HomeMy WebLinkAbout09 08 2009 PC MinutesAlbemarle County Planning Commission
September 8, 2009
The Albemarle County Planning Commission held a public hearing, work session and meeting on
Tuesday, September 8, 2009, at 6:00 p.m., at the County Office Building, Lane Auditorium, Second Floor,
401 McIntire Road, Charlottesville, Virginia.
Members attending were Marcia Joseph, Don Franco, Calvin Morris, Bill Edgerton, Linda Porterfield,
Thomas Loach, Vice Chairman and Eric Strucko, Chairman. Don Franco arrived at 7:24 p.m. Julia
Monteith, AICP, non -voting representative for the University of Virginia was absent.
Other officials present were Wayne Cilimberg, Director of Planning; Elaine Echols, Principal Planner; Amy
Pflaum, Senior Engineer; Gerald Gatobu, Principal Planner; David Benish, Chief of Planning; Bill Fritz,
Director of Current Development and Greg Kamptner, Deputy County Attorney.
Call to Order and Establish Quorum:
Mr. Strucko called the regular meeting to order at 6:01 p.m. and established a quorum.
Committee Reports:
Mr. Strucko invited committee reports.
• Mr. Morris reported that last week the Pantops Steering Advisory Committee briefed the Board of
Supervisors.
There being no further committee reports, the meeting moved to the next item.
Review of Board of Supervisors Meeting — September 2, 2009
Mr. Cilimberg reviewed the actions taken by the Board of Supervisors on September 2, 2009.
Other Matters Not Listed on the Agenda from the Public:
Mr. Strucko invited comment from the public on other matters not listed on the agenda. There being none,
the meeting moved to the next item.
Consent Agenda:
Accept applications and/or refer the following to the Agricultural Forestal District Advisory
Committee (see list below for full descriptions).
• Review of the Jacob's Run Agricultural/Forestal District
■ Yellow Mountain Addition
• Moorman's River Addition
■ Carter's Bridge Addition
• South Garden Addition
■ Kinloch Additions
■ Jacob's Run Addition
■ Buck's Elbow Mountain Creation
• Lanark Addition
• Free Union Addition
• Buck Mountain Addition
• Blue Run Addition
• Keswick Addition
■ Batesville Addition
• Eastman Addition
ALBEMARLE COUNTY PLANNING COMMISSION
SEPTEMBER 9, 2009 FINAL MINUTES
• Hardware Addition
• High Mowing Addition
■ Chalk Mountain Addition
■ Sugar Hollow Addition
■ Fox Mountain Creation
■ Ivy Creek Addition
See Attachment A: PC REFERRAL CONSENT AGENDA TEXT — individual description of each
addition
Mr. Strucko noted that there are 21 new or additions to agricultural forestal districts as a result of the
revalidation process. He asked if any Commissioner would like to pull an item from the consent agenda
for further review.
Motion: Mr. Morris moved and Ms. Porterfield seconded for approval of the consent agenda.
The motion passed by a vote of 6:0. (Mr. Franco absent)
Mr. Edgerton asked staff to provide graphic representation of the parcels that are being added. If this is
in response to the revalidation process he would like to see the benefit.
Mr. Cilimberg pointed out staff would email maps of the properties to the Commissioners.
Ms. Joseph noted it was unfortunate that these folks did not have more time to contemplate putting their
land under conservation easement.
Mr. Strucko noted that the consent agenda was unanimously approved.
Work Session:
CPA-2008-00003 Village of Rivanna Master Plan - Work session on Draft Plan dated August 26, 2009,
also including Resolution of Intent to amend the Comprehensive Plan. (Elaine Echols)
Ms. Echols presented a PowerPoint presentation and summarized the executive summary. She noted
that the consultants were not able to attend tonight's meeting. (Attachment — PowerPoint presentation)
The Commission last met on the Village of Rivanna Master Plan on March 17, 2009. Prior to that, there
were four meetings with the community and four meetings with the Commission between June 2007 and
now. At the last meeting, the Commission provided direction on density, land use, and transportation.
Staff and the consultant were directed to write the text that will accompany the plan to bring back to the
Commission for review on July 14. The meeting was rescheduled to September 8 to accommodate
community concerns.
The draft master plan was delivered to the Commission during the week of August 24 — 28. A resolution
of intent has been attached to this Executive Summary. The draft Village of Rivanna Master Plan is
formatted similar to the Pantops Plan. The key features of this plan are identified on the Executive
Summary page of the plan. One item for discussion is the level at which "adequacy of infrastructure" is
measured. Staff will review the draft language in the plan and ask for additional input. The maps as
shown are coming back to the Commission to look at the areas that are available for new development.
The purpose of this master plan was to provide guidance on where and how new development would take
place and also to make recommendations on the timing for new development. The vision for the Village
of Rivanna was one of a distinct small community that would have medium and low density residential
neighborhoods with easy access to the Village Center through multiple modes of travel. The community
will preserve historic features, provide open spaces for recreation and focus commercial activity inside the
'+ Village Center.
ALBEMARLE COUNTY PLANNING COMMISSION 2
SEPTEMBER 9, 2009 FINAL MINUTES
There were a number of guiding principles that came out of the public meetings:
,%W • Density, design and character of existing neighborhoods would be protected.
• The size and scale of new development would be compatible with existing development.
• The rural ambiance of the area would be retained.
• Commercial uses would be allowed only in the Village Center.
• The street connections and pedestrian paths needed to be sensitive to existing development.
• Historical sites will be protected.
• Water, sewer and streets will keep pace with growth.
• Public and private common space parks and sports fields will be provided to foster the
community.
This development area is fairly small. It is 2.7 square miles. There are 693 homes in Glenmore and 761
homes in the entire development area. Addition approved units already in the village are 674, which is a
maximum.
Staff highlighted the points of the framework plan. This particular development area will be mostly
residential in character. Existing neighborhoods will retain their low density character. Residential use will
be the dominant use and adequate infrastructure will be needed for new rezoning. The Village Center
was a rezoning approved in 2007 as Rivanna Village at Glenmore with a mixture of residential and non-
residential uses. The non-residential uses would only be allowed in the Village Center and are not to
exceed 125,000 square feet.
As part of this exercise the Commission looks at whether or not the areas outside of the existing
development areas should be brought into the development area. A decision the Commission made a
while back was that the rural areas should remain rural and there would be no expansion of the
development area boundaries with this master plan.
11"W The future Land Use Map showed the context of the map on the right. The map on the right is about the
areas that would be available for future development. In the future Land Use Map the density is expected
to radiate from the Village Center. The highest densities would be near the Village Center and the lowest
densities at the edges. The development on the west side of Carroll Creek would not exceed 3 units per
acre on the gross development. East of Carroll Creek would be expected at 2 units per acre or less. A
landscaped buffer would be expected across the frontage of 250 East so that people traveling along 250
really would not know there is a total new development. They are trying to keep the rural character of
Route 250 East. This plan anticipates 300 to 400 new units.
There are several recommended transportation improvements in this framework plan. On Route 250 East
those are more regional in scale than local as far as the Village at Rivanna goes. They have included
them in this master plan just so that they have the information there and also looking for that
endorsement. The recommended improvements are: Interchange improvements at 1-64 and Shadwell;
widening 250 East from two to three lanes to four lanes east of the Shadwell Interchange to Glenmore
Way; repair or replacing the bridge over the Railroad at Route 22; improve the intersection at Route 250
East and Milton Road and improve the intersection at Blackcat Road and Route 250 East. All of those
improvements with the exception of the widening of the lanes right in front of the Glenmore Entrance are
actually in the County's designated rural areas.
Staff wanted to understand and develop a recommendation for the characteristics of Route 250 East
across the frontage of the Village of Rivanna. What this plan is recommending is that the 1-64
interchange at Shadwell to Glenmore Way on Route 250 would be a four -lane rural section with a median
and a walking and biking path on one side and then from Glenmore Way to Blackcat road would be a
rural section with an optional median and a walking or biking path on one side of the road. The
recommendation that staff felt was most relevant to this plan and the work that the Commission does right
now is that there would be a limitation on the additional access points from Route 250 East, specifically
'144W Hacktown Road and in the vicinity of Breezy Hill Lane would be the places to provide access. There
would be not additional development in Glenmore without a second gate except for those properties that
are along Ashton Road. There was consideration of a potential signal that was proffered with Glenmore
ALBEMARLE COUNTY PLANNING COMMISSION 3
SEPTEMBER 9, 2009 FINAL MINUTES
at Glenmore Way. There is a potential of changing that to a roundabout in the future. In terms of transit
and pedestrian and bicycle network there is a recommendation for a fixed route commuter service when
ridership can support it. The new development would be transit ready. Rivanna Village at Glenmore is a
transit -ready development. In terms of bike and pedestrian access, the plan recommends pedestrian
crossing over Carroll Creek that would help link the Glenmore, Carroll Creek and Running Deer
neighborhoods with the Village Center. There are recommendations to potentially link Glenmore and the
nearby residential development to the Village Center with pedestrian access. Finally, a pedestrian and
bicycle path along the Route 250 East frontage area is proposed.
There is a part of the plan that links to parks and the green system. This plan includes a recommendation
for a public greenway along the Rivanna River. The plan also seeks to preserve floodplains, critical
slopes and riparian buffers. The Village Center in Rivanna Village at Glenmore would have an 18-acre
park. In the new areas for development, there is a recommendation that pocket parks be included as
focal points.
The implementation tables are much smaller than other master plans. The biggest thing that is needed is
to address the traffic issues at a regional level, which would be through the regional transportation plan
the MPO and UNJAM. The next issue is the monitoring of the sewage treatment plant. It has a limited
capacity. This plan is recommending that the density of the development area not exceed what the
current treatment plant has for capacity. There would be monitoring for additional community facilities.
In the last couple of weeks, there have been some emails sent around raising concern about traffic. The
point that was made in those emails is that Route 250 East is already over capacity from Route 22,
Louisa Road to the Charlottesville City limits. Staff noted that it was under capacity from the eastern
county line to the Route 22 Louisa Road which contains the frontage of the Village of Rivanna. The
reason for that capacity issue or that it is over capacity the closer one gets into Charlottesville is because
there is convergence of several roads. There is traffic generated not only by the Village of Rivanna but by
all sorts of other traffic including people living away from their jobs who are coming into Charlottesville
and into the county using 250 East. In 2035, the traffic will increase by 90 percent which is the prediction
between Route 22 and Charlottesville so that even with the recommended improvements that are shown
in the plan that stretch of road between Route 22 and the Charlottesville City limits is going to operate
over capacity. There is nothing that can be done to those roads that will bring it into capacity. The
percentage of increase contributed by the 300 to 400 dwelling units would be minor compared to the
whole because of the large amount of traffic that is expected on that road from other areas.
Staff brings the following questions for Commission consideration:
If Route 250 East will always be over capacity -
• Should additional development be allowed in the Village of Rivanna?
• If allowed, when should additional rezonings be approved?
Staff sees that there are three options:
Remove a portion of Village of Rivanna from the Development Area.
(The Planning Commission looked at that as an option several months ago and was not something they
wanted to do.)
Lower density more
• Recommend land use shown on the future land use map with the understanding that the
maximums are rarely achieved and that sewer limitations will affect the amount of growth that can
' occur much more than the road system.
ALBEMARLE COUNTY PLANNING COMMISSION 4
SEPTEMBER 9, 2009 FINAL MINUTES
Considerations:
• Absorption of existing approved units, which make take 20 years or more;
• All units may not be built;
• This is a development area;
• Village Center expected to be available for shopping (trip reductions);
• Sewer capacity will have more influence than transportation;
• All of the major streets in the Development Areas operate over capacity.
Staff noted that these are things the Commission needs to keep in mind as they review the
questions posed by staff.
Staff is asking the Planning Commission to discuss and endorse the Land Use Plan. Staff feels that
it represents what they have asked for in recognizing the sewer capacity issues. Staff is asking what
the Commission's position would be on approvals for new development, advice on any language
needed for the plan and potentially setting a public hearing for October.
Mr. Strucko invited questions for Ms. Echols. After that they will hear from members of the public.
Then the Commission will have a full discussion after considering the answers of the questions
posed by staff.
Ms. Joseph questioned the maps and why the area was shown over and over again and not just the
area being proposed to be the Rivanna Village.
Ms. Echols replied that staff tried to pull out the Rivanna Village area and can reduce those maps in
the future. When the consultants set up the maps it was done for the larger areas. Staff has tried to
pull out the Village since they are not recommending any changes to it. Staff can ask the
consultants to pull the maps down. She pointed out that the consultants were not able to attend
tonight's meeting.
Ms. Joseph noted that the map still has the boundary on it and it gets confusing when they talk about
if they took it out or not. The other thing that they talked about many times during the different
meetings was that people really wanted to get an idea of how many units could be within the land
use designation. She thought that was something like how many acres have they designated and
how many units they think might go in there just as a ball park figure. When staff puts a yellow swap
on the map what does that mean in terms of how many units could possibly go in there. They also
talked about whether it was possible to get a graphic showing what this may look like. If it is multi-
family then put in something that looks that way. She thought that people wanted to get some idea
of how this was going to manifest itself and what form it was going to take.
Mr. Benish noted that staff would make sure the numbers are correct.
Ms. Joseph suggested that information on the historic districts could be added. Limestone next door
has not been mentioned. The Southern Albemarle Historic District abuts this with 83,000 acres. She
thought that they could add some things to beef up that section.
Ms. Joseph felt that information would be helpful and would like to hear from the public.
Mr. Strucko opened for public comment and invited members of the public to come up and address
the Commission.
ALBEMARLE COUNTY PLANNING COMMISSION 5
SEPTEMBER 9, 2009 FINAL MINUTES
Betsy Baten asked for more specific wording relating to parks and open space in the village
particularly the equestrian center and the golf course, which are recognized as open space in the
*40W Glenmore Private Development Plan. She would like to bring that into language in the master plan
for the Village of Rivanna so that becomes part of the Village of Rivanna Parks and Open Space.
Neil Means, resident of Village of Rivanna, said that he sent out the emails about the transportation
that Ms. Echols summarized earlier. In the Comprehensive Plan it has always said in the functional
description in the definition of villages that a village is supposed to be linked to the City of
Charlottesville and urban areas by roads of an adequate capacity. Now they have realized that at
least since 2005 the Village of Rivanna has not been linked to Charlottesville by road of adequate
carrying capacity and it will never be. So it has to affect the density. It is a development area but is
also a village. If they took all of the units of housing in the Village of Rivanna and put them together it
will be a village already. It already has the population of a village. If the Rivanna Village is built they
will have something that looks like a village. If they build the recommended densities in this plan
plus what has already been approved and put them altogether it will be a town. They will not be able
to commute to the city. There should be some warning label when realtors market properties that
you may not be able to commute to your job or school from their home. If the Rivanna Village was
built the notion that would reduce trips is not accurate. The big problem is commuting time during
peak loads. The shopping trip reductions and daily usage is going to have less impact on the peak
loads than it might at first seem. Throughout this master planning process residents have attended
all of the meetings to discuss issues of densities and the consultants and staff have put them off and
said that first they will discuss the form and then they will talk about density. He felt that the
residents still have not had the opportunity to have any input on the density. This plan or draft
before the Commission is not something the residents have approved. If they can't provide the
roads and infrastructure to the growth area maybe they ought to spread the development out. That
way there would not be as many traffic jams.
Dennis Odinov, resident of Glenmore, said that the plan drafted so far really reflects a lot of what he
, W heard and participated in the citizens meetings. He also believed and agreed that the lack of a
sewer system will first hold back development before the traffic issue. Although he thinks the traffic
issue is very important. He has a problem with the extension of new Route 250 East from Route 22
to Glenmore because doing that would desecrate surrounding landscape. It is surrounded by
mature trees and is very shady and pretty and as previously stated that section of Route 250 is
under capacity. He felt that a roundabout would be a very dangerous solution. There is a limited
site line for a driver going west on Route 250 coming over the hill to the entrance of Glenmore.
Many people travel that road at high speeds. Therefore a roundabout would be very dangerous
unless there was a warning way in advance. He agreed with Ms. Joseph that they should get a
maximum build -out. They had asked for this. Generally he felt that this portion of the plan done so
far is very encouraging.
Neil Williamson, of Free Enterprise Forum, felt that it was very beneficial that a lot of the
commissioners were involved in the DISC I and II Committees. He noted the following concerns.
They are starting to see much of the concurrency of infrastructure that was predicted in
those committees. On page 1, 3 and 6 of the master plan reference, "Future development
should only be approved when adequate infrastructure is in place. As they are seeing in the
Places29 master plan and the Pantops master plan, the question coming up is one that he
has raised many times in what is the government's responsibility to ensuring such
infrastructure is in place. He acknowledged that some of this discussion belongs in
Richmond at state level and also in this room during the Board meetings.
• He asked if the county plans to change its school construction programs to start building
schools prior to the issuance of building permits. The county has a development area and if
they chose to have a development area they must also chose to target development and
target their spending within that development area concurrently. It is beholding on
Albemarle County and not the landowner to provide county services according to the
Comprehensive Plan that has been approved by the county and vetted through the citizens.
ALBEMARLE COUNTY PLANNING COMMISSION 6
SEPTEMBER 9, 2009 FINAL MINUTES
Since Albemarle County does not seem to be able to clear the backlog of infrastructure on
its own capital improvement projects, and the Crozet Library comes to mind, these
**MW references regarding future development being restricted by future county spending should
be removed. He thought that they were unrealistic and unenforceable.
Another concern is how the proposed regulations from the Department of Conservation and
Recreation influence the layout and design of this particular master plan. An initial review of
the proposed regulations caused him to question some of the design elements that are
included. If the state regulations prevent some of the master plan layout from being
completed how they will ensure the future development conforms to the form that they have
dictated for this plan.
Finally the Village of Rivanna master plan identifies over 25 million dollars of transportation
improvements relating mainly to US 250. The responsible party for funding these
improvements is the Virginia Department of Transportation. VDOT is in the process of
laying off 1,000 full time employees, 450 part-time staff, closing rest stops as VDOT
addresses a 2.6 billion dollar shortfall which has not been updated with today's governor's
projections. He would be very surprised to see this kind of money spent on US 250 in the
time frame of this master plan.
Mr. Strucko closed the public comment session to bring the matter back to Planning Commission for
discussion.
Ms. Echols noted that the first question raised was why designate any additional area for
development if the roads can't support it. That is something staff wants the Commission to make a
statement about because it has been a concern of the Commission and public.
Mr. Morris invited an update from Mr. DeNunzio of VDOT on 250 East and the area in question and
what he saw in the future.
Joel DeNunzio replied that from Glenmore to about Route 729 it is about 5,500 vehicles per day.
Route 729 brings in about the same amount of traffic at that traffic signal. So they get about 11,000
vehicles per day at that location. Crossing the Shadwell Bridge then Route 22 comes in which adds
another 11,000 to 12,000 vehicles. At that point on Route 250 that is where there is a real bottom
neck with about 22,000 to 23,000 vehicles per day. Currently they don't have any plans other than
studies that show widening of Route 250. There are not funded plans on Route 250 to his
knowledge that VDOT has in the works right now.
Mr. Loach asked if Route 250 will always be over capacitated.
Mr. DeNunzio replied that is a difficult question to answer. He would say Route 250 from Route 22
into the city without widening and without any way to put the traffic somewhere else that the road will
be over capacity until something is done. Road widening is a way to deal with the capacity issue. It
would require a lot of right-of-way funds and construction funds for that project.
Ms. Joseph noted that one of the things they have done in the Pantops master plan is created a
potential for parallel roads. They would need to look at that too. One of the things that did not make
the Fontana people very happy is require a through road through Fontana that connected Route 250
over to Route 20. She asked if some of these parallel roads would help with the over capacity issue.
Mr. DeNunzio replied that parallel roads would help. The real parallel road would be 1-64. They
would have to build a whole new facility to get the traffic onto 1-64. The only place he could think of
would be off Route 22 that crosses under 1-64. Then they have the issue of whether the interchange
would be too close to other interchanges. He did not think that had been looked at, but could require
1-64 capacity issues that could require widening through Charlottesville also. He noted that more
lanes are how they would address the capacity issue whether it is a parallel facility or a widening of
existing facilities.
ALBEMARLE COUNTY PLANNING COMMISSION
SEPTEMBER 9, 2009 FINAL MINUTES
Ms. Joseph noted that additional lanes are being required for some new commercial businesses on
Pantops when they come in for site plans.
Mr. DeNunzio noted that there was identified the need for six lanes in that area in a Corridor Study.
Mr. Strucko noted that they heard that there is a potential, but what makes it remote is the funding.
Mr. Loach agreed with Mr. Means that they should have a better way of tying development to
infrastructure. He had not seen the concurrency that Mr. Williamson sees. He was not sure where it
was in the future, but there has to be a better way of doing this. It should not come as a cost of the
quality of life for the growth area residents. They can't put the cost of that quality of life all of the
time on one segment of the population, which is growth area residents. He felt that development
should be allowed in the development but there has to be some way to tie it to the infrastructure.
There has to be some methodology that people can see and quantify when development takes place
that it is not going to be at the cost of their quality of life.
Mr. Strucko asked staff to identify the sewer capacity issues.
Ms. Echols said that right now there is a lot of sewer capacity available. The numbers were given in
the document. The capacity exists for the developments that have been approved and a little bit
more but it all depends on what the usage is. The Service Authority plans at one level and the
actual usage is more than 100 gallons per day less than that. The monitoring that takes place of the
sewage treatment plant and what is available to absorb is something that the Sewer Authority does.
So staff cannot tell the Commission exactly how many units can be supported by the sewage
treatment plant right now because of a lot of other factors. They can give figures based on the
current usage of Glenmore. It would allow for X number of new units. They can give figures that are
based on the 270,000 gallons per day, which is the figure the Service Authority uses for planning
purposes, would give another number of units. Because of the mixture of uses that are in the
Rivanna Village of Glenmore and how much they are going to need staff cannot give exact numbers,
but can say they think there is capacity for between 300 to 400 more units based on what the
sewage treatment plant can handle. That is at the lower end of the usage of the sewer treatment
plant facility. The Service Authority is not looking at creating more capacity unless that is something
that is looked as being Albemarle County's goal out there. The ability to create more capacity brings
them into a whole different level of regulations. There is a package treatment plant there right now.
It was built to add particular units. When those units are filled up then they have to go to a whole
different kind of system that comes under a different set of regulations. It would be difficult to create
more sewage capacity.
Mr. Loach said that he was okay with the sewage capacity. He agreed that they should use the road
issue to keep the density down.
Mr. Strucko said that the answer to when rezonings should be considered should be when the
infrastructure is adequate.
Mr. Morris agreed.
Ms. Joseph agreed acknowledging that funding does not exist for this infrastructure. She did not
think that this community wants to raise taxes to pay for the infrastructure.
Mr. Benish noted on page 21 there is a statement regarding residential development that future
residential development should only be approved if and when adequate infrastructure is in place to
support the development which is the broad infrastructure and not just the sewage system. It would
be all of the consideration. What staff is struggling with and the question they have for them is that
they need to define what that measure of adequacy is. For the Granger proposal with that
Comprehensive Plan Amendment for the Southern Urban area they set Level of Service D for
roadways. That has been the convention for urban areas. This is a little bit unique because it is a
ALBEMARLE COUNTY PLANNING COMMISSION
SEPTEMBER 9, 2009 FINAL MINUTES
development area that is served by an arterial roadway that VDOT typically looks for a Level of
Service C. If the Commission wants that clarity if they want to retain this within the development
" area that is probably the specificity that needs to be added. As it stands right now if the Level of
Service is C, as an example, there is a condition here that may never be reached for that
development area.
Ms. Joseph asked if it was Level C right in front or on that entire stretch.
Mr. Benish replied that based on VDOT modeling process now they would look at a broader regional
context than just the front section. They could specify whatever depth they want at certain
intersections or multiple intersections. But again using the Southern Urban Area B example there
they noted the Neighborhood Roadway Network that would serve the area.
Mr. Loach asked what would be the difference in Level of Service C and D.
Mr. Benish replied that D is a slower speed of roadway with certain expected delays. It would
visually be like what they would see in the city with slower speeds and longer cycles in lights. Level
C is more of a free flow, but there would some delays during peak hour. They recently had some
complications in the use of Level Service C and D. Staff would probably have to come up with
another mechanism other than C to get over that complication.
Mr. DeNunzio noted that on a corridor like that the Level of Service C would be based on the percent
of time following another vehicle. Basically the more vehicles that are out there the more crowded
the road and the lower level of service. It is based on how fast one can travel the road and not
ultimately how fast your car can go. It would be what the speed limit is versus how fast can go and
what the travel times are. As they increase the travel times the level of service goes down. He
thought that he could provide more specific data on what the percentages of time following or the
delays are after the fact. He did not have that information with him.
Ms. Joseph asked if they are looking at a portion of time for the level of service C.
Mr. DeNunzio replied that the levels of service are generally referred to as the peak hour times in the
morning and afternoon peak hour.
Ms. Echols noted that staff had been looking at volumes to capacity ratios in the Eastern Albemarle
Study. Mr. DeNunzio has not reviewed that with them. That is where staff is getting their information
when there were a number of different alternatives that were modeled in the Eastern Albemarle
Study. That is what Mr. Means was referring to. The modeling on that showed that the volume to
capacity ratio that there was more volume than capacity in certain roads. They are doing more
volume to capacity than the level of service, which all work in together. She tends to think that what
they are looking for is a measure she would prefer that the Commission give staff an opportunity to
bring in some additional information before making a decision. She felt that the Commission needs
to look at the full set of information.
Mr. Loach said that it is just as important for the public to understand.
Mr. Edgerton agreed that the Commission needed more information in order to make an informed
recommendation. If he heard correctly one of the dilemmas they are facing in this situation is that
the standard that the county has used in the past with non primary routes has been level D. But
VDOT uses a level C. If they are trying to determine what standard will be required for being
considered acceptable infrastructure they are going to have to make a decision about which
standard would apply. If level C is the cut off point for VDOT's primary roads they need to know.
Mr. Benish noted that staff will have to sit down with VDOT and whether they use C or D or some
other methodology for the roadway it would still set a methodology. The C and D approach might
not be the approach to use any longer. So they would want to sit down with VDOT about that. Also
while typically for neighborhood streets most all the streets in the county level D has been
acceptable in urban areas. There are certain strategic roads because of the volume level C are
ALBEMARLE COUNTY PLANNING COMMISSION 9
SEPTEMBER 9, 2009 FINAL MINUTES
preferred. If they were to stay with C and D staff needs to coordinate that with VDOT. But they may
use some other methodology. They need to work on what that measurement would be.
Mr. Strucko asked if there were any other comments. He asked if staff received their answers.
Ms. Echols reiterated that the Commission wants staff to bring back some information before setting
the public hearing.
Mr. Strucko replied that was correct. He thought that was fair. The question was whether additional
development should be allowed in the Village of Rivanna. He noted that the answer was yes
because it was a designated growth area, but only when there is an adequate infrastructure to
support what they are planning.
Ms. Echols summarized the Commissioner's comments as follows:
The Commission wants staff to incorporate into the plan some pictures about possible
development types.
Provide information on the numbers of acres there and what the developable acreage is and
what that translates into in terms of numbers.
• Wants staff to bring some additional traffic information which explains where they are right now,
what the different levels of service mean in terms of this particular area and the measurement
and most importantly what it means to the individual who would be living there in terms of the
amount of the delay they would be dealing with in getting from point A to point B. Point B is
inside the City of Charlottesville or beyond. .
Mr. Morris asked staff to really take a look at the data that was generated by the Eastern Connector
14"W Committee. As he recalled at the intersection of Rte. 250 East and 20 that right now is almost an F.
They cannot separate the Village of Rivanna from Pantops when talking about transportation. That
is the bottleneck as Mr. DeNunzio was saying.
Mr. Strucko agreed with Mr. Morris. He thought they need some coordination of information here.
He was still confused and had to go back and review some of the documents. The sewer capacity
issue is saying that they only have capacity for an additional 300 to 400 units. Ms. Joseph asked a
question earlier about how many units could possibly go into the Village of Rivanna. That has been
the question that the public has. It sounds like all of this is connected. He asked to see some
calculations. If the sewer capacity or road capacity generates a certain figure today what
improvements have to happen to the road or the sewer to meet full build -out of what they are talking
about in the Village of Rivanna. If the road and sewer reached its capacity, then they have to scale
back on what they expect in the Village of Rivanna.
Mr. Loach pointed out that these plans are reviewed every five years. So what they are trying to find
is the right starting point at this place and time. That is what he thought they should be looking at.
Ms. Joseph noted as a reminder that the Commission had received an email from Cyndi Burton who
was really in support of libraries. She asked that they take another look at that and that they be a
little more forceful in seeing if they can add something there if it makes some sense in this area.
Mr. Benish suggested that it might be useful to continue to monitor the need. There is a regional
plan for libraries that is pretty clear as to where those areas would be for service. He tried to check
with the County Executive's office today. There is a desire to relook at that study. It is also a
recommendation in the Pantops Plan that library service be provided there. So while it may not be
Rivanna is the location, it could be if that shifts. But quite frankly what has been looked at most
recently is the calculation for needs for libraries is actually going down and they need less library
space. They may have to figure out the most logical place to put less square footage of libraries
because of technology changes and funding issues.
ALBEMARLE COUNTY PLANNING COMMISSION 10
SEPTEMBER 9, 2009 FINAL MINUTES
Ms. Joseph noted that the Bookmobile goes to the Keswick Post Office, which can be an option.
Mr. Benish pointed out that computers and computer kios areas where the public can order and pick
up are all innovative options that have been identified before. He did not want to offer anything that
in reality does not appear to be very likely based on the plan to have a full blown branch out there.
But staff can continue to emphasize other services and to continue to monitor the need.
Mr. Strucko pointed out on the topic of public services Ms. Baten brought up a point about
designating parks and open space. She mentioned the Glenmore Golf Course and Equestrian
Center. That is not open to the public. Those are membership only.
Ms. Echols felt it was a legitimate request. Staff has noted on the Places29 plan where there is
privately owned open space that is just designated as open space. So staff can take care of that
one.
Ms. Porterfield pointed out that the Glenmore Golf Course and Equestrian Center are actually open
to the public for a fee.
Mr. Benish noted that Ms. Joseph had indicated that there were other things to help promote the
historic area. He asked Ms. Joseph to provide that information.
Ms. Joseph asked why they are so specific in designating an asphalt pedestrian path. She
suggested that it be a hard surface pedestrian path.
Ms. Echols replied that staff can put in hard surface.
Ms. Joseph said that on page 9, number 5 staff talks about the street connections and that street
designs will promote good driver behavior and be appropriately sized for the volume and speed of
traffic. She asked if staff talking about traffic calming.
Ms. Echols replied that one came out several years ago when there were some concerns about the
travel through the different parts of Glenmore. It was more about traffic calming to make sure future
streets are constructed in a way that minimizes traffic conflicts. That came out a number of years
ago from Glenmore. Darby Road is the road in particular that was bothering people. These are the
guiding principles and not recommendations.
Ms. Joseph submitted a couple of typos for staff to correct.
Mr. Strucko noted that they have a resolution of intent to act on. He asked if it was appropriate for
the Commission to act on it. It does not give any specific dates.
Mr. Benish noted that the resolution of intent says that they are going to study an amendment and
does not speak specifically to the draft they are looking at.
Mr. Strucko noted that they would hold a public hearing.
Ms. Joseph asked that the public hearing be sometime before December.
Motion: Ms. Porterfield moved and Mr. Morris seconded for approval of the resolution of intent for CPA-
2008-00003 Village of Rivanna Master Plan, as noted below.
The motion passed by a vote of 6:0. (Franco absent)
Mr. Strucko said that CPA-2008-00003 Village of Rivanna Master Plan would proceed with staff setting
the public hearing and incorporating the Commission's and public's comments and suggestions to the
draft.
ALBEMARLE COUNTY PLANNING COMMISSION 11
SEPTEMBER 9, 2009 FINAL MINUTES
RESOLUTION OF INTENT
WHEREAS, the Village of Rivanna is located east of the City of Charlottesville and south of
Route 250 East, with its southwestern boundary formed by the Rivanna River, its western boundary
formed by an unnamed stream just east of Camp Branch, its northern boundary formed by Route 250
East, and its eastern boundary formed by the eastern ridgeline of the drainage area for Carroll Creek and
Route 808; and
WHEREAS, the Village of Rivanna is one of eleven communities in Albemarle County identified in
the Land Use Plan, which is a component of the Albemarle County Comprehensive Plan; and
WHEREAS, it is desired to develop a master plan for the Village of Rivanna to serve as a general
guide for future development and systematic change within the Village.
NOW, THEREFORE, BE IT RESOLVED THAT for purposes of public necessity, convenience,
general welfare and good planning and land use practices, the Albemarle County Planning Commission
hereby adopts a resolution of intent to amend the Albemarle County Comprehensive Plan to adopt a
master plan for the Village of Rivanna as determined to be appropriate after study; and
BE IT FURTHER RESOLVED THAT the Planning Commission shall hold a public hearing on the
Village of Rivanna Master Plan proposed pursuant to this resolution of intent, and make its
recommendations to the Board of Supervisors at the earliest possible date.
The Planning Commission took a break at 7:16 p.m.
The meeting reconvened at 7:24 p.m.
Mr. Franco arrived at 7:24 p.m.
Deferred Item:
SDP-2009-00009 Arden Place
The request is for preliminary site plan approval of 212 multifamily residential apartment units and a
club house on the R15 residential zoned portion of Tax Map 61 Parcel 124 which consists of 11.350
acres. Associated waivers include section 4.2 (critical slopes) and section 21.7.c (disturbance of a
buffer zone adjacent to a residential district). The subject property is located in the Rio Magisterial
District on Rio Road East [State Route #631], about 900 feet from the intersection of Rio Road East
[State Route #631 ] and Seminole Trail [State Route #29]. The Comprehensive Plan designates this
property as Community Service in Urban Area 2. (Gerald Gatobu) DEFERRED FROM THE JUNE
23, 2009 PLANNING COMMISSION MEETING.
Gerald Gatobu presented a PowerPoint presentation and summarized the staff report. (See Staff
Report)
The request, SDP-2009-00009, Arden Place is for preliminary site plan approval for a 212 unit
multifamily residential apartment complex with a club house on the R15 residential zoned portion of
Tax Map 61 Parcel 124 which consists of 11.35 acres. Associated waivers include section 4.2
(critical slopes) and section 21.7.c (disturbance of a buffer zone adjacent to a residential district) The
property, described as Tax Map 61, Parcel 124 is 11.35 acres in size, is located in the Rio
magisterial district and is zoned R15 Residential and EC entrance corridor.
• There are four items before the Planning Commission tonight for the following: Critical Slopes
Waiver, Requested Buffer Disturbance, Preliminary Site Plan and a recommendation to the
Board of Supervisors for open space. Four actions are being requested.
liftw The proposed changes to the site plan include the following:
ALBEMARLE COUNTY PLANNING COMMISSION 12
SEPTEMBER 9, 2009 FINAL MINUTES
• There is now a second point of access that meets ordinance Section 32.7.2.4 for a second point
to a public street. It goes down towards Rio Road. For the most part that is the biggest change.
• There is also a path that connects and goes down all the way to the Woodbrook Lagoon project.
That is something that has been added. It is kind of a pedestrian path that will be going towards
the Conway property.
• There is a potential for a future connection to the Conway property that staff added to the staff
report as a point of discussion.
• There is also a revised traffic analysis that was also present in the staff report. Joel DeNunzio
as well as the representative for the applicant is present to answer questions about the traffic
impacts to this.
• The critical slopes waiver and the buffer disturbance waiver really has not changed apart from
the fact that the road will now be going downhill disturbing some critical slopes that are basically
man-made.
There is a connection over to the County of Albemarle Lagoon Project. The concept plan had
already been prepared. This is going to be a point of discussion and emphasis for a lot of the public
present. There is a proposed bike rake at the intersection. There are four parking spaces, benches
and a meadow overlook. Staff is proposing that the path come in and connect to this public space
so that people can take advantage of this public open space. That is something staff is proposing
and would be more than happy to talk about.
The applicant has made the two points of connection based on that. Staff recommends approval of
the critical slopes waiver and the buffer disturbance waiver.
Mr. Strucko asked if the critical slopes were man-made.
Mr. Gatobu replied yes. There are some areas of critical slopes within the C-1 parcel. There is no
site plan. Staff can approve the critical slopes administratively if there is a site plan that showed the
critical slopes and how they were made in that property. Staff agrees that most of the fill came from
the shopping center site and was dumped onto this property. Since there is no site plan that shows
that staff has to bring the request before the Planning Commission for a critical slopes waiver.
Mr. Strucko asked if the two points of connection are Forest Court and Rio.
Mr. Gatobu replied that is correct.
Mr. Strucko asked if the buffer disturbance is because of the road.
Mr. Gatobu replied yes because there is a 20' buffer between a commercial and a residential district.
They have to come before the Planning Commission per Section 21.7.c for the buffer disturbance
waiver in cases where staff cannot do that administratively.
Mr. Strucko asked about the open space.
Mr. Gatobu pointed out the open space. The green space is shown in the staff report as going all
the way down the property. There is wooded area that will be preserved for which the applicant gets
a 10 percent density bonus.
Mr. Strucko said that the pedestrian path connects to the Lagoon Project.
Mr. Gatobu replied yes, and that in the staff report it shows the pedestrian path going straight into
the Lagoon project.
Mr. Strucko invited other questions for staff.
*NW Ms. Porterfield said that with regard to the path she noticed that it is 10' wide. She asked if that
width is so it is ADA compliant.
ALBEMARLE COUNTY PLANNING COMMISSION 13
SEPTEMBER 9, 2009 FINAL MINUTES
Mr. Gatobu replied yes, that it is one of the standards that they have. He pointed out the trail
IVAW standards in the Design Standards Manual. What they have chosen is a Class A Type 2 low
maintenance multi use shed path. It is the one that requires the least amount of maintenance in this
case. They did not randomly pick, but chose the best available type of path or trail.
Mr. Strucko asked if it was an asphalt path impervious surface.
Mr. Gatobu replied yes that it was 10' suffice and 2 cleared shoulder. They chose the grades to be
ADA accessible.
Mr. Edgerton said that the preliminary site plan shows the two connections going out to Rio Road
and yet in the staff report at the very end on page 12 it states that the applicant is pursuing a
connection from the Carmike which would become the secondary road. Then the road to Rio would
not. He assumed that the Commission being asked to approve a plan that he really does not want to
proceed with because if he goes to the Carmike he will not be doing the connection to Rio. He
asked if that was correct.
Mr. Fritz noted that there were two issues there. One, that the plan before the Commission does not
have the Carmike access. The applicant is proposing that. What they have done is provided that
information to the Commission in the event that if the applicant is able to secure that access and
decides that he wants to go through with that staff would consider that to be a major change to the
site plan and the final site plan would come back before the Planning Commission. Staff wanted to
present that to the Commission at this meeting so that if the Commission had a strong feeling one
way or the other that information could be provided to the applicant. For example, if the Commission
felt that the Carmike access is not a good access there is not much point in the applicant continuing
to pursue it. When the final comes through then the Commission would likely not approve that. If
they thought it was a better access than the Rio access, then they could theoretically allow staff to
administratively approve the final site plan with the Carmike access and not having to bring it back to
the Commission. So the Carmike access is simply being provided for information right now. The
plan before the Commission does not have the Carmike access. If the applicant gets the Carmike
access staff will bring the final site plan back to the Commission for additional consideration unless
they tell staff at this meeting it does not need to be.
Mr. Strucko asked how viable the Carmike access for vehicular travel or a throughway is. It is a
parking lot.
Mr. Fritz replied that it goes through the travel way and parking lots of the Garden Shopping Center.
In the staff report it is noted that there are some issues with that. It is not an ideal situation by any
stretch of the imagination. But it does afford the opportunity to get into to the Gardens Shopping
Center which then gets one to Route 29 either farther north of Albemarle Square or going south to
use the light at Albemarle Square.
Mr. Strucko asked which connection that would be in lieu of, and Mr. Fritz replied the direct Rio
connection and not the Putt Putt connection.
Mr. Edgerton noted that was shown clearly on Sheet 5 which is identified as Arden Place Preliminary
Site Plan as is the one on the screen before us. If nothing else they need to figure out which one if
they take staffs recommendation for approval
Mr. Gatobu said that it would be the one shown on the screen that has the connection to Rio.
Ms. Porterfield said if she understood correctly that if the Commission is willing to go with the
Carmike access in lieu of the access directly on the Rio Road, they could word the resolution such
that staff would have the ability to do that.
ALBEMARLE COUNTY PLANNING COMMISSION 14
SEPTEMBER 9, 2009 FINAL MINUTES
Mr. Edgerton said what of the Commission would be telling staff essentially is that they did not view
the Carmike connection to be a substantial change from the preliminary warranting the final coming
*Aft back before the Planning Commission. It would still have to go through all of the administrative
review, engineering and so forth.
Mr. Strucko asked if the pedestrian pathway could be ADA compliant and have a pervious surface.
Mr. Gatobu replied yes. In this case it is actually shown in the Design Standard Manual. For the
most being that wide allows the path to be of a width of the Americans with Disability Act. They want
to try really hard to work with the grades to make sure that happens. Staff talked to Parks and Rec,
who are the experts on the trails, and they are very complimentary in what they want to do. Staff
reviewed the exhibit submitted by the applicant and asked if it something they would recommend in
terms of the design and they said yes that they would highly recommend it. Parks and Rec were
very impressed that the applicant went with the 10' wide path. In terms of safety the wider path
would allow one to see a little further making it safer.
Ms. Joseph asked if this pathway would become property of the County of Albemarle
Mr. Gatobu replied yes. The applicant has agreed to do maintenance because it will be part of the
parcel of their development. It is to their benefit to have it more than looking nice. So the applicant
has agreed to do that as well. They are ready to work with the County in terms of maintaining it.
Ms. Joseph asked about the buffer disturbance. In one paragraph staff states that the Architectural
Review Board will be working to make sure that 50' buffer is landscaped. She asked if was in their
purview to do that.
Mr. Gatobu replied yes. The first site plan that came in had a traffic circle. The ARB asked that the
applicant change the intersection so that they can reduce the amount of buffer disturbance. The
applicant complied with that. The ARB has reviewed the plan and has given some comments and
direction in terms of the buffer as well.
Ms. Joseph asked if that does not have to be a condition of approval for the ARB to grant them.
Mr. Gatobu said that it is a condition that is included that they need to get Architectural Review
Board approval.
Mr. Strucko noted that one of the issues they discussed that last time they looked at this was the
impact of traffic on Rio Road and the time element to get out of this development. He asked if they
have addressed that at all in the plan before the Commission that excludes the Carmike connection.
He asked if they are still faced with the same issues about the 20 minutes.
Mr. Gatobu said that the applicant has revised the traffic study. He asked that Joel DeNunzio or
Amy Pflaum address that issue.
Joel DeNunzio noted that they have received a revised traffic study from the applicant. There were
a couple of things in the first one that had around 1,100 seconds and 19 minutes delay on the left
hand lane out of Putt Putt. That was not accurate. When they looked at the revised study they
found that the revisions included accounting for the signal of Old Brook Way up the way, which
allowed for some more gaps in the road that made it a little bit better. But there was also the
inclusion as one comes out of Putt Putt Place if taking a left there is actually a shared left turn lane
on both sides. When including that left shared turning lane it actually allows a two stage gap
procedure form Putt Putt Place out to Rio Road. So it allows one to get the first gap that is created
off to the left from Old Brook Road intersection, you get in the median and then the gaps that are
created from the Albemarle Square signal you can proceed to go. So it is basically like having a
median in there. When accounting for the median being in place the levels of service to get out of
that are acceptable.
ALBEMARLE COUNTY PLANNING COMMISSION 15
SEPTEMBER 9, 2009 FINAL MINUTES
Mr. Strucko noted that in the letter it notes that the delay drops to roughly 30 seconds.
Mr. DeNunzio replied that was correct. It was both the signal at Old Brook and the two way turn lane
that made those two changes.
Mr. Strucko asked if he had looked at any of the traffic work that would result from the connection to
the Carmike and the elimination of this road to Rio Road directly.
Mr. DeNunzio replied that they have reviewed that. Really making that connection to Carmike does
not have much effect on traffic coming from Putt Putt Place onto Rio Road making a left turn. He felt
that it had a little affect on the right turns from Rio Road to Route 29 North. He felt that it was a little
bit of an improvement in the movement right there.
Mr. Strucko asked how VDOT views a connection through a parking lot.
Mr. DeNunzio said that this all private and internal. They really did not consider it. It really does not
address the issues that they had with the levels of service movements coming out of Putt Putt. As
far as a second connection here it shows a little bit of an improvement at the signal over there, but it
might be it is not really a travel way going through a parking lot. So making the connection has some
benefit, but not as a true roadway. As far as using that connection instead of the Rio Road
connection, the additional right -in and right -out on Rio Road, as far as the traffic goes he did not
think that there was much increased benefit for one or the other there. The Putt Putt Place and the
Rio Road connection are so close that having a second connection to Rio Road is acceptable. Last
time they considered this they said they were putting more conflict points on Rio Road, which is
never a desirable thing. It can work from a spacing perspective having a right turn lane going into
the right -in for this new connection, but as far as the traffic he did not think that it addresses any of
the issues. The left turn movement was always the concern. Having another right -in and right -out
really does not address that.
Mr. Strucko noted that what he heard Mr. DeNunzio saying was having the connection directly to Rio
and another connection through Putt Putt Place there is really no added benefit for the second
connection.
Mr. DeNunzio replied traffic wise there would be no benefit until they get the commercial
development in there, which is when they might see a benefit from that second connection.
Mr. Strucko said that there is some benefit to connecting to Carmike, but it is not really a through
way.
Mr. DeNunzio noted that he did not mean that the second Rio Road connection is non desirable.
With or without it as far as VDOT is concerned that both are acceptable.
Ms. Joseph noted that in looking at a travel way as a parking area they have done this at least twice
in the past. In Albemarle Place a travel way connected through the parking area. Also, it was done
in Hollymead Town Center when they were looking at a travel way connecting through the
commercial through the parking areas back out onto Route 29. So it is not anything new and
different. It has been done before.
Mr. Strucko hoped that they could get more input on this from the applicant. He opened the public
hearing and invited the applicant to address the Commission.
Valerie Long, representative for the applicant, presented a PowerPoint presentation and explained
the changes in the proposal. (Attachment — PowerPoint Presentation) She noted that other present
included Andy Megentee, Principal of Coleway Development, LLC and Bill Wrench, of Renaissance
Planning Group who is serving as traffic engineer for the project. They appreciate being back before
the Planning Commission. Staff has covered the changes very well. Therefore, she would skip
through those changes in the interest of time.
ALBEMARLE COUNTY PLANNING COMMISSION 16
SEPTEMBER 9, 2009 FINAL MINUTES
She asked to highlight at the beginning that this is an infill development project. They pulled out
a copy of the Comprehensive Land Use Plan that has a section in it that is often overlooked.
That policy in many ways was created precisely for this type of a project. It specifically states
that infill development is considered one of the key initiatives for implementing the growth
management policy and is encouraged for the following reasons: to use the development area
lands in the most efficient manner possible, to discourage sprawl development and to maximize
use and support of community facilities and infrastructure such as roads, utilities and transit.
Then it mentions specifically that there are much higher costs involved with developing infill
projects than there are compared with other sites and consideration of permitting more intensive
uses and densities on some properties may be necessary to get development costs including
measures necessary to minimize impacts of development. When they looked at that policy this
project really included a lot of those challenges.
This is obviously an infill project surrounded by property that has already been developed on all
sides at a relatively intense stage. It is in the development area and is zoned for 226 units by
right, which includes the R-15 density plus the automatic bonus densities that could be granted
depending on the type of project. It is pedestrian oriented. It is a good example of how
development in the designated development area when coordinated with surrounding
development can really create a project that is very harmonious with the Neighborhood Model
Principles. Because of the way the property around this property has development there are a
variety of housing types with a mixture of uses with the retail and public spaces nearby. It is
walkable to a variety of destinations, which includes retail, office, professional and medical
offices, recreational facilities and the public library, etc.
It is proposed as a market rate apartment community. They are preserving 10 percent of the
woodlands. They are proposing to dedicate a sense of area of open space and the trails for
public use. There will be a swimming pool and clubhouse amenities on site. They are
requesting the Commission to grant two waivers to approve the site plan and also to weigh in on
to the Board of Supervisors with regard to the open space dedication. The pedestrian path
connecting to the Lagoon Project is on the site plan. Regardless if the Carmike connection is
ultimately developed they will develop the pedestrian path to connect to the Carmike.
The darker green area is the tree preservation area that provides for some automatic bonus
densities, which is equivalent to 17 units. The applicant asks the Commission to grant the
critical slopes waiver. The disturbance for the road is exempt from the waiver requirements. But
the disturbance for the clubhouse and some of the parking lot is not exempt. At the last meeting
she went through the critical slopes analysis in late June.
The buffer waiver is a little more complicated because it is an unique situation. It is a single
parcel with split zoning of C-1 and R-15. There is a 20' buffer required to be maintained on the
commercial side of the line. They are not allowed to do any grading on the commercial side of
the line where it is adjacent to the residential unless they get a waiver from the Commission. In
order to develop the residential it is necessary to do a little bit of disturbance on that buffer area
in order to create the road. Obviously, this is the only place for the access at this point. The
area is entirely on the commercial side of the line, but because it is adjacent to the residential
they have to obtain the Commission's consent for that disturbance. It is a buffer in name only. It
is not a wooded vegetative area that is actually providing any type of a real buffer from anyone.
It is storage facilities and is a gravel parking lot. It is not like they are disturbing an actual buffer.
It is a line on a map.
There are 212 units being proposed. They get the 107 base units, which is based on the R-15
density. They get another 17 units by preserving 10 percent of the woodlands and an additional
25 units for the dedication of open space or the trail dedication. The woodlands preservation is
an automatic bonus density. The open space trail dedication is discretionary. Ultimately the
Board of Supervisors has to act on that. They are asking the Commission to recommend
approval for those additional units. They could get to 226 units with all automatic bonus density
credits. Through affordable units they could do 221 units or through a variety of options they
could get to 226 units. They are not doing that, but asking for 212 which they feel is appropriate
for the area and for the market rate product they are trying to provide.
ALBEMARLE COUNTY PLANNING COMMISSION 17
SEPTEMBER 9, 2009 FINAL MINUTES
• The access points are noted. She noted the pedestrian connection to Rio Road. It makes that
,% full connection. There is a full sidewalk along Rio Road in both directions so it connects the
pedestrians to that public sidewalk network that already exists.
• They are working very closely with the owners of the Carmike Shopping Center. It is actually the
Gardens Shopping Center, which are out of town owners. They have been quite cooperative.
But it is a long process to work out all of the details of the connections. This is the preferred
location if and when they could ever work out all of the details to get there. They are far from
there yet. They wanted to, as Mr. Fritz noted, to at least provide the Commission with
information since it was something they were working on in the interest of full disclosure. The
owners of the shopping center have noted that one of the conditions would be that they have to
gate that connection so that it is only the Arden Place residents that would be coming through. It
is not in any way going to be a public cut through. Nobody wants that. One of the other issues to
work out is how do they route the cars to ensure that there is no conflict with the pedestrians and
other patrons of the shopping center. Obviously they are not going to grant the necessary
easements and approvals to make that connection if they are not very convinced that they can
do that in a way that ensures the safety of their owners, tenants, guests and the general public.
Obviously, they would not want to do that either. There are those issues to work out. They are
moving forward, but it is taking time.
• The traffic study has been pretty well explained. Their traffic engineer is present if there are any
questions. They have engaged a second traffic engineer to provide an audit of the first traffic
study. The first traffic study for the June meeting has been revised as Mr. DeNunzio described
to include another intersection and take a few other factors into consideration, which lowered the
delay time substantially. VDOT has thoroughly reviewed the information as well.
Mr. Strucko invited questions for the applicant
Mr. Morris asked for a run down on the applicant's actions in regards to the path connecting to
Woodbrook.
Ms. Long replied that right now there was no path to Woodbrook directly. The path connects to the
County's Lagoon Project that is adjacent to Woodbrook, but does not connect to Woodbrook. At the
last meeting they had a path connecting directly to Woodbrook, which had been the request of staff
and others. In working with staff they recognized the public benefit of it. They think it is more
appropriate for it to connect to the County Lagoon's Project than into Woodbrook. They are happy to
do it recognizing that there are some members of the Woodbrook community that don't support the
path into Woodbrook. They are just doing what the County has asked them to do, which is to
connect it to the Lagoon Project. It will provide some public benefit connecting that public land, the
Lagoon Project, which will be a little bit more inviting perhaps once the Lagoon Project is fully
implemented to the public spaces on Rio Road. That will then lead one to a number of other places.
In addition it will connect into the Carmike and Gardens Shopping Center, which ultimately provides
a pedestrian access to Albemarle Square Shopping Center and Route 29. This really opens up a lot
of possibilities when making those two connection points. They feel that it would be quite a benefit
to the public and would ask the Commission to support that dedication.
Mr. Strucko invited public comment.
Mr. Fritz noted that staff today received two written correspondence that they did not have time to
put in the packet. He passed around the two letters.
John Gallenger supported luxury apartments being built on the site. He would prefer trees and a
meadow on the project, but felt that luxury apartments would be a good fit on that property. He was
frustrated that they need to appear again this evening. Since the last time he thought that they had
decided that a Woodbrook connection was a bad item. Due to the one way in and out of Woodbrook
he questioned why they would want to put a hole in one of their boundaries and jeopardize their
security by providing access to the Lagoon Project since it is a not a park. He questioned what
would be the purpose of someone walking from Rio Road to look at a sandy berm. Just past the
bike rack on the picture there were bike racks and benches. It is a small creek reconfiguration
ALBEMARLE COUNTY PLANNING COMMISSION 18
SEPTEMBER 9, 2009 FINAL MINUTES
project and not a real park project or a Chris Green Lake. He questioned if it was a real park there
would be more than four parking spots and some benches. More traffic in Woodbrook would
threaten the community's safety. The footpath would be sending more people into Woodbrook
where they don't have sidewalks or street lights, which would be more safety issues. They are
hearing different opinions from their neighbors tonight. The Woodbrook Community. Association
cannot argue both for and against the Woodbrook connector. They have chose to side with the
neighbors that live closest and agree that there are valid safety issues that have not been addressed
at these meetings. In closing please let the applicant build his apartments because luxury
apartments is what they should all hope for in this location. That way they could permit the green
space he is applying for so it would not impact their neighborhood. , which is what they hope for in
this location. Please tell the County that the Woodbrook connection causes far too many security
and safety issues and should be dropped from the plans.
Jerry Bettentif, resident of Woodbrook, pointed out through a show of hands that only one person in
the audience living in the Woodbrook had asked for a trail in their neighborhood. The trail was being
requested from persons outside the community. In asking how many would consider a 10' paved
asphalt strip to be a road there was a show of hands of over 10 to 15 person. Therefore, the 10'
strip sounds like a roadway to the people in Woodbrook. That leads to a creditability problem with
the county. A few months ago they were told that the Woodbrook Lagoon was a storm water
enhancement project. Most persons viewed it as an environmental improvement project and did not
object to their tax dollar being spent for that. He now wondered if it was a runoff project for the
benefit of Arden Place with the cost being shifted from the developer to the public. He would study
the maps further and perhaps it is not. The storm water enhancement project is not being presented
more like a park to justify the need for a 10' road or trail in the area. From the discussions he heard
that it was an ADA requirement for the path to be 10' wide and paved. From goggling he found that
the ADA trail requirements call for a 3' wide path with a stabilized surface that can be gravel or
packed soil. They are mostly concerned about the slope of a trail in terms of wheelchair suitability
for the trail. There is even an exception depending on terrain and area for a 32" trail. The
implication he had read and heard this evening did not indicate this. There is not need for a 10' wide
trail or path in this area. If the county wants to build a 3' wide ADA compliant trail in this area he
would ask that they do a survey to determine the potential users and to get some kind of idea of the
costs benefit ratios.
Kathy Welch, an 18 year resident of Woodbrook, reemphasized what had just been said about the
ADA requirements. There is no requirement that the so call trail has to be 10' wide. It only needs to
be 3' to 4' wide and composed of crushed stone or gravel and be a firm and stable surface. She took
a tape measure and measured her car, which was 5 % feet. Her car could drive along the 10' foot
path as suggested with a 2' space on each side. If the Carmike entrance is approved it would go
across this footpath and she feared that there would be possible vehicular traffic. She questioned if
there would be any traffic signals considered by VDOT for safety purposes particularly for children
on bicycles. She questioned why they would want the path to end up in the swamps or wetlands.
She questioned the motive behind this to put in a paved surface to end up in wetlands.
Lee Floydburg, resident of Woodbrook, spoke in opposition to any sort of path connecting into
Woodbrook. This is a complex bio-filter to protect the wetlands where pollutants will be building up
behind the berms to prevent runoff of pollutants into the Chesapeake Bay Watershed area. He
questioned how this Lagoon area can be described as a park. He questioned if the paved area
would increase the paved hardscape runoff from the development to further stress this bio-filter
system which protects the Chesapeake Bay. The children will be pulled to this area. The path will
provide a direct link for the children from the Arden Place development and the Carmike Theatre for
them to go down and find a place to get themselves hurt. It is an attracted nuisance and not a park
for children. This is supposed to be dedicated to the county which will create maintenance costs for
all taxpayers when no one sees this as a reasonable preferable project. This can also pose some
safety risks and concerns at the intersection of the roadway and they will have to install guards to
get in the way of vehicles getting on the path.
ALBEMARLE COUNTY PLANNING COMMISSION 19
SEPTEMBER 9, 2009 FINAL MINUTES
Ann Hobson, 39 year resident of Woodbrook, said that her property faces part of the Lagoon
property. She was not familiar with the term footpath and therefore went to Webster's Dictionary,
which indicated it was a narrow path for pedestrians only. She decided to go out and measure some
of our familiar landmark. She measured two sidewalks in two area 4' and 4.5r". She measured bike
paths that measured 4' 41/2". The average trail in Penn Park is between 71/2' and 8'. At Albemarle
High School it was 19', which did not include the curbing. That corresponds very closely to one-half
the road way the County is asking us to use to call a footpath. She did not think that the choice of
words was common and saying they need it is not correct. They need to remember the end of the
lagoon project was where there is a joint gate with no fencing around the property. She votes
against the path since it is not something that they want. It seems to be just what was originally
proposed for access to our road.
Terry Gallanger, wife of John the current President of Woodbrook and 19 year resident, noted that
John has been part of this process since March. Living in the back of the neighborhood this
proposal does not affect them directly. But they want to support the Powells since they are their
neighbors. The majority of the neighborhood came forward at the last meeting and said that they did
not want the path connection and gave good reasons. Mr. Fritz at the last meeting said that it was
an unfair representative of Woodbrook and that most of the neighbors wanted the path. She did not
know where that came from when they showed up in mass last time and strongly opposed a
connection. Also why a blacktop pathway next to a stream that is not a nature path. They have a lot
of deer and other animals visiting their yard. She asked if the environment needs a blacktop
pathway. She noted that at the last meeting they were told that as a roadway it was private property
and they would not be able to use it. She asked if it was a pathway would it still be private property
also and not be able to be used by Woodbrook residents. She proposed that they support Mr.
Powell and the surrounding neighborhood to say no pathway and if the Woodbrook residents want a
nature way and not a blacktop then that is something the next President can look at. Possibly it is
something that a Boy Scout troop could work on.
Charlie Tractra, resident of Woodbrook, noted that at the last meeting he found that he was wrong
that the applicant was an evil entity trying to destroy his community. He also found that the applicant
was under the impression that his community was against him for no particular reason. That night
he found out that they both were wrong. At the end of the meeting he offered him the opportunity to
try to work together. Since that time he has come to see that the applicant was actually more the
victim than Woodbrook was. They have worked together with staff to address the problems,
particularly the traffic problems, so that everybody could win. Because of this tonight he can state
that he has not objections to building this apartment complex and actually supports the additional
units he needs. His only objection is the proposed pathway. On June 23 over 90 percent of the
people who spoke supported the option that there is no connection to Woodbrook from any other
development. He supported the 90 percent and did not understand why the board would demand
that the 10' paved footpath be built. His pickup truck is 6' wide and could use this footpath as a road
way. Supposedly this footpath will be part of a park to be used by county residents. It would also be
useful to the neighborhood so they can walk to Fashion Square Mall. Remember there will be a
fence keeping them out of the Dumbarton Property. While this may sound beneficial these ideas
have not been thought out. He asked that they please ask the planners how the residents, particular
the children, will cross Rio Road. Also where will county people find a place to park their cars?
Existing parking areas are private, there is no parking on Rio Road and the parking is very limited in
Woodbrook. There will be a lot of security issues. While drawing a colored line on a map is easy
actually building this footpath should take more thought and responsibility from you.. But until all
questions are answered why not just accept a right-of-way for a path that can be built in the future.
This will give the county time to solve the aforementioned problems and also the new community of
Arden Place will be able to voice their opinion on something that will directly affect them.
Mr. Eugene Powell, resident of 2701 Brookmere Road for 34 years, said that a lot of activity takes
place there. A pathway would be a disaster because many people walk across his property all the
time. He decided to build a path around behind the creek. But the people continue to walk across
the field through his yard to get to the theater parking lot even though he tells them to go around this
way. He was opposed to any kind of path through Woodbrook with a connection to the theater. It
ALBEMARLE COUNTY PLANNING COMMISSION 20
SEPTEMBER 9, 2009 FINAL MINUTES
would be a road through there and keep on going. He hoped the Commission would disapprove this
request.
Beatrice Powell agreed with her husband Eugene in opposing the path. They now have many
people coming through their yard and approving this pathway would only increase the numbers.
Their property adjourns the proposed road path. She strongly opposed the request and asked that
the Commission disapprove the request because it was a problem for many residents of Woodbrook.
Stephanie Max, a resident of Woodbrook for 11 years, said that they access Albemarle Square.
They walk through the front of the properties across Woodbrook Shopping Center and Gardens
Shopping Center to Albemarle Square and ACAC. Their children walk to ACAC. She asked if they
put in the 10' path how they would keep the cars off it. She was concerned if they put in signs the
cars would still use the path.
Kenneth Hoy, resident of 204 Woodbrook Drive, said that he attended the last meeting and thought
the consensus was that there would be no type of walkway or a roadway coming into or going close
to the Woodbrook area. He respectfully requested that the Commission vote against this.
Laurie Campbell, an area resident of Woodbrook for 13 years, opposed the path and to allow people
to come into their neighborhood. She was appalled at the presentation of the 10' path. At the last
meeting there was no mention to use the ADA regulations. She felt it was wrong to use people with
disabilities to make them look good. She supports people with disabilities, but does not use them to
make herself look better. She was appalled that the ADA Disabilities Act was brought into the 10'
path. She opposed the request and asked the Commission to remember what was said at the last
meeting.
Steve Huck, an 8 year resident of Woodbrook, opposed the 10' wide path with the 2' clearing on
each side. It would give benefit to see people jumping out at walkers for potential crime. It would be
making a marvelous place for crime. He asked that the Commission disapprove this request.
Mike Allure opposed the path because it leads to an area that will create a hazard to little children. It
does not matter whether the children come from Woodbrook or other communities because the path
would lead them into an unattended area, which is not a park, creating an access from a public
parking lot. He sees right now that there are businesses closing down and more vacancies. He did
not know what kind of businesses or people that area will drawn. But he was concerning about
drawing children into an unattended area that is not a park and encouraging them to go there. That
is why he did not think a 10' path is a good idea for kids.
Eric Baker, resident of Woodbrook for 8 years, opposed the request because the area is very quiet
and safe at present and did not need any connection. .
Robert Manica, area resident, opposed the connection to the Carmike Theater. At the road
connection at Rio Road onto Garden Boulevard there is a right turn in and right turn out only on
Route 29 with no deceleration lane. Therefore he feared that the back way through Arden Place
would be used frequently. He feared that they would move the problem from Rio to 29.
Ty Ellen, a resident of Woodbrook for 30 years, opposed the connection into Woodbrook and did not
see any benefit to the Woodbrook residents at all. The children are required to ride the bus to
school. The pathway is not needed for the children to get to school. The one way into Woodbrook
has worked for years and she asked that the Commission disapprove this request. She requested
that no connection into Woodbrook from any other communities be denied in the future.
There being no further public comment, Mr. Strucko closed the public hearing to bring the matter
before the Planning Commission.
Mr. Strucko asked if the Lagoon Project is in the CIP or any of the County park plans
ALBEMARLE COUNTY PLANNING COMMISSION 21
SEPTEMBER 9, 2009 FINAL MINUTES
Mr. Gatobu noted that this project will be funded through a grant. It was not being funded by the
county. As a planner, professional and someone that is trained in LEED he heard the neighbors and
had talked to them. As a professional they look at what the circumstances are and consider all of
the factors including the crime. If this was not opened to anybody else it would not be a problem to
the community. He talked with Greg Harper today and asked what he thought about it since he was
in charge of it. He said that he spoken with a Woodbrook resident and was told that if only
Woodbrook was allowed to use the path into the Lagoon Project that they would be fine with it. He
found something to be terribly wrong with that. That was his professional opinion. It was not against
anybody in the neighborhood regarding their recommendation for a 10' path. He felt bad that
someone felt they would take advantage of ADA and that they don't. It is in the Design Standard
Guidebook and why would they do that. He apologized to the Chairman, but noted at some point
they have to get in some rational on why they do what they do.
Mr. Strucko thanked staff because that was a hard accusation to make and he appreciated him
commenting on it.
Ms. Joseph noted that the goals of the Lagoon on the County website says are to provide water
quality, preserve and enhance on site wetlands and create educational opportunities and facilitate
access. This is not something that was made up by Planning Department per say, but were the
goals set up when the grant was received for creating this area. She understands what people are
talking about. As a landscape architect she feels very sad that people worry about pathways. It is
one of the most important things that came from a Parks and Rec survey. In the survey 80 to 90
percent said they wanted to see natural walking paths. This is something that did not come from
nowhere. Consequently that is what they have looked for since the majority said they wanted to see
linear paths. She acknowledged this is not a park with playing fields. But when doing intense
activity in the development area a little piece of green space for people who live in the dense area is
appreciated.
Mr. Strucko noted that it was recreational park space and passive park space. He would categorize
this as a passive park space.
Ms. Joseph asked Ms. Pflaum if this is used specificity for storm water for Arden Place. She asked
what is this being used for.
Amy Pflaum, Engineer, replied that it is providing a benefit to a development area that includes
portions to the west side of Route 29. It encompasses the area and parts of the Gardens area. It
has been around much longer than the Arden Place project. Arden Place will have to meet the
requirements of the Water Protection Ordinance. It will have to provide on site storm water
management. They are already proposing in the preliminary plan a bio-filter and underground
detention. They will have to take care of all of their own storm water management. They will not be
given any storm water credit for the Woodland Lagoon Project. She asked to clarify a few points.
The 10' wide asphalt requirement is a County requirement for the Class A Type 2 trail. Another part
of the Class A requirement is that it meet the ADA standards for grades. The ADA standards the
width is less than 10'. There are two criteria that the applicant has meet with the proposed trail — the
County criteria of a Class A Type 2 trail and the ADA standards for grading. The ADA standard from
the Virginia greenways toolbox has 2 different levels of an ADA accessible trail. One would be a 48"
wide with a hard non skid asphalt surface, which would be an easy trail. A moderate access trail
would be 36" wide with a hard packed surface. Those are the 2 different things or criteria being
looked at for this trail. It is the County criteria and the ADA criteria. There was concern about the
trail crossing or the vehicular connection at Carmike. That will not be a public road and VDOT will
not be maintaining it or putting up a cross walk. As Ms. Long said Carmike would request that there
be a gate at that connection where it meets the parking lot. It will only be used by Arden Place
residents. It will be a low volume of traffic and no resident pedestrian conflict because of it being a
low usage road. Our trail standards also require that some kind signage or cross walks at a location
of where a trail is crossing a roadway. So they could require that on the final site plan if that
Carmike connection is utilized
ALBEMARLE COUNTY PLANNING COMMISSION 22
SEPTEMBER 9, 2009 FINAL MINUTES
Mr. Morris asked would it still be in compliance if the pathway was 4'/2 wide with a hard surface and
be an easy pathway.
Ms. Pflaum replied that it was her understanding if it was asphalt and reduced it would meet the ADA
in the Greenways Manual but not meet the Class A Type 2 trail for the County.
Mr. Strucko noted that there were different classes of County trails.
Ms. Pflaum said what the applicant has proposed is the highest class of trail or the best case
scenario. They met with County Parks and Rec and they felt it was beneficial to have that type of
trail. It is a higher cost to the developer, but it is a very nice wide accessible trail.
Ms. Porterfield asked if they could get the Class A Type 1 low maintenance pedestrian path would
that be acceptable with staff who has worked with the developer.
Ms. Pflaum noted that the idea is that this open space and path in combination will be going to the
Board of Supervisors for the acceptance of the open space. Staff and the applicant were working
together to come up with the best possible proposal. If it is determined that the 10' path is not the
best proposal then she believed there would be room to lessen it.
Mr. Loach asked if the 5' path would be an acceptable path.
Ms. Long thanked Ms. Pflaum for the clarifications. The applicant would be fine with building a
narrower trail. It would be a considerable cost savings to build a narrower trail. They want to build
what the County is requiring in order to obtain the bonus densities they are proposing. If the Board of
Supervisors does not accept the dedication of the trail for width then they wouldn't to get the bonus
density which would throw the project into a black hole. They have been asked to build a 10' trail
ever since she has been involved in the project. They will do whatever is required. To address one
comment there is no desire from anyone that vehicles are on this trail. They would be willing to use
whatever safety measures are deemed appropriate. The County does not want vehicles driving on
the trail. They are will to work with the County on the width of the trail, whatever signage or
crossroads if the Carmike connection is ultimately implemented to take whatever measures are
deemed appropriate. The Arden Place developer has incentives to ensure that it is a safe trail.
There is a mutual incentive to make sure the trail is safe for everyone.
Mr. Loach asked if they would consider building the path to a certain point and waiting for input from
the Arden Place residents.
Ms. Long replied that they are happy to carry out the willingness of the County as long as the Board
of Supervisors will accept the open space and grant the bonus density.
Mr. Strucko questioned how the nature of this path affects bonus density.
Ms. Long replied that part of the bonus density is automatic. There are 24 to 25 units that are
discretionary to the County. The Board of Supervisors can accept and give a certain amount of
credit. The 25 units if it they give all the requested credit in exchange for dedicating land for the
public. In working with staff for months they have indicated they will recommend that the Board
accept this dedication of open space and public land if they find a public benefit. After careful
analysis they say trails already are there and people are using them. By connecting the trail to
public space staff thinks the open space meets public benefit. And if do it this in the way suggested
staff will recommend that the Board accept it and agreed to the bonus density.
Mr. Fritz noted that one action the Planning Commission needs to take was to provide a
recommendation to the Board whether to accept the open space and what bonus density level. One
thing to talk about is where the path goes and whether it is to the County Lagoon project or not.
ALBEMARLE COUNTY PLANNING COMMISSION 23
SEPTEMBER 9, 2009 FINAL MINUTES
Mr. Strucko noted in looking at the proposed open space there is a significant piece of land directly
adjacent to the County Lagoon project. It adds on to what the County owns on the Lagoon project.
He asked how much land was there.
Ms. Long replied that it is over one acre of land in total that is for sale plus along the trail as shown
on Attachment F of staff report.
Mr. Fritz said that not only is the dedication a question, but where the trail goes, should the
dedication be accepted and the standard of the trail to be constructed. The proposed standard is
the highest standard and is the one that provides the lowest cost of maintenance to the County and
the maximum flexibility of usage. If this body felt that the Class A Type 1 was more appropriate then
that is what the Commission could recommend to the Board.
Ms. Joseph noted that Attachment F was saying that the woodland will remain undisturbed.
Mr. Fritz noted that was correct that the woods would remain undisturbed but there was not transfer
of the property.
Mr. Strucko noted that the property behind Building 6 attached into the lagoon area. So they don't
have to extend the trail all the way to the existing lagoon.
Mr. Gatobu replied that the trail would only go to the boundary line.
Mr. Edgerton noted what Mr. Strucko was suggesting is if the applicant was willing to commit to not
disturbing the one acre plus that is behind Building 6 then the County could get an extra one acre
plus and the applicant gets the density bonus. It would be a win/win situation. He asked why the
trail couldn't stop at the woodlands. The current Lagoon project did not consider a connection at all.
Mr. Fritz noted that the connection to the Lagoon project staff sees it as an educational opportunity
and offers the same connection as Woodbrook has to the Arden Place residents. There are four
parking spaces on the Woodbrook side and bike racks. That is why staff is recommending the
connection to go all the way to Lagoon project.
Mr. Edgerton said that if the applicant were not able to disturb the wooded area and they were able
to add an extra one and a half acre to the Lagoon project to make it more effective why wouldn't they
do that. He did not think the applicant would be losing anything since they would be getting their
density bonus.
Ms. Porterfield asked if the applicant has agreed to dedicate and maintain the path.
Ms. Long replied that those are some issues they have not gotten to yet. But they would be happy
to maintain the trail if that is the preference of the County. Arden Place will have their own
maintenance crew on site anyway and are willing to pick up trash on the trail if that is the desire of
the Board.
Ms. Porterfield noted that could be part of the trade off to lessen the width of the path so it does not
look like someone's driveway.
Ms. Joseph asked if she understood from a speaker that the County staff met with some residents of
Woodbrook to talk about the Lagoon project and if they offered to help out Mr. Powell by putting in
some additional screening trees so people would not be straying through his yard.
Ms. Pflaum replied that General Services met with the Woodbrook residents, but she did not think
they made an offer to Mr. Powell.
ALBEMARLE COUNTY PLANNING COMMISSION 24
SEPTEMBER 9, 2009 FINAL MINUTES
Mr. Franco pointed out that he met with General Services after that meeting. He did not think that
1114 , they made that offer. One thing he talked about was how important they felt a connection through
the park was and if they felt it was important to have that path if they could design it to design it so it
focused people to the right-of-way as opposed to people's yards. He did not know where that
project stands. He asked if there was a requirement for a site plan for the park because it does have
parking.
Mr. Fritz replied that it does not meet the threshold for a site plan.
Ms. Joseph asked if they can require some screening or something for Mr. Powell
Mr. Kamptner noted that if it was going to be somewhere it would have to be part of the County's
Lagoon Project since it was off -site and not part of this site plan. The Commission could ask
General Services to consider the installation of these screening trees.
Ms. Joseph asked if they could make a stronger recommendation, and Mr. Kamptner replied that it
was out of their authority.
Ms. Joseph asked if the Commission could ask the Board to do something for Mr. Powell, and Mr.
Kamptner replied yes.
Mr. Strucko said that it sounds like the Commission is coming closer to a solution regarding the path.
He was hearing that the community's anxiety's is about a throughway of some sort. It sounds like
anything that is of significance like asphalt is going to cause anxiety. He would love to see a
pedestrian walkway through this area to serve if no one else but the Arden Place residents. So to
ease the concerns of the Woodbrook community and to continue to provide this amenity to Arden
Place he thought that they could pick a path standard that is still open to folks with people with
disabilities but is less substantial than 10' with 2' wide shoulders. Also they could potentially end the
path behind Building 6 and consider that is roughly of one acre of untouched space in view of the
Lagoon project. He asked if that was something the Commissioners and applicant can agree to.
Mr. Franco said that he was on the same page, but wanted to understand what is being deeded to
the County. Is it the path or is it acreage?
Mr. Strucko replied that in Attachment G of the packet it is everything colored in green that is the
open space dedication that does not include acreage.
Mr. Fritz noted that it was 1.08 acres which includes the path and some of the area adjacent to it.
Ms. Long asked to provide one point of clarification on Exhibit G the portion of the path that goes
behind Building 6 and goes from roughly where the Carmike connection is if made to the Woodbrook
Lagoon. It is not colored green on the exhibit, but it is part of it. The land around trail back there is
not part of the dedication, but just the path itself is. They will defer to their guidance.
Mr. Morris noted that area around it is part of the preservation area.
Ms. Long said that was correct it was untouchable and they could not touch those trees. The
preservation plan was part of the conservation plan and part of the preservation of those woods.
They have to have a tree preservation plan. There are actually some notes on the site plan. It is
small type and hard to see. But the detailed requirements of the conservation plan are spelled out on
the site plan. Essentially it is to leave the trees as they are and to take measures to protect during
construction.
Mr. Edgerton asked if the applicant was willing to consider dedicating that piece of land that he is
willing to commit to not touching to the County.
ALBEMARLE COUNTY PLANNING COMMISSION 25
SEPTEMBER 9, 2009 FINAL MINUTES
Ms. Long replied that land was not part of the dedication and she would have to confer with her
client and come back up. She did not know the answer to that question.
Mr. Edgerton noted that would give him reason to be enthusiastic about the project.
Ms. Long noted that there is an underground sewer that has to go in one area. That area is not
counted as part of the woodlands preservation area.
Mr. Franco asked if that property is amended to include that area and deeded to the County can it be
deeded such that the County can't build a road through it at some future point and it is really just for
a trail or path just to the Lagoon Project.
Mr. Kamptner replied that they have accepted deeds of dedication in the past. In this case since the
dedication is for a specific purpose that could be reflected in the deed so it is clear that it is
dedicated to a public use for a pedestrian connection.
Mr. Franco asked if they could allay the concerns of a vehicular connection, and Mr. Kamptner
replied yes that he thought that they can do that.
Mr. Strucko noted that another issue is the proposed connection to the Carmike parking lot. What
bothered him the most was when the applicant through Ms. Long said that the Carmike folks wanted
to gate that. That sealed the deal for him and thought that was not the kind of connection they
wanted.
Mr. Morris said that he could understand why they would want to gate it to prevent it from becoming
as a thoroughfare. That is the exact case they had in Carriage Hill.
Mr. Strucko said if the connection is not done in Carmike then they need the two connection points
on Rio and eventually Putt Putt Place. He asked won't that connection to Rio have to happen if the
commercial happens in front the property.
Ms. Porterfield asked if the connection to Putt Putt Place was implemented, would they get the
warrants to put the light in.
Mr. DeNunzio said that it depends on the type of commercial and the intersection would have to
warrant the light. He noted that it depends on the volume of traffic, but it would help the chances. At
that time the traffic signal light would require a design access management exception. He thought
that they would have a spacing issue with the upstream signals. They would still like to see with
commercial development possibly looking at connecting back through the existing signal there going
back through Albemarle Square.
Mr. Fritz noted that was assuming there were no changes to the current ordinance.
Mr. Strucko asked how they feel about the two connection points.
Mr. Franco agreed with Mr. Morris in that gated or not it works to have the connection at Carmike.
The extra entrance onto Rio is something that can be dealt with at site plan when that future front
piece connects. He felt that access management might tell us in the future that connecting to either
the Albemarle Square light or back to Putt Putt makes more sense from the conflict management
perspective. So he would rather go with pursuing the Carmike and see if it happens. If it does not
happen he was contend with just Putt Putt, but he was happy to go with the second point as shown.
Ms. Porterfield said that the Carmike exit -entrance would be useful and it does take the future
residents in and out of the back end of Arden Place. She was concerned regarding emergency
vehicles. If there was no Carmike connection, she was concerned with not having two entrances
because there would be a lot of units and a lot of people in Arden Place.
ALBEMARLE COUNTY PLANNING COMMISSION 26
SEPTEMBER 9, 2009 FINAL MINUTES
Mr. Strucko said that he was concerned with an arrangement between two private owners. He was
not sure that connecting to a parking lot is an effective throughway.
Ms. Joseph supported the Carmike connection even thought it was gated. She assumed it would be
accessible to emergency vehicles. If the path was gated it would alleviate the concerns about the
conflicts between vehicles and pedestrians.
Mr. Edgerton supported a connection at both ends even with a gate. He would be comfortable if
they could eliminate the path to the preservation area if the applicant would consider making that
area part of the dedication. He would be willing to recommend to the Board that to be in lieu of the
pathway.
Mr. Strucko asked Ms. Long to come forward with her response to the Commission's question.
Ms. Long noted that this part of the path has always been part of the open space dedication. If she
understood the request the Commission was asking that they add to the dedication in this area. The
engineer says it is roughly about an acre of space. What they need to do is work with County staff to
establish the boundaries of the additional area. They need to maintain a buffer around this building.
They think they can commit to an additional half acre. They need to reserve space because there is
a water line easement and sewer line easement. They need to reserve rights for the space for the
utility easements and for the necessary buffer. But they can do a half acre at least and perhaps
more. They need to work with staff on the boundaries. There are critical slopes right behind Building
6 which is part of the preservation area.
Mr. Strucko asked if they would stop the path where the proposed connection with Carmike is
Ms Long said that was acceptable to the applicant because they ultimately need the Board to
support it. They would expect if that was the recommendation of the County's professional staff and
Commission that it would be approved by the Board. They will have to take the Board's ultimate
direction. But, that is acceptable to the applicant.
Mr. Fritz noted that staff will have to go to the Board to explain along with the minutes what the
Commission is looking for. The Commission is looking to add some of the wooded area that is
behind Building 6 which would just be preserved as a natural wooded area to enhance the area that
the County has as part of the Lagoon Project, but not part of the Lagoon Project. The topography
does not lend itself to be part of the Lagoon Project. This area would be part of a natural area. The
path would stop at the point of connection to the Carmike of the pedestrian connection. They would
have to work with the applicant to identify what those boundaries are before they go to the Board of
Supervisors because they need to draw a line on the plan.
Ms. Porterfield noted that the path would shrink down to the 5' path.
Mr. Fritz noted that he had not gotten there yet. He asked if that was the consensus of the Planning
Commission.
Mr. Edgerton said that he thought that the path had disappeared
Ms. Porterfield said she was talking about the path from Rio Road all the way through Arden Place
at a width of 5' with the applicant maintaining that path.
Mr. Fritz noted that it would bring the standard down to 1A.
Mr. Franco noted that he received a phone call from one of the officials of ACAC today that
suggested that this was a good project and liked the idea of the path for use by its members. Right
now they run around the parking lot. He felt the path would be useful to his business and the
community.
ALBEMARLE COUNTY PLANNING COMMISSION 27
SEPTEMBER 9, 2009 FINAL MINUTES
Mr. Morris asked if staff needs to bring it back if in fact the Carmike connection works out.
Mr. Fritz replied if the Commission decides that it is not a substantial change warranting coming back staff
will process to the final site plan administratively.
Mr. Morris recommended that.
Mr. Strucko said that if the Carmike connection does not work what would they tell staff to fall back on.
Ms. Porterfield replied that they would go with the two on the other side, one directly off Rio and the other
off Rio via Putt Putt.
Mr. Fritz noted that the potential condition he had written was: No access directly to Rio Road if access
to Carmike is provided.
Mr. Strucko said that if access to Carmike is not provided then the Commission would want the access to
Rio Road and through Putt Putt.
Mr. Franco noted that he was not sure that no access so much as no access is required. He asked if they
are saying that they would prohibit access in the future.
Mr. Fritz said that because this is a ministerial action that a future ministerial action could undo the
condition to allow the commercial property to develop. He asked if that was what he was referring to.
Mr. Franco replied yes.
Mr. Fritz said that when that commercial property came in it would be looked at anew and the same
process they are placing the condition on could be used to remove the condition in the future.
Mr. Strucko asked if they still need the buffer disturbance waiver with the direct access. He noted that the
Commission was okay with the critical slopes.
Mr. Fritz replied yes.
Ms. Porterfield suggested that something be done to avoid needing an applicant to have to request a
waiver for man-made critical slopes. Such a request could be to staff to administratively approve it.
Mr. Fritz noted that staff is working on that.
Mr. Franco asked as part of the final recommendation that goes forth he would also like to say that the
path stuff and the acreage behind building 6 that they have been talking about is a recommendation to
the Board of Supervisors. If the Board chooses to do something different, he was happy to approve this
site plan as recommended or with the conditions associated with that land that the Board sees fit to place
on it without having to come back to the Commission.
Mr. Morris agreed.
Mr. Franco said that the Commission is recommending the bonus density for dedication of land for public
use; that dedication includes building a path from Rio Road to basically the Carmike entrance area as
discussed and dedication of additional land for addition to the lagoon project, but not with a path that the
applicant is building. That is the recommendation to move forward to the Board. If that is amended
somehow at the Board as part of their process he did not want particularly to see this come back to the
Commission for another round.
Ms. Long agreed.
Mr. Strucko asked that a motion be crafted.
ALBEMARLE COUNTY PLANNING COMMISSION 28
SEPTEMBER 9, 2009 FINAL MINUTES
Motion for Critical Slopes Waiver Request:
Motion: Mr. Franco moved and Ms. Porterfield seconded for approval of the critical slopes waiver
request per Section 4.2 for SDP-2009-00009, Arden Place based on the findings in the staff report that it
met the minimum criteria.
The motion passed by a vote of 7:0.
Motion for Buffer Disturbance Waiver Request:
Motion: Mr. Franco moved and Ms. Porterfield seconded for approval of the waiver request for
disturbance of a buffer zone adjacent to a residential district from Section 21.7.c of the County Code for
SDP-2009-00009, Arden Place for the reasons stated by staff.
The motion passed by a vote of 7:0.
Motion for SDP:
Motion: Mr. Franco moved and Mr. Morris seconded for approval of the preliminary site plan SDP-2009-
00009, Arden Place with the conditions recommended in staff report, with amendment of condition F to
reflect the discussions of tonight to eliminate the applicant building a path from the potential Carmike
entrance to the Lagoon Project and to include the dedication of land between those two points.
Mr. Fritz noted that condition G needed to be amended, which will change the trail type from a Class A
Type 2 to a Class A Type 1. The new condition would be no access directly to Rio if access to Carmike is
provided.
Mr. Strucko asked what the dimension of the trail would be with the new classification.
Mr. Gatobu replied the trail would be 5'.
Mr. Fritz noted the condition to be included should read: The Path shall not extend north of Carmike
pedestrian connection.
Mr. Franco agreed for acceptance of the two conditions as stated by Mr. Fritz.
Mr. Morris seconded the amendment.
Mr. Franco said that the trail standard would be Class A Type that would have a 5' width surface.
Mr. Fritz asked if there was any further discussion.
Mr. Franco said that one last amendment was that they were still considering that to be the width but they
were trying to design the trail to ADA standards.
Mr. Fritz said that it would be the design alignment which has a 10' maximum and the 2' upgrade.
Mr. Franco said that the one underneath said ADA accessible.
Mr. Fritz suggested the condition say with design alignment with a Class A Type 2, and Mr. Franco
agreed that was what he wanted to say.
Mr. Morris seconded the amendment.
Mr. Strucko asked that the roll be called.
ALBEMARLE COUNTY PLANNING COMMISSION 29
SEPTEMBER 9, 2009 FINAL MINUTES
The motion passed by a vote of 7:0 with the following conditions.
A. Must comply with the Virginia Statewide Fire Prevention Code. Approval is subject to field
inspection and verification. [Fire and Rescue]
B. RWSA capacity certification is required before final site plan approval can be granted.
C. Proposed wooded area must meet the definition of "wooded area" found in section 3.
[Albemarle County zoning ordinance]. An arborist report and a tree preservation plan
must be submitted with the final site plan.
D. A conservation plan checklist must be shown on the final site plan. The conservation plan
checklist will have to be checked and signed [Albemarle County Code section 32.7.9.4.b.]
E. Applicant must obtain VDOT approval before final site plan approval can be granted.
F. Albemarle County Current Development Engineering approval must be obtained.
G. Add the following 2 notes to the Arden Place ADA Trail Feasibility Exhibit dated 8-5-09,
and include the exhibit in the final site plan. The first should go above the part that
begins, "Trail width..." It should say, "ADA Standards Listed in the Virginia Trail ways
Toolbox". The second note should say, "The trails shall have ADA-accessible grade and
conform to standards for Class A, Type 1 Trails as described in the Albemarle County
Design Standards Manual." The 5-foot wide path shall not extend north of the Carmike
pedestrian connection.
H. There will be no vehicular access to Rio Road from Arden Place other than from Putt Putt
Place if vehicular access to Carmike is provided.
I. Applicant must address all outstanding ARB conditions before final site plan approval can
be granted.
Motion for Approval of proposed dedication to County of Open Space of Dedication of path:
Motion: Mr. Franco moved and Mr. Morris seconded to recommend approval to the County of the open
space of the proposed pedestrian path running from Rio Road to the potential Carmike entrance with the
additional dedication to be defined by staff before it goes to the Board.
Mr. Fritz noted that the dedication would be in the area behind Building 6 adjacent to the Lagoon project.
Ms. Porterfield added that the applicant is going to do maintenance of the path.
Mr. Franco amended the motion to include Mr. Fritz's statement with the understanding that the applicant
is doing maintenance of that path and that if this condition changes at the Board as part of their
acceptance that it does not affect the preliminary site plan approval.
Mr. Morris seconded the amended motion.
The motion passed by a vote of 7:0.
Mr. Strucko said that SDP-2009-00009, Arden Place was approved and would go to the Board of
Supervisors on a date to be determined just for the open space review with the following
recommendation:
The Planning Commission recommended approval to the Board of Supervisors of an open space
dedication including a proposed pedestrian path running from Rio Road to the potential Carmike entrance
and an additional land dedication to be defined by staff before it goes to the Board as follows:
1. The dedication would be in the area behind Building 6 adjacent to the Lagoon project.
2. The path shall be designed as a 5-foot wide Class A, Type 1 path with ADA-compliant grades.
The applicant will provide maintenance of that path.
3. If either of the Commission's recommended conditions change as part of the Board's acceptance,
the changes do not affect the Commission's preliminary site plan approval.
Old Business:
ALBEMARLE COUNTY PLANNING COMMISSION 30
SEPTEMBER 9, 2009 FINAL MINUTES
Mr. Strucko asked if there was any old business.
Mr. Franco noted a phone call from a business in his district regarding delayed scheduling of a ZMA and
SP.
Mr. Cilimberg responded that scheduling was based on the schedule for review of submitted information.
The applicant recently submitted new proffers, which went under review as of today. The earliest date
the project could be scheduled after comments are provided to the applicant following staff review would
be Nov. 10. Staff will contact the applicant and provide them an option of being scheduled in October if
they do not wish to receive staff comments.
There being no further old business, the meeting moved to the next item.
New Business:
Mr. Strucko asked if there was any new business.
Mr. Fritz noted based on the question on critical slopes staff plans to hold a round table or a work
session with the Commission and take the proposed changes to the Board in the winter. Staff is
working on it.
• Since only two Commissioners, Franco and Porterfield were attending the Places29 open house at
the Fire Station the meeting did not have to be adjourned to that date September 10, 2009.
There being no further new business, the meeting moved to the next item.
Adjournment:
With no further items, the meeting adjourned at 9:39 p.m. to the Tuesday, September 15, 2009 meeting at
6:00 p.m. at the County Office Building, Second Floor, Auditorium, 401 McIntire Road, Charlottesville,
Virginia.
v
V. Wayne CilirCerg, Secretary
(Recorded and transcribed by Sharon C. Taylor, Clerk to Planning Commission & Planni�oards)
Note:
ATTACHMENT A — Consent Agenda PC REFERRAL CONSENT AGENDA TEXT
ALBEMARLE COUNTY PLANNING COMMISSION 31
SEPTEMBER 9, 2009 FINAL MINUTES