HomeMy WebLinkAboutSP201900002 Presentation 2020-07-14SP2O19-02 Pleasant Green
PLANNING COMMISSION PUBLIC HEARING
J U LY 14, 2020
SP201900002 Pleasant Green— fill in the floodplain SP
Request to amend SP2016-003 West Glen SP to relocate the
stream crossing
o Special Use Permits required for fill in the Flood Hazard Overlay
under Section 30.3.11 of the Zoning Ordinance.
Location
TM Ps: 05600-00-00-11500;
056A1-01-00-030A0; 055C0-03-
00-OOOA1
South of Cling Lane, northeast of
Peach Tree Dr. and Orchard Dr.,
West of Blue Ridge Ave.
Zoned R-6 Residential
Flood Hazard Overlay along
Powell's Creek
Crozet Master
Plan
Neighborhood Density
Residential (yellow)
Greensapce (green)
No stream crossing shown in
this location
Conceptual road network
connecting through parcels
to the east
PROPOSED CONNECTION
TO CLING LN
WETLANDS (TYP)
-PROPOSE I
--
CROSSING
m .J:iI _ - O�y-. � `+ + c °.y%•• - i�1 10, Wz 10'H
J
TRIPLE BOX CULVERT
1OAR0 MANAGED SLOPESPER A
'*�
TORM BELOW W , �SRLE [ t- d 500 YR FEMA FLOODPW -1
3 1OO'STREAM BUFF _ .� •`'. •�' �/. �, 34
- r._
rH /
W�
BOX CULVERT _ _ -
1 j\ G
-- `O' STREAM BUFFER --. WETLANDS 4TY
OPEN
`:._ •a- -- _ - _ li. '--_ �_ STREAM `PROPOSED -
_ - TRAIL EASEMENT 1- -
4 RO _ - I CENTERLINE
RAIL MEN
C,., TREEDltl1- PRE S�EDSLOPES—L _ II.L �'
PER BEMARLE CEOUNW GIS E PROPOSED FILL I
COUNTNTYGIS FEMA FLOODPWN
FRINGE • QpyCHARD OR
Ex,snNG-
SANITARY
SEWER
TO REMAIN
History
SP1990-103 special use permit for fill in the
floodplain that allowed existing crossing of
Powell's Creek and construction of Cling Lane.
Condition of SP1990-103: Stream crossing to
provide access to 30 lots; no development of
residue property or access to adjacent
properties allowed until second access is
provided to Orchard Drive.
SP2016-003: Fill in the Floodplain Special Use
permit approved for the crossing of Powell's
Creek to allow the development of the residue
property
SDP2019-009 and SUB2019-108- Approved site
plan and subdivision for Phase 1.
SDP2020-019 and SUB2020-033- Phase 2 Initial
Site Plan and Preliminary Plat under review
itigatic
easure
o-�
Favorable Factors:
1. The new location of the stream crossing will greatly reduce the
impact on the stream, buffer, and floodplain than the previous
location.
2. The stream crossing will allow development of the property
consistent with the Crozet Master Plan.
3. The applicants are proposing a greenway dedication in an area
identified for greenway within the Crozet Master Plan, which will
help ensure preservation of the stream buffer.
4. The stream crossing in this location promotes interconnectivity
and disperses traffic onto a road system that is able to handle the
additional traffic load.
Unfavorable Factors:
1. The Crozet Master Plan does not identify a road with a stream
crossing in this location and the Comprehensive Plan recommends
that roads with stream crossings only occur in areas shown in the
Master Plans.
Staff recommends approval of SP2019-02 with the following conditions:
1. The culverts under the proposed Connector Road extension over
Powell's Creek must be in general accord with the attached Concept Plan
titled "Pleasant Green Subdivision Special Use Permit Plan" (the "Plan")
prepared by Collins Engineering with a revision date of May 20, 2019. To
be in general accord with the plan, development must reflect the general
size, arrangement, and location of the culverts, as well as maintaining no
increase of the 100 year flood elevation outside of the Pleasant Green
property. Modifications to the plan, which do not conflict with the
elements above may be approved subject to the review and approval of
the County Engineer
2. Prior to final road plan approval or permitting of a land disturbance in
the floodplain, the applicant must obtain from the Federal Emergency
Management Agency (FEMA) a conditional letter of map revision
(CLOMR, or CLOMA), and prior to road acceptance the applicant must
obtain from FEMA a letter of map revision (LOMR or LOMA). In addition,
the applicant must copy the County Engineer on all correspondence with
FEMA. Construction and installation of the culverts must be in
compliance with approved road plans and FEMA approved CLOMR or
CLOMA.
Conditions cont'd...
3. Any residential lots and associated streets resulting from the
subdivision of the property, with the exception of the stream crossing
and roadway identified on the attached plan as Connector Road, must be
located outside of the 100 foot stream buffer, Flood Hazard Overlay and
preserved slopes on the property. Lots may be permitted to be located
within the landward 10 feet of the 100 foot stream buffer only if the lots
are adjacent to approved stormwater management facilities located
within the landward 50 feet of the stream buffer. Approval of lots located
within the stream buffer must be subject Subdivision Agent approval.
4. The net density of the property must not exceed 6 units per acre, in
accordance with the Crozet Master Plan. Net density must be calculated
by subtracting the area within the Flood Hazard Overlay District, the100
foot stream buffer and areas of preserved slopes from the total acreage
of the property subject to the special use permit.
5. Prior to issuance of a grading permit to allow installation of the stream
crossing or with submittal of the final subdivision plat, whichever comes
first, the applicant must submit an easement plat dedicating to the
county the area identified for a greenway trail on the attached plan.
Conditions cont'd...
6. If the construction of the stream crossing for which this Special
Use Permit is issued is not commenced by [insert date 5 years
after the date the County Board approval of the Special Use
Permit], the permit will be deemed abandoned and the authority
granted there under will thereupon terminate.
7. Prior to approval of the first final Virginia Stormwater
Management Program (VSMP) plans or the first final subdivision
plat, whichever comes first, the applicant shall conduct a Phase II
Environmental Site Assessment (ESA) in accordance with ASTM
standards. The Phase II ESA shall include sampling and testing of
accumulated sediment behind the dam that exists on the
Property. The applicant shall be required to comply with all
recommendations of the Phase II ESA prior to issuance of the first
building permit on the Property. The applicant shall also be
required to remove accumulated sediment from behind the dam
prior to demolition of the dam and dispose of the sediment,
either on site or off site, in accordance with the Phase II ESA
recommendations.
Motion
A. Should the Planning Commission choose to recommend
approval:
Move to recommend approval of SP 2019-002 Pleasant Green
with conditions recommended by staff.
B. Should the Planning Commission choose to recommend
denial:
Move to recommend denial of SP 2019-002 Pleasant Green
(state reasons for denial).
Total Acres:
Total Possible
Units:
39.422
237
Density Information- Pleasant Green
SDP2016-11 The Vue