HomeMy WebLinkAboutWPO202000053 Correspondence 2021-09-26Emily Cox
From: Deel, Justin <justin.deel@dcr.virginia.gov>
Sent: Thursday, September 23, 2021 12A2 PM
To: Frank Pohl; Jeremy W. Swink
Cc: Emily Cox
Subject: Re: FW: Pleasant Green Phase 2 SWM Agreements
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Frank,
After further discussion with Kimley-Horn, the Pleasant Green Phase 2 development will not impact the hazard
classification for Upper & Middle Mint Springs Dams, nor will it increase the dam's spillway design flood requirements.
An updated hazard classification was submitted to DCR by Greg Harper, which concluded that both are High hazard
dams. The required spillway design flood for a High hazard dam is 0.9 PMP. The provided study did not include an
attempt to reduce the required spillway design flood using incremental damage analysis. Based on this exclusion it is
assumed that a reduction could not be achieved.
In conclusion, further development within the DBIZ will not increase the hazard classification nor will it increase the
spillway design flood for Upper & Middle Mint Springs Dams, as both items are at their maximum requirements (High &
0.9PMP).
Thank you,
Justin
Justin Deel, P.E.
Regional Dam Safety Engineer
Department of Conservation & Recreation
804-221-0476
On Wed, Sep 22, 2021 at 3:12 PM Deel, Justin <justin.deel@dcr.virginia.gov> wrote:
Frank,
Pleasant Green Phase 2 will not increase the hazard classification. However, it is unclear if the development will affect
the spillway design flood, which was not determined in the new study. My understanding is that information is
forthcoming as an addendum to the study.
Justin Deel, P.E.
Regional Dam Safety Engineer
Department of Conservation & Recreation
804-221-0476
On Wed, Sep 22, 2021 at 2:41 PM Frank Pohl <fpohl@albemarle.ore> wrote:
Justin,
Are you at a point where you can confirm that the referenced project did not change the hazard classification of the
dam? I think we need a response from you before we can proceed.
Thanks,
Frank
Frank V. Pohl, PE, CFM
County Engineer
Albemarle County
fl2ohl Opal bemarl e.org
434-296-5832 x7914
401 McIntire Road, North Wing, Charlottesville, VA 22902
From: Jeremy W. Swink <SwinkJW@stanleymartin.com>
Sent: Wednesday, September 22, 20212:10 PM
To: Frank Pohl <fpohl@albemarle.org>; Emily Cox <ecox2@albemarle.org>; Ana Kilmer <akilmer@albemarle.ors>;
Scott Collins <scott@collins-engineerins.com>
Cc: Ken B. Stubenhofer <StubenhoferKB@stanleymartin.com>; Gregg P. O'Donnell
<OdonnellGP@stanleymartin.com>; Sheldon D. Shifflett <ShifflettSD@stanleymartin.com>
Subject: FW: Pleasant Green Phase 2 SWM Agreements
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Frank / Emily— I have attached a couple of documents. The first is a copy of Justin Deel's approval of the final DBIZ
report that was submitted. The 2nd is a screenshot showing that the Mint Springs Dam is now considered a high
hazard rating in DCR's system. Because the dam is a high hazard rating (excluding Pleasant Green Phase 2), the
proposed development cannot change the hazard rating. I know we have reviewed this over the past few weeks, but I
wanted to provide relevant documentation so we can move the project forward.
With this information in hand and assuming it is consistent with your conversation with Greg Harper, can we clear this
comment, post bonds, record the SWM Agreement and move the project forward starting with the WPO plan
approval?
2021 NATIONAL
BUILDER OF THE YEAR
From: Ana Kilmer <akilmer@albemarle.ore>
Sent: Wednesday, August 18, 2021 10:09 AM
To: Jeremy W. Swink <SwinkJW@stanleymartin.com>; Emily Cox <ecox2@albemarle.org>; Frank Pohl
<fpohl@albemarle.org>; Megan Nedostup <mnedostup@albemarle.ore>
Cc: Gregg P. O'Donnell <OdonnellGP@stanleymartin.com>
Subject: RE: Pleasant Green Phase 2 SWM Agreements
CAUTION: EXTERNAL email.
I received 1 stormwater agreement on 5/7/2021 for WPO-2020-00053. The agreement has not been routed for
approval. Has the pending issue been resolved?
Thankyou
Ana D. Kilmer
Program Administrator
Community Development Department
County of Albemarle
akiImer(c@aIbemarle.ore
Office: 434-296-5832 ext. 3246
401 McIntire Road, North Wing, Charlottesville, VA 22902
From: Jeremy W. Swink <SwinkJW@stanleymartin.com>
Sent: Wednesday, August 11, 20218:41 AM
To: Ana Kilmer <akilmer@albemarle.org>
Cc: Gregg P. O'Donnell <OdonnellGP@stanleymartin.com>
Subject: Pleasant Green Phase 2 SWM Agreements
CAUTION: This message originated outside the County of Albemarle email system. DO NOT CLICK on links or open
attachments unless you are sure the content is safe.
Ana — Hope you are doing well. Gregg is out this week, but I wanted to check with you to see if the County Attorney
has countersigned the SWM Agreements that we signed back in January. I believe the remaining issues with the plan
are being resolved and I wanted to make sure the other loose ends were tied up. If it has been recorded already,
apologies for the extra follow up!
Jeremy Swink
Vice President, Land — Charlottesville and Richmond Divisions
STANLEY MARTIN HOMES
404 People Place #303 Charlottesville, VA 22911
swinkiw(cDstanleymartin.com 571.309.5043
StanlevMartin.com
5 2021 NATIONAL