Loading...
HomeMy WebLinkAboutSDP202100056 Correspondence 2021-09-23/A® SEH Building a Better World for All of Us® September 21, 2021 Andy Reitelbach Senior Planner Planning Services Division Albemarle County 401 McIntire Road Charlottesville, VA 22902 Dear Mr. Reitelbach: RE: SDP2021-00056 Airport Road Pump Station Project Final Site Plan Review Response Letter Rivanna Water & Sewer Authority SEH No. RIVAN 153082 14.00 We received your August 12, 2021 letter with review comments on our final site plan submittal SDP2021- 00056 for the RWSA's Airport Road Pump Station. On behalf of the Rivanna Water & Sewer Authority of Albemarle County, Virginia, we have prepared this letter in response to your comments. Our letter is formatted to list your inquiry/comment in regular or bold font followed by our response in italics font. 1. [32.5.2(a)] Identify on the cover sheet that this plan is a "final site plan." Also, provide the application number on the cover sheet of the plan — SDP2021-00056. Response: The cover sheet has been updated to reflect that this is a "final site plan". The application number has been added to the cover sheet 2. [32.5.2(a)] The signature line for the Health Department can be removed from the approval box on the cover sheet. This site is within the jurisdictional area of the Albemarle County Service Authority (ACSA). Response: Virginia Department of Health has been removed from the approval box on the coversheet. 3. [32.5.2(a)] On the cover sheet, provide an address for the property owner. Response: The address for the property owner has been added to the cover sheet. 4. [32.5.2(b)] Clarify why the proposed impervious area identified on the cover sheet is less than the sum of the building footprint, generator enclosure, and paved parking/vehicular circulation area. Response: This is a typo and has been updated on the cover sheet. 5. [32.5.2(c)] As it appears that the ground storage tanks are to be built at a later time, either Engineers I Architects I Planners I Scientists Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive, St. Paul, MN 55110-5196 SEH is 100 % employee -owned I sehinc.com 1 651.490.2000 1 800.325.2055 1 888.908.8166 fax SDP2021-00056 Airport Road Pump Station — Final Site Plan Review Comments Letter Page 2 remove them from this plan, or provide phase lines/information on the plan identifying the limits of the future phase(s). Response: The dashed lines depicting the anticipated location of the future tanks have been removed from the plan sheets and replaced with the following note "SPACE FOR ANTICIPATED FUTURE GROUND STORAGE TANKS". 6. [32.5.2(i)] Provide the state route number for Berkmar Drive on the site plan layout sheet (sheet C09). Response: The state route number for Berkmar Drive has been added to Sheet C09. [32.5.20); 32.5.2(k)] An easement plat will be required for all stormwater management facility, drainage, and access easements. This easement plat will need to be reviewed, approved, and recorded prior to the approval of the final site plan. 8. [32.5.2(n); 4.17] Outdoor lighting. a. The light loss factor (LLF) on the photometric plan (sheet DE1) must be 1.00. Revise the luminaire schedule with an LLF of 1.00. Response: Sheet DE1 has been revised and updated with a light loss factor of 1.00. b. Revise the photometric plan calculations to reflect an LLF of 1.00. Response: Sheet DE1 has been revised and updated with a light loss factor of 1.00. 9. [32.5.2(p); 32.7.9] Landscape plan. a. The Conservation Plan checklist on the landscaping plan sheet will need to be completed, signed, and dated by the property owner prior to approval of the final site plan. Response: The landscaping plan has been signed and dated by the property owner. b. It is suggested that the label for the proposed undisturbed buffer along the southwestern property line be revised to separate the 20' undisturbed buffer at the rear of the property from a "variable width" undisturbed buffer closer to the proposed Berkmar Drive right-of-way, to accommodate the proposed clearing and replanting that will occur in that area. Response: The "20.0' UNDISTURBED LANDSCAPE BUFFER" was kept on the plans. This gives the onsite representative of the Owner and Engineer more control in minimizing tree removal. c. In the landscaping schedule, provide the number of Virginia Pines that are proposed to be planted. In addition, provide the caliper of the proposed trees, and the expected height of the trees at ten years maturity after planting. Response: The landscaping schedule has been updated to reflect this information. The original comments from the review and action letter for SDP2020-00060 are in gray font. Follow- up comments from the review of the final site plan, SDP2021-0056, are in bolded black font. Please address these follow-up comments as well. SDP2021-00056 Airport Road Pump Station — Final Site Plan Review Comments Letter Page 3 1. [32.5.2(b)] Include the generator and its enclosures in the list of proposed uses on the cover sheet of the plan Also, provide the square footage and height of the generator enclosure on the cover sheet and on the layout plan. Clarify the structure that is enclosing the generator and portable pump. Are they enclosed within the building, or is a fence surrounding these elements? Response: The generator has been added to a list of uses on the cover sheet. The generator is covered by an extension of the pump station roof, so the height is the same as the building. There are no walls or fence surrounding the generator, it is open on all sides. A fence will be provided around the perimeter of the site. 2. [32.5.2(b); 4.12.7] As the proposed use is an unscheduled use in regard to the Parking requirements, Section 4.12, submit a letter to the Zoning Administrator with a request for the proposed number of parking spaces. This request must include justification for why the proposed number of parking spaces is expected to provide sufficient parking capacity for the proposed use. The number of parking spaces required for this use will ultimately be determined by the Zoning Administrator. This comment has not been addressed. Submit a letter addressed to the Zoning Administrator with justification for the proposed number of parking spaces to be provided. The ultimate determination on the required number of parking spaces will be made by the Zoning Administrator. Response: A letter has been prepared and submitted to the Zoning Administrator for this determination. This letter has also been enclosed following this response letter. 3. [32.5.20); 32.5.2(1)] Identify all existing sewer and drainage facilities, as well as all existing and proposed utilities. a. An approved easement plat will be needed for the proposed utilities and stormwater facilities. Once recorded, the deed book and page number(s) for the new easements will need to be noted on the plan before final approval can be granted. This comment must still be addressed. Response: An easement plat will be prepared for the stormwater facilities once the County has approved of the proposed design. 4. [32.5.2(k)] Proposed sewer and drainage facilities. Depict these facilities and their dimensions. If necessary, an approved and recorded easement plat will be required prior to approval of a final site plan and/or final subdivision plat. (This comment and the comment above are standard comments for all site plans, and staff recognizes that they may not apply to this project in the same way as most other projects since this site plan is for an RWSA facility.) This comment must still be addressed. Response: There is no sewer associated with the project. Stormwater facilities have been updated as per conversations with J. Anderson. 5. [4.1] Provide a note on the cover sheet identifying whether this property is located within the ACSA jurisdictional area. This comment has not been addressed. Response: This comment has been addressed. Albemarle County Architectural Review Board (ARB) - Khris Taggart, ktaggart(aalbemarle.org 1. No details have been provided on the appearance of the ground storage tanks. If the ground storage SDP2021-00056 Airport Road Pump Station — Final Site Plan Review Comments Letter Page 4 tanks are proposed with this submittal, provide details on the architectural designs of the ground storage tanks, including a color sample. If details on the appearance of the ground storage tanks are unavailable at this stage, revise the site plan to remove all references to the ground storage tanks. Response: As per email correspondence with K. Taggart, the dashed lines depicting the anticipated locations of future tanks have been removed from the plan sheets and replaced with the following note "SPACE FOR ANTICIPATED FUTURE GROUND STORAGE TANKS'. See comment #1 regarding notes/references to ground storage tanks. If details on the appearance of the ground storage tanks are unavailable at this stage, revise the site plan to remove all references to the ground storage tanks. Response: As per email correspondence with K. Taggart, the dashed lines depicting the anticipated locations of future tanks have been removed from the plan sheets and replaced with the following note "SPACE FOR ANTICIPATED FUTURE GROUND STORAGE TANKS'. 3. The standard mechanical equipment note is not included in the site plan. Revise the plan to include the standard mechanical equipment note: " Visibility of all mechanical equipment from the Entrance Corridor shall be eliminated." Response: This note has been added to Sheet A200 4. The LLF of the proposed fixtures is less than 1.0. Revise the photometric plan using an LLF of 1.0 for all fixtures. Response: Sheet DE1 has been revised and updated with a light loss factor of 1.00. No details on the view of the ground storage tanks from Airport Rd. have been provided. If the ground storage tanks are to be proposed and reviewed with this submittal, provide site sections that show the view of the site, including the storage tanks from the Airport Rd. frontage. Response: As per email correspondence with K. Taggart, the dashed lines depicting the anticipated locations of future tanks have been removed from the plan sheets and replaced with the following note "SPACE FOR ANTICIPATED FUTURE GROUND STORAGE TANKS.. Albemarle County Engineering Services (Engineer) - John Anderson, ianderson2(c@albemarle.org Requested changes; see the attached checklist and comment memo. Response: Responses to the comment memo are below: 1. Recommend revise plan title to include ref. to SDP202100056. Response: This has been added to the title sheet. 2. Revise T01 to include reference to related plan, WPO202100035. Response: This reference has been added. 3. Revise sheet list, T01, to remove ESC-SWM-PPP (WPO plan -related) sheets from the final site plan. Response: The sheet list and the sheets included in the resubmittal have been updated to address this comment. 4. Revise T01 topography note to confirm existing topography has been at least visually verified within the last 12 months [See Final Site Plan checklist for plan reviewers, p. 1, Existing conditions plan view information; 2nd item —ref. attached]. SDP2021-00056 Airport Road Pump Station — Final Site Plan Review Comments Letter Page 5 Response: This note has been added. 5. Coordinate final site plan design with VDOT. VDOT has near -term plans to extend Berkmar Drive Ext. to Airport Drive. Ensure that the final site plan proposed grade (final contours) are consistent with roadway extension. At present, they are not. Proposed grade suggests relatively abrupt rise into the site, with gradual fall, west to east, across the site. Ref. sheet C12, Grading Plan. If grade is to be flatter, consistent with future Berkmar Drive Ext. roadway, then grades must be lowered across the site. Retaining walls may be required between proposed development and parcel to immediate north in order to eliminate 4'-5' grade rise at entrance to RWSA pump station. Retaining walls are a common remedy for addressing grade issues. Retaining wall ht. > 4-ft. requires a sealed geotechnical retaining wall design. Please coordinate directly with VDOT on Berkmar Drive Ext. (future) design, and accommodate reasonably -predictable VDOT Berkmar Drive Ext. future design needs. Note: Virtually all sheets of the FSP show and label Anticipated VDOT Grading Easement (Typ.), yet the FSP proposes grades that conflict with Berkmar Drive Ext. future grading. Please revise FSP consistent with anticipated VDOT Grading Easement. Response: We are aware of the future extension of Berkmar Drive. The Owner and Engineer have coordinated with VDOT to the best extent possible. The plans for the permanent site access drive have been coordinated with preliminary drawings in an effort to minimize future conflicts. Please remove sheet C09 bioretention basin specific design elements (footprint with label is fine), as well as sheets C10, C11, C13, C16, DC03 from the site plan since ESC measures and SWM facilities are not approved with a site plan, but with a WPO plan. WPO plan review is pending (WPO202100035). Response: These sheets have been removed from the set and the Sheet List on T01 has been updated. C12: Provide final disposition of runoff along south side of site access; specifically: provide channel lining design and velocity/capacity calculations for runoff in ditch -line between contours 623 and 615. Proposed grade routes runoff to a bend in site access, at which point runoff appears to sheet across site access without routing to any SWM capture or conveyance system. Include a new Drainage Plan sheet that shows storm runoff collection and conveyance. Response: Stormwater facilities have been updated as per conversations with J. Anderson and are shown in the resubmitta/ of the WPO plan. 8. With WPO Plan, account specifically for increased sheet flow from impervious parking and site access (reasonably anticipated to occur) along south side of development, given close proximity to property line. Response: Stormwater facilities have been updated as per conversations with J. Anderson and are shown in the resubmittal of the WPO plan. 9. C15: Engineering defers to Planning Division as to whether proposed grading within 20.0' undisturbed landscape buffer qualifies as undisturbed. C08, Existing Conditions, accurately describes existing condition as 'existing wooded area mix of deciduous and evergreen trees.' The site is 100% mature canopy mix. If mature mix of deciduous and evergreen trees is removed, replacements will not attain maturity for decades. Engineering defers to Planning, but if site grade is lowered, generally, it may be not only feasible but relatively easy to preserve 20.0' undisturbed landscape buffers along parcel boundaries, for the entire development. Engineering encourages SDP2021-00056 Airport Road Pump Station — Final Site Plan Review Comments Letter Page 6 design to preserve an undisturbed landscape buffer to the maximum extent practical. Retaining walls may aid in addressing this and other review comments. Response: This was not noted in the comments from the Planning Division. The minor grading and replanting in the 20-foot buffer was designed in an effort to maintain as much of the mature canopy as possible and is believed to be preferable to planting vegetative screening through a double staggered row of evergreen trees planted 15-feet on center, as described in 32.7.9.7.e. Albemarle County Information Services (E911) - Elise Kiewra, ekiewra(,aalbemarle.org No objections at this time. Response — Noted. Albemarle County Building Inspections - Betty Slough, bsloughno.albemarle.org Add the following note to the general notes page: Buildings or structures built before January 1, 1985 must have an asbestos survey performed in order to apply for a demolition permit. Asbestos removal permits are required if positive for such from Albemarle County and VDOLI. Contact VDOLI for their additional requirements and permits for demolition projects at 540-562-3580 x1 31. Response: This is green field construction and there is no structure demolition as a part of this project. There is only miscellaneous trash/debris removal. To avoid confusion with the Contractor, at this time, the note has not been added. Albemarle County Transportation Planning - Daniel Butch, dbutch(c@albemarle.org No objections at this time. Response — Noted. Albemarle County Department of Fire -Rescue - Howard Lagomarsino, hlagomarsino(&albemarle.org No objections at this time. Response — Noted. Albemarle County Service Authority (ACSA) - Richard Nelson, rnelson(c@serviceauthority.org No objections at this time. Response — Noted. Virginia Department of Transportation (VDOT) -Adam Moore, Adam. Moore(dvdot.virginia.gov No objections at this time; see the attached memo. Response: The contractor will apply for and hold the land use permit for this work. Closure We would like to thank you for your comments and trust that our responses and attachments are sufficient to address your concerns. If you wish to discuss the project or have any additional questions, please do not hesitate to contact me by phone at 507.440.7485 or bweiss@sehinc.com. Sincerely, SDP2021-00056 Airport Road Pump Station — Final Site Plan Review Comments Letter Page 7 Brad Weiss, P.E. Project Engineer Enclosures: Updated Final Site Plan Drawings Parking space determination letter ENCLOSURE A UPDATED FINAL SITE PLAN DRAWINGS