HomeMy WebLinkAboutWPO202100033 Review Comments WPO VSMP 2021-07-30f•� OF AL8 County of Albemarle m COMMUNITY DEVELOPMENT DEPARTMENT VSMP Permit Plan Review Project title: Troxell Poultry House Project file number: WP0202100033 Plan preparer: Brian Kinzie [Brian@blackwellengineering.com] Owner or rep.: Broc Troxell [troxellfarms@gmail.com] Plan received date: 28 May 2021 Rev. 1 received: 07 July 2021 Date of comments: 29 June 2021 Rev. 1 comments: 30 July 2021 Reviewer: Name 401 McIntire Road, North Wing Charlottesville, VA 22902-4S79 Telephone:434-296-S832 WWW.ALBEMARLE.ORG County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is denied/approved. The rationale is given in the comments below. The VSMP application content requirements can be found in County Code section 17-401. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary. 1. Please use Albemarle County SWPPP template: https://www.al bemarle.orci/home/showpu blisheddocument/ 166/637202310327530000 Rev. 1: Comment addressed. 2. Ensure registration statement and section 9, signed certification are signed. Rev. 1: 3. Rev. 1: Registration statement must be signed by the operator. Either the contractor must sign it, or the owner who signed it must be listed as the operator. B. Pollution Prevention Plan (PPP) The PPP content requirements can be found in County Code section 17-404. Please provide a PPP. See 17-404 for required contents: https://mcclibrary.blob.core.usciovcloudapi.net/codecontent/12230/385730/Chapter%20 17%20Water%20Protection.pdf Rev. 1: Comment addressed. C. Stormwater Management Plan (SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is denied, and the reasons are provided in the comments below. The Engineering Review Comments Page 2 of 5 stormwater management plan content requirements can be found in County Code section 17- 403. 1. A stormwater management maintenance agreement must be recorded before this plan can be approved. Please contact Ana Kilmer [akilmer@albemarle.org 434-296-5832 ext.32461 to complete this process. Rev. 1: Comment not addressed. 2. Since forest & open space is being used in the VRRM, this area must be shown on a plat labeled as SWM forest & open space and recorded with a deed before this plan can be approved. There must also be an easement labeled SWM Facility easement around the proposed pond and its outfall and access area. The easement plat application can be found here: https://www.albemarle.org/home/showdocument?id=1052 Rev. 1: Comment not addressed. 3. Please add the following note to this plan and the plat mentioned in the above comment: "The SWM Forest and Open Space Easement is subject to the guidance set forth by DEQ in the Virginia Stormwater Management Program. The areas will remain undisturbed in a natural, vegetated state, except for activities as approved by the local program authority, such as forest management, control of invasive species, replanting and revegetating, passive recreation (e.g., trails), and limited bush hogging to maintain desired vegetative community (but no more than four times a year)." Rev. 1: Comment not addressed. Response letter said it was on sheet 2, but it was not evident. 4. Please clarify where the 17.5 acres of forest & open space is located. The legend appear incorrect on sheet 2. Rev. 1: Comment addressed, however, please label it as SWM forest & open space easement. 5. Please add a title to sheet 1 and include WPO202100033 in the title. Rev. 1: Comment addressed. 6. Professional seal should be signed and dated. Rev. 1: Comment addressed. 7. Please provide date the topographic information was obtained/survey was completed. Rev. 1: Comment addressed. 8. Please show the WPO buffer and any critical slopes from county GIS on all applicable sheets. Rev. 1: Comment addressed. 9. It would be helpful to have a grading and layout sheet separate from the E&S sheet. Rev. 1: Comment addressed. 10. Please double check all grading and contour labels. The northern end of the site appears to have 1 ft contours tying in to 2 ft contours. Also, the proposed contours do not match the labels on the northwest side of the site. Rev. 1: Comment addressed. 11. Is the disturbed area 7.65 acres or 7.71 acres? There is a discrepancy in the plans. Rev. 1: The calculations packet project description (page 1) still says 7.65 acres. Please update. i contour elevations on all applicable sheets, especially the drainage divides. Rev. 1: Comment addressed. 13. Please list the required maintenance for the proposed SWM pond on the plans. Rev. 1: Comment addressed. 14. Please provide the following as -built check list on the plans: https://www.albemarle.org/home/showpublisheddocument/3381 /637327510536700000 Engineering Review Comments Page 3 of 5 Rev. 1: Comment addressed 15. On page 5 of your calculations packet, please clarify that you are meeting flood protection by 9VAC25-870-66-C2B (it appears you were missing the Q. Rev. 1: Comment not addressed. See below: At the point where water leaves the site, it meets energy balancve as per 9VAC25-870-66.B3. At the the point where the two streams converge (Point A), the pre and post developed conditions have identical Ws but the developed site has a lower peak flow for both the 2 and 10 year storm events, meeting 9VAC25-870-66.2B. 16. Please provide a detail for the emergency spillway for the permanent dry pond. Rev. 1: r..... ...* �ddrn—A 17. Per 9VAC25-870-66-B, concentrated stormwater flow shall be released into a stormwater conveyance system. The currently proposed outfall does not appear to go into a conveyance system or channel. Rev. 1: Is this Ditch 1 in the calculations? Please clarify and ensure plan view matches calculations. Plan view said swale cross section. DI's and culverts were clearly labeled. Also, plan view contours do not appear to show a v-ditch or swale as shown in calculations (or a channel). Contours below pipe outfall are shown below. A ditch or swale is not evident. If necessary, a site visit can be completed to verify the ditch/swale: 18. Rev. 1: Existing drainage area appears too large. It should only be the DA to the proposed outfall point. D. Erosion and Sediment Control Plan (ESCP) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is disapproved, and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17-402. Please provide the paved CE with wash rack detail from the Albemarle County Design Standards Manual (page 8): httos://www.aIbemarle.org/Home/ShowDocument?id=270 Rev. 1: Comment addressed. 2. Please show dust control as an E&S measure. Rev. 1: Comment addressed. Engineering Review Comments Page 4 of 5 3. Please show a stockpile, staging and parking area. Rev. 1: Staging and parking area should have perimeter controls. STOCKPILE LOCATION STAGING & PARKING AREA 4. Please provide adequate perimeter control, including silt fence around the southern and eastern ends of the project. Rev. 1: See comment above. Ensure Albemarle County Standard Notes are on the plan: httDS://www.albemarle.ora/home/showoublisheddocument/1262/63732132525S330000 Rev. 1: Comment addressed. 6. Provide details for the trash rack and anti -seep collars. Rev. 1: Ensure trash rack detail specifies the anti -vortex. 7. Please clearly show the drainage area for the sediment basin as well as the required dry and wet volume storages. Rev. 1: Volumes were not evident on the plan, elevations were shown. Also show the freeboard on the detail as well as the embankment top width. 8. Please add a note to the plans that County Inspector may require additional measures as needed on site. Rev. 1: Comment addressed. The VSMP permit application and all plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a completed application form. Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Process: After approval, erosion and sediment control and stormwater management improvements must be bonded. The bonding process begins when the plan is approved, and the applicant submits a bond estimate request form and fee to the Department of Community Development. A plan reviewer will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Engineering Review Comments Page 5 of 5 Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted to the County, who will record the agreement. After bonding and agreements are complete, county staff enters project information in a DEQ database for state application processing, if a DEQ permit is required. DEQ reviews the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter, which must be posted at the construction site. After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Applicants must complete the request for a pre -construction conference form and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre - construction conference, should everything proceed satisfactorily, ajoint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; https://www.al bema rle.org/government/com m unity-development/apply-for/engineering-applications