HomeMy WebLinkAboutARB201900100 Correspondence 2020-03-09 (2) 6/4/2020 Xfinity Connect FW_ARB-2019-100 Scottsville Elementary Addition Updated Drawings,ARB Staff Comments Printout
Brent Nelson<bnelson@albemarle.org> 6/4/2020 5 58 PM
FW: ARB-2019-100 Scottsville Elementary Addition Updated Drawings, ARB
Staff Comments
To brentnelson707@comcastnet<brentnelson707@comcast net>
Brent W. Nelson
Senior Planner
Albemarle County
Community Development
434-296-5832 ext. 3438
bnelson@albemarle.org
From:Frank Hancock<Frank.Hancock timmons.com>
Sent:Monday,March 9,2020 9:13 AM
To:Tyler Whitney<1whitney@gparch.com>,Brent Nelson<bnelson@albemarle.org>
Subject:RE:ARB-2019-100 Scottsville Elementary Addition Updated Drawings,ARB Staff Comments
CAUTION:This message originated outside the County of Albemarle email system.DO NOT CLICK on links or open attachments unless you are sure
the content is safe.
Brent,
Thank you for the clarification
Frank
Frank Hancock,PLA
Senior Project Manager
TIMMONS GROUP I www.timmons,com
From:Tyler Whitney<twhitney-@gparch.conl>
Sent:Monday,March 9,2020 9.12 AM
To:Brent Nelson<bnelson@albemarle.org>;Frank Hancock<Frank.Hancock@Lmmons.conp
Subject:RE'ARB-2019-100 Scottsville Elementary Addition Updated Drawings,ARB Staff Comments
Hi Brent,
Thank you for the update. I will get you a new printed set shortly
Best,
Tyler
From.Brent Nelson<bnelson@8lbemarle.org>
Sent:Friday,March 6,2020 5.43 PM
To:frank.hancock@timmons.com
Cc:Tyler Whitney<twhitney@gparch.com>
Subject:FIN ARB-2019-100 Scottsville Elementary Addition Updated Drawings,ARB Staff Comments
Frank- I am sending this email as a follow up to our phone conversation earlier this week regarding Comment 5 in my email below to
Tyler Whitney.
You can disregard that comment.As discussed,I thought you were providing frontage trees along the Route 20 right-of-way in the original
submission.Instead,you are using the term"frontage"to describe the location of trees along an interior parking lot edge Because this is
an amendment to an existing site,we are not requiring you address the Entrance Corridor guideline requinng trees along the Route 20
right-of-way.
I assume your voicemail earlier today was in regard to this
Brent W. Nelson
Senior Planner
Albemarle County
https://connect.xfinity.com/appsuite/v=7.10.0-29.20200507.032519/print.html?pnnt_1591308758251 1/4
6/4/2020 Xfinity Connect FW ARB-2019-100 Scottsville Elementary Addition Updated nrawings,ARB Staff Comments Pnntout
Community Development
434-296-5832 ext. 3438
bnelson@albemarle.org
From:Brent Nelson
Sent:Friday,February 21,2020 11 10 AM
To:Tyler Whitney<twhitney.@gparch.corn>
Subject:RE ARB-2019-100 Scottsville Elementary Addition Updated Drawings,ARB Staff Comments
Hi Tyler - I have completed my review of your latest resubmission.My comments are below in color following
my original comments of 09-30-2019(in black).
1 Revise Sheet E3 Exterior Elevations to include the 5 proposed building materials shown on the materials board submitted with this application
02-21-2020 Addressed with the latest submission
2.Revise Sheet DI Electrical Site Plan to
a.Indicate the lumens value for each proposed fixture
b.Indicate the mounting height for the wall-mount fixture
C.Indicate the fixture tilt for each proposed fixture Fixtures emitting 3,000 or more lumens shall have a zero-degree tilt
d.Indicate the tightmg maintenance factor(LLF).An LLF of 1 is required by ordinance.
02-21-2020 All addressed with the latest submission
Note Lighting schedule on Sheet D1 contains the wording"or acceptable equal by Lithonia or Hubbell"Revise the drawing by
removing this wording.Any change to the lighting will require additional review and an approved site plan amendment.
3.Revise Sheet 04 Electrical Site Plan-Photometrics to
a.Show side,front and rear property lines Add additional footcandle values to demonstrate that lighting values do not exceed 0 5 footcandles
at the property lines as required by ordinance
b.Include the standard lighting note.Each outdoor luminaire equipped with a lamp that emits 3,000 or more initial lumens shall be alit!!cutoff
luminaire and shall be arranged or shielded to reflect light away from adjoining residential districts and away from adjacent roads The
spillover of lighting from luminaires onto public roads and property in residential or rural areas zoning districts shall not exceed one-half
footcandle.
02-21-2020 (a&b)Addressed with the latest submission
4.The two(2)light pole-mount fixture is labeled as LED-A in the Lighting Fixture Schedule(Sheet DI Electrical Site Plan)and as LED-B on the
Electrical Site Plan Revise the drawings to correct this discrepancy.
02-21-2020 Addressed with the latest submission
5.Sheet C9 Landscape Notes and Details indicates one(I)proposed large shade tree and 6 existing large shade trees along the Entrance Comdor road
Revise drawings to show location of these existing and proposed Entrance Corridor trees
No drawing was provided addressing this comment.
6 Add a latest revision date to all revised sheets
None of the drawings provided were dated No original drawing date and no revision dates.
With your next resubmission,please provide a complete set of all drawing sheets provided in your original August 26,2019 ARB
submission.All drawings should contain original drawing dates and all revision dates.
Please contact me should you have any questions.
Brent W. Nelson
Senior Planner
Albemarle County
Community Development
434-296-5832 ext. 3438
bnelson@albemarle.org
From:Tyler Whitney<twhitney@goarch.com>
Sent:Friday,February 14,2020 4:31 PM
To:Brent Nelson<bnelson@albemarie.org>
Subject:RE.ARB-2019-100 Scottsville Elementary Addition Updated Drawings
CAUTION:This message originated outside the County of Albemarle email system.DO NOT CLICK on links or open attachments unless you are sure
the content is safe.
https://connect.xfinity.com/appsulte/v=7.10.0-29.20200507.032519/print.html?pnnt_1591308758251 2/4
6/4/2020 Xfinity Connect FW_ARB-2019-100 Scottsville Elementary Addition Updated Drawings,ARB Staff Comments Printout
Hi Brent,
Just wanted to check in. Hard copy drawings should have been delivered on 1/30 Are the updated drawings under review? Our civil
engineer just got back site plan review comments and wanted to check the status of the CofA.
Thanks,
Tyler
From:Brent Nelson<bnelson@albemarle.org>
Sent:Wednesday,January 29,2020 5 51 PM
To.Tyler Whitney<twhitney@gparch.com>
Cc:Margaret Maliszewski<MMaliszewski@a albemarle.org>
Subject:RE:ARB-2019-100 Scottsville Elementary Addition Updated Drawings
Hi Tyler - Thank you for your email As noted in my comment letter of September 30,2019(snap shot below),please provide one set of
the revised drawings along with a memo summarizing the revisions you've made.The drawings and memo can be left with our
receptionist in COMMUNITY DEVELOPMENT.Please include a transmittal indicating the project is ARB 2019-100,Scottsville
Elementary Additions and Improvements and that it goes to me.I will commence my review after receiving this
From Comment Letter(09-30-2019)
Within 15 days of the date of this letter,please reply(email is acceptable)indicating whether you will or will not proceed
with these revisions.If you choose not to proceed with these revisions,staff will be unable to approve your application.If
you choose to proceed with the revisions,please forward me one set of revised drawings together with a memo
summarizing the revisions you've made. Your decision to make the revisions will suspend the 60-day review period
associated with your original submittal.I expect to complete the review of your revised proposal within 2 weeks of your
re-submittal
Thanks,
Brent W. Nelson
Senior Planner
Albemarle County
Community Development
434-296-5832 ext. 3438
bnelson@albemarle.org
From:Tyler Whitney<twhitney@gparch.com>
Sent:Monday,January 27,2020 5 38 PM
To:Brent Nelson<bnelson.@albemarle.org>,Margaret Maliszewski<MMaliszewski(alalbemarie.org>;Tim Padalino
< adalino albemarle.org>
Cc:Walter Hams<wharrisc albemarle.or9>,Steve Mundt<smundt@gparch.com>
Subject:ARB-2019-100 Scottsville Elementary Addition Updated Drawings
CAUTION:This message originated outside the County of Albemarle email system.DO NOT CLICK on links or open attachments unless you are sure
the content is safe.
Hi Brent,
Here are updated drawings for the county-wide Certificate of Appropriateness for the addition at Scottsville Elementary based upon
your last round of comments Let me know if you need anything else
Thanks,
Tyler Whitney,AIA,LEED AP BD+C
Architect
GP
Caws fl O PMflK
Mr:434 270 0144 I Email:twhitney@gparch.corn
123 East Main Street,Second Floor I Charlottesville,VA 22902
Calverton I Tysons I Charlottesville
https://connect.>unity.com/appsuite/v=7.10.0-29.20200507.032519/print.html?print_1591308758251 3/4
6/4/2020 Xfinity Connect FW ARB-2019-100 Scottsville Elementary Addition Updated nrawings,ARB Staff Comments Printout
Creative Collaboration I Sustainable Solutions I Engaging Environments