HomeMy WebLinkAboutWPO201900006 Bond Estimates 2019-05-22 The Covenant School - Major Amendment
WPO file number: WP0201900006
TMP(s): 090A0-00-00-00200
Date Estimate Completed: 5/22/19
Erosion and Sediment Control Bond Estimate
Item Item No Unit Unit Cost Cost
Number (installed)
stablization(PS,TS) 0 5 acres $5,000 00 $2,500 00
silt fence(SF) 315 0 ft $5 00 $1,575 00
safety fence(SAF) 4000 ft $5 00 $2,000.00
diversion(DD,FD,RWD) Mill.ft $13 00 $0 00
temporary slope drain(TSD) pipe length 0 ft pipe diameter _in $0 00 $0 00
earthwork for trap/basin
height of dam at toe • 0 ft cut at high side ft
height of fill at face 0 ft cut at face ft
length of dam 0 ft length of cut ft
top width 0 ft width of cut ft •
(area above transition 0 sf (area below transite 0 sf
(total width of dam) 0 ft (total width of cut) 0 ft
(height below transitio 0 ft (depth below transit 0 ft
(area below transition; 0 sf (area above transitii 0 sf
(total fill volume) 0 0 cy (total fill volume) 0 0 cy
length of spillway _ft (TOAL CY estimate 0 cy $13 00 $0 00
width of spillway ft (spillway stone tons 0 tons $50 00 $0 00
structures for basin
riser height ft
riser diameter in (riser unit price) SO 00 $0 00
barrel length ft base plate or fdn $200 00 $0
barrel diameter in (barrel unit price) SO 00 $0 00
barrel collars $200 00 $0
baffle length ft $50 00 $0
silt fence inlet protection(IP) $100 00 $400 00
stone inlet protection(IP) $200 00 $400 00
outlet protection(OP) length ft width ■ft $607 50 $607 50
channel(SCC,matted) length ft width ft $0 00
check dam depth in channel ft channel width ft $0 00 $0 00
construction entrance(CE) $2 500 00 $2,500.00
wash rack $2 000 00 $2,000 00
paved construction entrance $3,500 00 $0 00
rip-rap,placed depth ME ft length RIM ft
width $60 00 $0 00
survey and layout(price per 0 1 mi) acres Mill traps and basins — $250.00
mobilization $2,500 00
stream crossing(computed independently) $0 00
cost sum $14,732 50
contingency $1,473 25
5/22/2019
The Covenant School - Major Amendment
WPO file number:WPO201900006
T M P(s): 090A0-00-00-00200
Date Estimate Completed: 5/22/19
Erosion and Sediment Control Bond Estimate
Item Item No. Unit Unit Cost Cost
Number (installed)
Total $16,210
5/22/2019