MEMORANDUM OF COMMENT REVIEW
To: Margaret Maliszewski
2300 Hunters Way Hardware Store&Coffee Shop
Job: 1924 -2300 Hunters Way Hardware Store&Coffee Shop
Transmitted for: Comment Review for ARB Submission
Comments from 09/16/19 ARB Review:
1. Provide window glass specs confirming that Visible Light Transmittance
(VLT) is not below 40% and Visible Light Reflectance (VLR) is not above
30%. Provide a sample for review.
a. Copy of window spec sheet attached to this memo.
2. Revise the dumpster detail to indicate that the brick will match the red brick
of the building closest to the EC.
a. Dumpster enclosure to match brick on building - Lawrenceville
Carter's Grove brick
3. See landscape recommendations.
4. Ensure that vehicles awaiting repair will be fully screened from the EC.
a. Landscaping elements and elevation of site fully screen vehicles
awaiting repair.
5. Add the standard mechanical equipment note to the architectural drawings.
a. Noted on elevations sheets.
6. Add one 2 i" caliper tree along the 4-space parking row located south of the
dumpster enclosure. Provide shrubs, 24" high at planting, along this
perimeter.
a. Landscaping added to EC side of building,per Shimp Engineering.
1108 EAST HIGH STREET, CHARLOTTESVILLE, VA 22902
PHONE: 434.971.7202 I FAX: 434.295.2413 I HENNINGSENKESTNER.COM
(Yj? 12{1,
HENNINGSEN KESTNER
ARCHITECTS
7. Provide landscaping consisting of trees and shrubs along the EC side of the
building,between the building and the drive-thru lane.
a. Landscaping added to EC side of building,per Shimp Engineering.
8. Provide landscaping consisting of trees and shrubs along the EC side of the
drive-thru lane. Coordinate landscaping with utilities.
a. Landscaping added to EC side of building, per Shimp Engineering.
9. Revise the utilitarian guard rail to a guard rail that has an appropriate
appearance for the EC.
a. See attached Response Letter #3 from Shimp Engineering dated
July 10, 2020.
10.Show on the plan the locations of all drive-thru related equipment and
provide design details for all equipment.
a. No other equipment will be installed for the drive-thru. The only
element is the drive-thru window, covered by a canopy that is
part of the architectural design.
11.Make the extents of the new stormwater management facility easement
easily legible on the grading and utility plan.
12.Consider adjusting the drive thru lane and grading to make the lane more
level and provide a better base for the building, and to allow a zone to screen
the guard rail,and to slightly ease the slope to the EC.
a. Grading, entrance lanes, rail screening all properly addressed
and changed by Shimp Engineering.
13.Provide a rendered elevation of the west side.
a. Provided attached to this memo.
14.Consider maintaining a regular fenestration pattern and explore alternate
sign locations.
a. Fenestration has been adjusted to a more consistent
architectural rhythm. Alternate sign locations will be reviews
pending tenant specifics.
Emailed to Margaret Maliszewski on September 14, 2020