May 24, 2012
Eugene Ryang
Water Street Studio
111 Third St. SE
Charlottesville,VA 22902
RE: LOR#2 to SDP-2011-082 (Birdwood Golf Practice Tee)
Dear Mr. Ryang,
This letter approves your submitted Letter of Revision for the above referenced site plan. Since
this letter of revision is associated with the original Birdwood Golf site plan,but is included as
part of redevelopment occurring on and near the Boar's Head Sports Club complex in
conjunction with SDP-2011-082,this letter will be filed with both site plans. The letter of
revision proposes the following changes:
1) All grading and drainage changes associated with WPO-2012-044
This is the second(2nd)Letter of Revision for this site. Three(3) Letters of Revision are allowed,
after which all required changes must be submitted as a site plan amendment. Since the original
site plan number for Birdwood Golf Course is SDP-1981-012,up to 3 Letters of Revision may
be submitted for Birdwood Golf Course,but tied to SDP-2011-082. Up to 3 separate Letters of
Revision may be submitted for the Boar's Head Sports Club, also tied to SDP-2011-082. A total
of 6 Letters of Revision may be tied to SDP-2011-082,but only 3 of these may apply to the
Birdwood Golf Course. The other 3 must be tied to the Boar's Head Sports Club.
Sincerely,
Joanne Tu Purtsezova, Planner
1
Philip Custer
From: Philip Custer
Sent: Friday, July 20,2012 3.13 PM
To: 'Schooley, Christopher(cds7c)', Eugene Ryang, 'Alan Franklin'
Cc: Joanne Tu Purtsezova, Mark Hopkins
Subject: Boars Head SWM Amendment(WPO-2011-00103)
Good afternoon,
I have reviewed the SWM plan amendment for Boars Head Squash Facility(WPO-2011-00063), received 12 July 2012.
The changes to Biofilter C are approved on the condition that a Minor Site Plan Amendment is approved. At the time
that the minor amendment approval is received,3 updated copies of this SWM plan amendment should be provided to
me so that I may pass it off to the inspector.
In the minor amendment application, please include profiles for the new and revised drainage facilities. If a change in
horizontal or vertical direction is necessary for the pipe underneath the sidewalk,a manhole structure will be required
A curb and a curb inlet will likely be needed now that the ditch is being removed. This may result in the water line
having to be relocated. The site plan will also need to show and label a detectable warning surface at each handicap
ramp.
Please let me know if you have any questions.
Thanks,
Phil
296-5832 x3072
1
PROJECT NAME: Boar's Head Sports Club
FILE#' WPO-2011-00103
DATE APPROVED: 14-May-12
Item Unit Amount Unit Cost Subtotal ,
trees&shrubs ball/burlap planted 8 $100.00 $800 (only bonded the minimum planting requireme
underdrain stone cubic yard 37 $17.00 $629 biofilter surface area/27*1'depth
stone delivery load 4 $45.00 $180
underdrain pipe,6"PVC linear foot 230 $1.35 $311
filter fabric square yard 112 $10.00 $1,120 biofilter surface area/27*1'depth
sand/soil mixture cubic yard 74 $20.00 $1,480 biofilter surface area/27*2'depth
EC-1 outlet protection each 1 $200.00 $200
class Al rip-rap square yard 341 $30.00 $10,230
48"concrete riser structure each 1 $1,000.00 $1,000
Outlet pipe linear foot 85.00 $25.00 $2,125
EC-3,EC-2 matting square yard 720.00 $10.00 $7,200
Facility A subtotal $25,275
trees&shrubs ball/burlap planted 6 $100.00 $600 (only bonded the minimum planting requireme.
underdrain stone cubic yard 26 $17.00 $442 biofilter surface area/27*1'depth
stone delivery load 3 $45.00 $135
underdrain pipe,6"PVC linear foot 6 $1.35 $8
filter fabric square yard 93 $10.00 '$930 biofilter surface area/27*1'depth
sand/soil mixture cubic yard 52 $20.00 $1,040 biofilter surface area/27*2'depth
EC-1 outlet protection each $200.00 $0
class Al rip-rap square yard 37 $30.00 $1,110
48"concrete riser structure each 1 $1,000.00 $1,000
Outlet pipe linear foot 46.00 $25.00 $1,150
EC-3,EC-2 matting square yard 0.00 $10.00 $0
Facility B subtotal $6,415
trees&shrubs ball/burlap planted 9 $100.00 $900 (only bonded the minimum planting requireme
underdrain stone cubic yard 40 $17.00 $680 biofilter surface area/27*1'depth
stone delivery load 4 $45.00 $180
underdrain pipe,6"PVC linear foot 220 $1.35 $297
filter fabric square yard 190 $10.00 $1,900 biofilter surface area/27*1'depth
sand/soil mixture cubic yard 80 $20.00 $1,600 biofilter surface area/27*2'depth
EC-1 outlet protection each 1 $200.00 $200
class Al rip-rap ' square yard 223 $30.00 $6,690
48"concrete riser structure each 1 $1,000.00 $1,000
Outlet pipe linear foot 220.00 $25.00 $5,500
EC-3,EC-2 matting square yard 0.00 $10.00 $0
Facility C subtotal $18,947
subtotal $50,637
project management $7,595
subtotal $58,232
10%Contingency $5,823
TOTAL $64,055
_
ROUNDED TOTAL $64,100
min total after reduction $12,820
t
t
t
(slut
t
t
t
(s;ut
t
t
t
(slut
BOND ESTIMATE-EROSION CONTROL Spreadsheet last revised:12-5-01
PROJECT NAME: Boars Head Sports Club
PROJECT NUMBER: WPO-2011-00103
DATE OF ESTIMATE: 05/14/12
ESTIMATE BY PBC
BASED ON: Plan signed 5/2/2012
WATER ITEM DESCRIPTION UNIT QUANTITY UNIT COST ITEM TOTAL
SEED,FERTILIZE,MULCH ACRE 3.65 1500 5475
SILT FENCE LF 555 5 2775
TREE PROTECTION FENCE LF 120 3 360
TEMPORARY FILL DIVERSION LF 0 3 0
DIVERSION DIKE LF 390 3 1170
TEMPORARY SLOPE DRAIN LF 0 20 0
SEDIMENT TRAP 1 ACRES 0.82 1000 820
SEDIMENT TRAP 2 ACRES 2 1000 2000
CULVERT INLET PROTECTION EA 0 500 0
INLET PROTECTION EA 10 200 2000
OUTLET PROTECTION EA 3 200 600
EC-2&3 DITCH PROTECTION LF 0 10 0
RIP-RAP LF 300 55 16500
CHECK DAMS SQ.YD. 0 30 0
PAVED CONSTRUCTION ENTRANCE EA 3 2000 6000
subtotal 37700.00
project management 5655.00
subtotal 43355.00
CONTINGENCY LS 10% 4335.50
TOTAL 47690.50
BOND AMOUNT REQUIRED 47700.00