooked any of this in the current submittal, please just let me
know where to find it.
From the final review checklist, the following items are missing:
1. Top and bottom retaining wall elevations.
2. Wall-mounted light locations on the photometric plan and fixtures listed in the light fixture schedule.
3. Cut sheets for wall and site lights included in the site plan set(not separate, stand-alone sheets).
4. Architectural elevations drawn to scale.
For items missing from the October 21, 2019 ARB action letter, please see the highlighted sections of the attachment.
Once you've had a chance to review this information, please contact me to discuss next steps.
Thanks.
Margaret
From: Margaret Maliszewski
Sent:Tuesday, March 24, 2020 4:59 PM
To:Jessica Hood <iessica@carterengineering.net>
Cc:Jeff Carter<jeff@carterengineering.net>
Subject: RE: W4 Car Wash ARB submittal
3
Jessica,
Your submittal was received on March 9. On the standard schedule,that corresponds to an April 20 ARB meeting. We
don't yet have any direction on public meetings beyond April 5. When I learn more, I will contact you.
Thanks.
Margaret
From:Jessica Hood <jessica@carterengineering.net>
Sent:Tuesday, March 24, 2020 4:18 PM
To: Margaret Maliszewski<MMaliszewski@albemarle.org>
Cc:Jeff Carter<jeff@carterengineering.net>
Subject: RE: W4 Car Wash ARB submittal
CAUTION:This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Good afternoon, Margaret,
What's the typical turnaround for review? I understand there may be a delay due to the current pandemic. Please
provide an update when you have a moment.
Thanks,
J eyyi,ca- Hoad.
Carter Engineering Consultants,Inc.
3651 Mars Hill Road,Suite 2000
Watkinsville,GA 30677
Office:(770)725-1200, Extension 222
Mobile:(706)594-8784
Fax:(770)725-1204
www.carterengineering.net
From: Margaret Maliszewski<MMaliszewski@albemarle.org>
Sent:Tuesday, March 17, 2020 5:35 PM
To:Jessica Hood<jessica@carterengineering.net>
Subject: RE:W4 Car Wash ARB submittal
Thank you so much for your quick response.
From:Jessica Hood <jessica@carterengineering.net>
Sent:Tuesday, March 17,2020 5:32 PM
To: Margaret Maliszewski<MMaliszewski@albemarle.org>
Cc:Gregory 0. DeBacker<gdb@fbglaw.com>;Jeff Carter<jeff@carterengineering.net>;Justin Hendley
<justin@w4wash.com>
Subject: RE:W4 Car Wash ARB submittal
CAUTION:This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
4
Good afternoon, Margaret,
Please see below and attached to access the requested drawings. Let me know if you have any questions or require
additional information.
19016W4D Site Development Plans
Thanks,
Je.syizia, How
Carter Engineering Consultants,Inc.
3651 Mars Hill Road,Suite 2000
Watkinsville,GA 30677
Office:(770)725-1200, Extension 222
Mobile:(706)594-8784
Fax:(770)725-1204
www.carterengineering.net
From: Margaret Maliszewski [mailto:MMaliszewski@albemarle.org]
Sent:Tuesday, March 17, 2020 1:20 PM
To:Gregory 0. DeBacker<gdb@fbglaw.com>
Subject:W4 Car Wash ARB submittal
[EXTERNAL]
Greg,
Thank you for your ARB submittal for the W4 Development Car Wash.To facilitate review, would you please provide
PDFs of the submittal (both site and architectural drawings)?
Thanks.
Margaret
Margaret Maliszewski, Chief of Planning/Resource Management
Albemarle County Department of Community Development
401 McIntire Road
Charlottesville,VA 22902
434-296-5832 x3276