June 11, 1997
Ted Glass
Roudabush, Gale, &Associates, Inc.
914 Monticello Road
Charlottesville,VA 22901
Re: SDP 97-037 Forest Lakes North Car Wash Preliminary Site Plan
Dear Mr. Glass:
The Planning Commission approved the preliminary site development plan referenced above
with your one-way modification request at its June 10, 1997 meeting. The Planning Commission
has requested to review the final site plan.
The approval of the preliminary site plan is valid for one year in accordance with Zoning
Ordinance Section 32.4.3.1. Expiration will require a new application to be filed and processed.
The final site plan will be subject to all final site plan requirements (Zoning Ordinance Section
32.6), in addition to the following conditions:.
1. Prior to submittal of the final site development plan for Planning Commission review,the
applicant shall obtain tentative approvals of the following conditions:
a. Planning Department approval of:
1. Landscape plan.
b. Engineering Department approval to include:
1. Labeling the existing alignment and roadway features for Timberwood
Parkway (i.e.,pavement width, entrance to Food Lion,pavement
markings, etc,);
2. Approval of grading plans and computations;
3. Approval of stormwater detention plans and computations;
4. Virginia Department of Transportation [VDOT] approval of plans,
drainage computations, and Fortune Park Road plans or connection to a
state-maintained road. Per VDOT:
a. Fortune Park Road has not been approved,however an existing
entrance from Timberwood Parkway is adequate to serve this site;
b. For Fortune Park Road, a traffic analysis will be required to
determine the level of service at build-out at Timberwood Parkway
and Worth Crossing.
c. Albemarle County Building Code and Zoning Services approval to include:
1. Rearrange the employee parking so that it is 16 feet wide or barrier
free accessibility. (This parking space does not have to be marked as
accessible on the pavement nor have a standing sign indicating
accessibility.
d. Albemarle County Service Authority approval to include:
1. The meter shall be located in a grassy area within the existing easement of
the 12" water main;
2. Provide revised water usage numbers so the meter can be sized;
3. Increase the fall away from the exit site of the wash bays. The general
note regarding grading the site so runoff will not enter the bays is
inadequate.
e. Albemarle County Architectural Review Board issuance of a Certificate of
Appropriateness.
f. Each wash bay shall contain a wash basin. Water collected in the basin, whether
first recycled or not, shall be routed to the sanitary sewer system (or it shall be
discharged in a manner approved by the department of Health or any other
applicable state or federal agency.)
2. The Planning Department shall not accept submittal of the final site plan for signature
until the until tentative approvals for the following conditions have been obtained:
a. Engineering Department approval of:
1. Erosion and Sediment Control Plan.
You are responsible for contacting all applicable departments and agencies, and satisfying the
conditions for approval of the final site plan. When the final site plan meets all requirements and
conditions, and tentative approval has been granted by each department or agency, a final
submittal must be made to the Department of Planning and Community Development in order to
schedule the plan to be signed at the next Site Review Committee meeting.
Please contact me at your earliest convenience if you have any questions or require additional
information.
Sincerely,��pp
Eric L Morrisette
Planner