HomeMy WebLinkAboutSUB202100118 Review Comments Road Plan and Comps. 2021-08-26 (2)V 401 McIntire Road, North Wing County of Albemarle Charlottesville, VA 22902-4579 Telephone:434-296-5832 COMMUNITY DEVELOPMENT DEPARTMENT WWW.ALBEMARLE.ORG Road and Drainage Plan Review Project title: Biscuit Run Park Phase 1 Project file number: SUB-2021-00118 Plan preparer: Anhold Associates David Anhold [david@anholdla.com] Owner or rep.: County of Albemarle Steve Hoffman [shoffman n@k12albemarle.org] Plan received date: 5 July 2021 Date of comments: 26 August 2021 Reviewer: Matt Wentland David, We have reviewed the plans and have the following comments: Engineering 1. Replace the SDP number with the SUB202100118 number on the cover sheet. VDOT VDOT comments are attached to this email. ACSA — Richard Nelson The road plans are currently under review with ACSA. Fire Rescue — Howard Lagomarsin Per plans dated 6/21/21: 1. Please provide no parking signs for section of roads/travelway that do indicate parking spaces. This includes the route from Scottsville Rd to the parking lot and the curve around the end of the parking lot. Planning, ARB and GIS had no objections to the plans. Engineering Review Comments Page 2 of 3 Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Process: After approval, plans will need be bonded. The bonding process begins when the plan is approved, and the applicant submits a bond estimate request form and fee to the Department of Community Development. A plan reviewer will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted to the County, who will record the agreement. After bonding and agreements are complete, county staff enters project information in a DEQ database for state application processing, if a DEQ permit is required. DEQ reviews the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter, which must be posted at the construction site. After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Applicants must complete the request for a pre -construction conference form and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre - construction conference, should everything proceed satisfactorily, ajoint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; httos://www.a lbemarle.org/government/com m un ity-develoi2ment/a pply-for/engineering-applications If you have any questions or concerns, please contact me either by email (mwentlandC@albemarle.org) or by phone at 434-296-5832 ext. 3458. Sincerely, Engineering Review Comments Page 3 of 3 Matt Wentland, P.E. Civil Engineer II File: SUB202100118 Biscuit Run Park Phase 1 review comments 08-26-21.clocx