HomeMy WebLinkAboutWPO201800025 Bond Estimates 2019-01-31 Crozet Water Treatment Plant Expansion
WPO file number:WP0201800025
TMP(s):05700-00-00-010A0,05700-00-00-029B0
Date Estimate Completed: 01/31/19
Erosion and Sediment Control Bond Estimate
Item Item No. Unit Unit Cost Cost
Number (installed)
stablization(PS,TS) 0.5 acres $5,000 00 $2,500 00
silt fence(SF) 2000.0 ft $5 00 $10,000 00
tree protection(TP) 280 0 ft $5 00 $1,400 00
diversion(DD,FD,RWD) 0 ft $13 00 $0 00
temporary slope drain(TSD) pipe length 111111F0 ft pipe diameter 0 in $0 00 $0 00
earthwork for trap/basin
height of dam at toe `ft cut at high side 0 ft
height of fill at face ft cut at face ft
length of dam ft length of cut ft
top width ft width of cut ft
(area above transition 0 sf (area below transits 0 sf
(total width of darn) 0 ft (total width of cut) 0 ft
(height below transitio 0 ft (depth below transit 0 ft
(area below transition' 0 sf (area above transits 0 sf
(tote'" volume) 0 0 cy (total fill volume) 0 0 cy
length of spillway ft (TOAL CY estimate 0 cy $13 00 $0 00
width of spillway ft (spillway stone tons 0 tons $50 00 $0 00
structures for basin
riser height ft
riser diameter III in f❑ser unit price) $0 00 $0 00
barrel length ft base plate or fin $200 00 $0
barrel diameter in (barrel unit price) $0 00 $0 00
barrel collars $200 00 $0
baffle length ft $50 00 $0
silt fence inlet protection(IP) $100 00 $0 00
stone inlet protection(IP) ■ $200 00 $800 00
outlet protection(OP) length 0 ft width ft $0 00 $0 00
channel(SCC,matted) length 0 ft width ft $0 00
check dam depth in channel O ft channel width ft $0 00 $0 00
construction entrance(CE) $2,500 00 $5,000 00
wash rack $2,000 00 $4,000 00
paved construction entrance $3,500 00 $0 00
rip-rap,placed depth Oft length IMIRP ft
width 0 0 $60 00 $0 00
survey and layout(price per 0 1 mi) acres 0 traps and basins ii $0 00
mobilization $2,500 00
stream crossing(computed independently) $0 00
cost sum $26,200 00
contingency $2,620 00
1/31/2019
Crozet Water Treatment Plant Expansion
WPO file number:WPO201800025
TMP(s):05700-00-00-010A0,05700-00-00-029B0
Date Estimate Completed:01/31/19
Erosion and Sediment Control Bond Estimate
Item Item No. Unit Unit Cost Cost
Number Jinstalled)
Total $28,820
1/31/2019