HomeMy WebLinkAboutWPO201900006 Correspondence 2019-04-29 WOOLLEY ENGINEERING
April 29, 2019
MEMORANDUM
To:
i ngineer
County of Albemarle,Virginia
From: Mr. Eric Woolley, PE
Woolley Engineering
Regarding: The Covenant School- Major Amendment (TM 90-A P 2)
VSMP Permit Plan Review
With this memo, we are responding to the comments that were directed to our office following the
review of our site plan for a new recreation area at The Covenant School. The comments were
received in written format and dated March 19, 2019. I have attached this response memorandum
to two (2)revised full-sized copies of the site plan.
Stormwater Pollution Prevention Plan (SWPPP)
1. Please find the signed Certification sheet attached to this memorandum. This
Certification is to be included in the SWPPP which was already submitted to the County.
Pollution Prevention Plan (PPP)
1. Please find an 11" x 17" copy of the PPP attached to this memorandum which shall be
inserted into the SWPPP which was already submitted to the County.
Stormwater Management Plan (SWMP)
1. The cited SDP from note 14 on C1.0 has been corrected. A stormwater management
table has been added to C6.0.
2. Riprap has been extended from the new drainage pipe to the toe of the slope leading to
the existing biofilter. The gravel diaphragm has been relocated to a more suitable
location which is less steep.
3. A table with calculations for the stormwater management strategy has been added to
sheet C6.0.
4. Callouts have been added to C5.0 stating which retaining walls require building permits.
Additional retaining wall details can be found on S 1.0 and S2.0.
WOOLLEY ENGINEERING 220 East High Street (434) 973-0045
Charlottesville,Virginia 22902
NM
WOOLLEY ENGINEERING
Erosion & Sediment Control Plan (ESCP)
1. No comments.
I hope that these responses, in combination with the revised site plan have satisfied the deficiencies
as noted in your previous comment memorandum. Please do not hesitate to call with any questions
or concerns. Thank you for your time and consideration.
Sincerely,
, ,,..--. ..,---z.....4e
Eric Woolley, PE
Attached: (2) Site Plan
(1) SWPPP Certification
(1) PPP
Cc: Frank Berry, The Covenant School
File
2