HomeMy WebLinkAboutWPO202100056 VSMP - SWPPP 2021-10-01Stormwater Pollution Prevention Plan (SWPPP)
For Construction Activities At:
Waverly Residence
Near 7085 Batesville Road
Afton, VA 22920
Prepared by:
Line and Grade, LLC
Prepared for:
Cyrena Sparkman
SWPPP Preparation Date:
September 30, 2021
(This document is to be made publicly available according to 9VAC25-880-70, Part II, section D)
CONTENTS:
1. Registration statement
2. Notice of general permit coverage
3. Nature of activity
4. Erosion and Sediment Control Plan.
5. Stormwater Management Plan
6. Pollution Prevention Plan.
7. Discharges to impaired waters, surface waters within an applicable TMDL
wasteload allocation, and exceptional waters.
8. Qualified personnel
9. Signed Certification
10. Delegation of authority.
11. General permit copy
12. Inspection logs
A. Corrective Action Log
B. SWPPP Amendment Log
C. Grading and Stabilization Activities Log
Section 1. Registration statement
VIRGINIA DEPARTMENT OF ENVIRONMENTAL QUALITY
GENERAL VPDES PERMIT FOR DISCHARGES OF STORMWATER FROM
CONSTRUCTION ACTIVITIES (VAR10)
REGISTRATION STATEMENT 2019
Application type. {L7i NEW PERMIT ISSUANCE
(CHOOSE ONE) ❑ MODIFICATION WITH ACREAGE INCREASE
❑ MODIFICATION WITHOUT ACREAGE INCREASE
❑ EXISTING PERMIT RE -ISSUANCE
Section 1. Operator/Permittee Information.
PERMIT #:
PLAN/ID #:
TECHNICAL CRITERIA: IIB ❑ IIC ❑
A. Construction Activity Operator (Permittee). The person or entity that is applying for permit coverage and will have
operational control over construction activities to ensure compliance with the general permit. A person with
signatory authority for this operator must sign the certification in Section V. (per Part Ill. K. of the VAR10 Permit).
Operator Name:
Cyrena Sparkman, Property Owner (Contractor TBD)
Contact person:
C rena Sparkman, Property Owner (Contractor TBD
Address:
41 Wicket Way; POB 2304
City, State and Zip Code:
Cashiers, NC 28717
Phone Number:
703-200-1947
Primary and CC Email:
cy@sparkman.net; charles.lee.sparkman@gmaiLoom
B. Electronic correspondence. To receive an emailed coverage letter or to pay by credit card, you must choose YES
and include a valid email. May we transmit correspondence electronically? YES 0 NO ❑
Section II. Construction Activity Information.
A.
Include a site map showing the location of the existing or proposed land -disturbing activities, the limits of land
disturbance, construction entrances and all waterbodies receiving stormwater discharges from the site.
B.
Project site location information.
Construction Activity Name:
Waverly Residence
Address:
Near 7085 Batesville Road
City and/or County and Zip Code:
Afton, VA 22920
Construction Activity Entrance Location
(description, street address and/or
latitude/longitude in decimal degrees):
37.995005,-78.743951
Latitude and Longitude
(6-digit, decimal degrees format):
37.995650,-78.743861
C.
Acreage totals for all land -disturbing activities to be included under this permit coverage. Report to the nearest
one -hundredth of an acre.
Total land area of development (include entire area to be
disturbed as approved in the Stormwater Management Plan):
55.45 aC
Primary estimated area to be disturbed (include portions with
Erosion and Sediment Control Plan approval only):
3.05 aC
Off -site estimated area to be disturbed (if applicable):
D.
Property Owner Status:
FEDERAL ❑ STATE ❑ PUBLIC ❑ PRIVATE 42
E.
Nature of the Construction Activity Description (i.e. commercial,
industrial, residential, agricultural, environmental, utility):
1 Residential / Agricultural
F.
Municipal Separate Storm Sewer System (MS4) name(s) (if the
site is discharging to a MS4):
G.
Estimated Project Dates (MM/DD/YYYY).
Start Date:
02/01/2022
Completion Date:
02/01/2023
H.
Is this construction activity part of a larger common plan of
development or sale?
YES ❑ NO 2
Rev 11/2020 PAGE 1 1 6
CONSTRUCTION GENERAL PERMIT (VAR10) REGISTRATION STATEMENT 2019
1. 6"Order Hydrologic Unit Code (HUC) and Receiving Water Name(s). Include additional areas on a separate page.
HUC
I NAME(S) OF RECEIVING WATERBODY
020802040101
Stockton Creek - Mechums River
Section Ill. Off -site Support Activity Location Information.
List all off -site support activities and excavated material disposal areas being utilized for this project. Include additional
areas on a separate page.
Off -site Activity Name:
Address:
City or County:
Off -site Activity Entrance Location (description, street
address and/or latitude/longitude in decimal degrees):
Latitude and Longitude (6-digit, decimal degrees format):
Is this off -site activity an excavated material disposal
area?
YES ❑ NO ❑
If this off -site activity is an excavated material disposal
area, list the contents of the excavated fill material:
Will a separate VPDES permit cover this off -site activity?
YES ❑ NO ❑
Section IV. Other Information.
A.
A stormwater pollution prevention plan (SWPPP) must be prepared in accordance with the requirements of the
General VPDES Permit for Discharges of Stormwater from Construction Activities Prior to submitting the
Registration Statement. By signing the Registration Statement, the operator is certifying that the SWPPP has been
prepared.
B.
Has an Erosion and Sediment Control Plan been
submitted to the VESC Authority for review?
YES 2 NO ❑
Erosion and Sediment Control Plan Approval Date (for
the estimated area to be disturbed MM/DD/YYYY):
C.
Has land -disturbance commenced?
YES ❑ NO 0
D.
Annual Standards and Specifications. if this project is utilizing approved Annual Standards and Specifications
(AS&S), attached the completed AS&S Entity Form.
AS&S Entity Name (if different from the Operator
identified in Section I):
E.
Billing information (leave blank if same as the Operator identified in Section I. above). This entity will receive
Annual Permit Maintenance and Permit Modification Fee invoices (if applicable).
Billing Name:
Contact Name:
Address:
City, State and Zip Code:
Phone Number:
Primary and CC Email:
Rev 11/2020 PAGE 2 16
CONSTRUCTION GENERAL PERMIT (VAR10) REGISTRATION STATEMENT 2019
Section V. Certification. A person representing the operator as identified in Section I. A. and meeting the requirements
of 9VAC25-880-70. Part III. K must physically sign this certification. A typed signature is not acceptable. Please note that
operator is defined in 9VAC25-870-10 as follows:
"Operator" means the owner or operator of any facility or activity subject to the Act and this chapter. In the context of stormwater
associated with a large or small construction activity, operator means any person associated with a construction project that meets
either of the following two criteria: (i) the person has direct operational control over construction plans and specifications, including
the ability to make modifications to those plans and specifications or (li) the person has day-to-day operational control of those
activities at a project that are necessary to ensure compliance with a stormwater pollution prevention plan for the site or other state
permit or VSMP authority permit conditions (i.e., they are authorized to direct workers at a site to carry out activities required by the
stormwater pollution prevention plan or comply with other permit conditions). In the context of stormwater discharges from
Municipal Separate Storm Sewer Systems (MS4s), operator means the operator of the regulated MS4 system.
9VAC25-880-70. Part III. K. Signatory Requirements. Registration Statement. All Registration Statements shall be signed as follows:
a. For a corporation: by a responsible corporate officer. For the purpose of this chapter, a responsible corporate officer
means: (i) a president secretary, treasurer, or vice-president of the corporation in charge of a principal business function, or
any other person who performs similar policy -making or decision -making functions for the corporation; or (h) the manager
of one or more manufacturing, production, or operating facilities, provided the manager is authorized to make management
decisions that govern the operation of the regulated facility including having the explicit or implicit duty of making major
capital investment recommendations, and initiating and directing other comprehensive measures to assure long-term
compliance with environmental laws and regulations; the manager can ensure that the necessary systems are established or
actions taken to gather complete and accurate information for state permit application requirements; and where authority
to sign documents has been assigned or delegated to the manager in accordance with corporate procedures;
b. For a partnership or sole proprietorship: by a general partner or the proprietor, respectively, or
c. For a municipality, state, federal, or other public agency. by either a principal executive officer or ranking elected official.
For purposes of this chapter, a principal executive officer of a public agency includes: (i) the chief executive officer of the
agency or (n) a senior executive officer having responsibility for the overall operations of a principal geographic unit of the
agency.
Certification: "I certify under penalty of law that I have read and understand this Registration Statement and that this
document and all attachments were prepared in accordance with a system designed to assure that qualified personnel
properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage
the system or those persons directly responsible for gathering the information, the information submitted is to the best
of my knowledge and belief true, accurate, and complete. I am aware that there are significant penalties for submitting
false information including the possibility of fine and imprisonment for knowing violations."
Printed Name:
Signature (signed in ink):
Date Signed:
Section VI. Submittal Instructions. Submit this form to the VSMP Authority. If the locality is the VSMP Authority, please
send your Registration Statement submittal directly to the locality; do NOT send this form to DEQ. A list of local VSMP
Authorities is available here: VSMP Authorities.
If DEQ is the VSMP Authority, please send to: If the locality is the VSMP Authority, please send to:
Department of Environmental Quality
Office of Stormwater Management Suite 1400
PO Box 1105
Richmond VA 23218
corlstrUctio11Rp@deg.yirginia.l:OV
Rev 11/2020 PAGE 3 16
Section 2. Notice of general permit coverage
(This notice is to be posted near the main entrance according to 9VAC25-880-70, Part II, section
C.) (DEQ coverage letter to be provided when obtained)
Section 3. Nature of activity
Project Description:
This project consists of the construction of a single family residence and associated access. The existing site is
55.45 acres of vacant wooded land bordered to the north by Stockton Mill Creek and to the south by Batesville
Road.
Erosion and Sediment Control Sequencing:
1. CONTRACTOR SHALL CONDUCT A PRE -CONSTRUCTION MEETING WITH THE PLAN APPROVING AUTHORITY
PRIOR TO ANY LAND DISTURBANCE OR E&S CONTROL INSTALLATIONS.
2. INSTALL CONSTRUCTION ENTRANCE, SEDIMENT TRAP, AND PERIMETER CONTROLS PRIOR TO ANY
DISTURBANCE.
3. ONCE INITIAL MEASURES ARE IN PLACE, REQUEST AN INSPECTION OF THE INITIAL EROSION AND SEDIMENT
CONTROL MEASURES FROM THE COUNTY OF ALBERMARLE E&S INSPECTOR. CALL 24-HOURS IN ADVANCE
OF INSPECTION.
4. PROTECT PERMANENT VEGETATION FOR THE DURATION OF THE PROJECT.
5. COMMENCE DEMOLITION NECESSARY TO PERFORM PROPOSED WORK ONLY (INCLUDING EXCAVATION
WORK).
6. CONTRACTOR TO LEAVE EXISTING STABILIZED AREAS IN A NON -EROSIVE CONDITION UNTIL NECESSARY
TO INSTALL PROPOSED IMPROVEMENTS. DISTURBED AREAS NOT IMPROVED SHALL BE SEEDED WITHIN 14
DAYS OF DISTURBANCE.
7. CONSTRUCT STORM STRUCTURES, IF APPLICABLE, STARTING AT THE DOWNSTREAM TERMINUS OR TIE-IN.
BACKFILL ALL EXCAVATIONS AND TRENCH AREAS.
8. COMMENCE CONSTRUCTION OF PROPOSED PAVING AND SITE ELEMENTS, WITH THE EXCEPTION OF ANY
PROPOSED BMES.
9. FOR GRASSY AREAS: INSTALL PERMANENT SEEDING AND MULCH. STABILIZE ALL DISTURBED AREAS.
10. FOR GRAVEL AREAS: RESTORE GRAVEL AFTER TRENCHING AND EXCAVATION OPERATIONS ARE
COMPLETE.
13. REPAIR ANY EROSION AND REMOVE ANY SEDIMENT.
15. DRESS AND OVER -SEED ALL DISTURBED AREAS AS NECESSARY TO AFFECT PERMANENT VEGETATIVE
COVER. STABILIZE ALL REMAINING DISTURBED AREAS WITH TOPSOIL, SEED, AND MULCH ONCE WORK IS
COMPLETE.
16. REMOVE SEDIMENT TRAP AND ASSOCIATED DIVERSION DIKES ONCE PERMANENT VEGETATIVE COVER HAS
BEEN ESTABLISHED ON SITE.
17. BEGIN INSTALLATION OF ANY PROPOSED BUTS ONCE ALL CONTRIBUTING AREAS ARE STABILIZED AND
FREE OF DEBRIS. REFER TO INSTALLATION CHECKLIST AND INSPECTION MILESTONES FOR CONSTRUCTION
MILESTONES. INSTALL PERMANENT CONVEYANCE CHANNELS TO BUTS AT THIS TIME, STABILIZING
IMMEDIATELY WITH EC-2 TYPE 1 MATTING.
18. AFTER FINAL SITE STABILIZATION AND APPROVAL FROM THE APPROPRIATE EROSION AND SEDIMENT
CONTROL AUTHORITY, THE SILT FENCE, INLET PROTECTION AND OTHER STABILIZATION MEASURES SHALL
BE REMOVED.
Section 4. Erosion and Sediment Control Plan.
EROSION & SEDIMENT CONTROL NARRATIVE: EROSION AND SEDIMENT CONTROL MEASURES: MAINTENANCE:
PROJECT DESCRIPTION:
THIS PROJECT CONSISTS OF THE CONSTRUCTION OF A SINGLE FAMILY RESIDENCE AND ASSOCIATED ACCESS. THE DISTURBANCE AREA ASSOCIATED WITH
THIS PROJECTIS S3.O5AC(J32,960 SF). IT IS ANTIOPAMDTWITTHE WORK WILLUAK IN FEBRUMYMD VEST J2 MONTHS.
MONA SITE CONDITIONS:
THE SITE CONSISTS OF VACANT WOODED LAND BORDERED TO THE BEAN BY STCCKION MILL CREB(. THE SLOPES WITHIN THE PROJECT AREA RANGE
FROM3TO3OPEWENQO
ADJACEMAREAS:
THE PROPOSED PROJECT IS BORDERED BY SINGLE FAMILY RESIDENCES ON ALL SIDES, BY STCCKTON MILL CREEK TO THE NORTH, AND BY BATESVILLE
COADTOTHESOUTH.
OFTSITEAREAS:
T IS NOT ANTICIPATED TWIT ANY OFFSITE AREAS WILL BE DISTURBED DURING CONSTRUCTION. UNSUITABLE MATERIALS RESULTING FROM THE
PROPOSED W(RKSHALL BE HW LED FROM THESITEAND DISPOSED OFATAN APPROVED DISPOSALSITE PERMITTED SEPARATELY FROM THIS PROJECT.
SOILS:
SEETHE UWASOUS DELINEATION MAPSHEETCIG.
CTURCALAREAS:
TXISSITE W15NOCRITICALAREASINTIREIMMEDATEVICINMOFTIREMOPOSEDMWTRUMON.HOWEVER,PROWRERMIONMWROLMEASURESAS
SHOWN ON THE PLANS SHAD BM PUT IN PtACEiO AMMENTSILT FROM LEAVING THE PROJECTAMAAND MARAS TXESTREAM BUFFER DOWNHILL
EROSION& SEDIMENT CONTROL MEASURES:
REFER TO THIS SHEET MR LIST OFALL PROPOSED EROSION AND SEDIMENT CONTROL MEASURES TO BE USED ON SIZE.
RflMMNEMSTABILIZATION:
THE AM WILL BE STABWZED THROUGH THE USE OF PERMANENT SEEMS, STONE AND GREW, LANDSCAPING, AND PAVEMENT. SEEDING INFORMATION,
CATS AND AMENDMENTS ME INCLUDED ON THE PLANS. SOIL MOND SHALL BE COMPLETED THE CONTRACTOR TO DETERMINE THE SUITABILITY OF
FASTING SOIS AND THE NEED FOR MY SOIL AMENDMENTS TO ENSURE THAT PERMANENT SEEMS WILL GROW EFFECTIVELY.
STORM WATER RUNOFF CONSIDERATIONS:
STORMWATER RUNOFF DURING CONSTRUMON WILL BE DIRECTED THROUGH APPROPRIATE EROSION AND SEJIMEM CONIROS TO CLEAN WATER
BEFORE DISCHARGING TO AN ADEQUATE 01 PROTECTED FROM EROSION AND SEDIMENT AS SHOWN ON THE PLANS.
MAINTENANCE:
ALL E&$ MEASURES SHALL BE INSPECTED REGULARLY AS REQUIRED BY STATE STANDARDS AND MAINTAINED IN GOOD WORKING ORDER. REQUIRED
REPAIRS SHALL BE IMAGE IMMEDIATELY. SEE THE MAINTENANCE NARRATNE ON THIS SHEET FOR SPECIFIC MNNTSANCE ITEMS AND INSPECTION TIMES.
GENERAL EROSION AND SEDIMENT CONTROL NOTES:
ESL DRUM OTHERWISE INDICATED, ALL VEGETATIVE MD STRUCTURAL EROSION MD SEDIMENT CONTROL MMORCES WILL BE CONSTRUCTED MD
M UNTAJNED ACCORDING TO MINIMUM STANDARDS AND SPECIFICATIONS OF THE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK MD
VIRGINIA REGUATONS MR 625M OEROSION AND SEDIMENT CONTROL REGULATIONS(4VAC5630).
ES2: THE PLVMPPROWNG AUTHORITY MUST BE NOTIFIED ONE WEEK PRIOR TO THE PRECONSIRUCOON CONFERENCE, ONE WES PRIOR TO THE
COMMENCEMENT OF LAND DISTURBING ACTUDY, AND ONE WFEH PRIOR TO THE FINAL INSPECTION. THE NAME OF THE RESPONSIBLE LAND
DISTURBER MUST BE PROVIDED TO THE PLANAPSONNG AUTHORITY PRIOR TO ACTUAL ENGAGEMENT IN THE LWDOISTURSING ACTWN SHOWN
ON THE APPROVED PLAN. IF THE GAME IS NOT PROVIDED PRIOR TO ENGAGING IN THE LW6gSTURBNG ACTMTY, THE P AN'S APPROVAL WILL BE
REMOMM
ES3: ALL EROSION AND SEDIMENT CONTROL MEASURES ME TO BE PLACED PRIOR TO OR AS SOON AS THE FIRST STEP IN CLEARING.
ESA ACOPY OF THE APPROVED EROSION AND SEDIMENT CONTROL AAN SHALL BE MUNTAJNED ON THE $IZE AT ALL TIMES.
E55: PRIOR TO COMMENCING LAND DISTURBING ACTMTS IN MEA50THER TWOS INDICATED ON THESE PLANS UNCWDING, BUT NOT MOM TO OFF
$IZE BORROW OR WASTED AREAS), THE CONTRACTOR SHALL SUBMIT A SUPREMENTMY EROSION CONTROL PION TO THE OWNER MR REMM
ANDAFPROVAL BYTHEPLW MFAOVING AUDgRITY.
ES THE CONTRACTOR IS RESPONSISE FOR INSTALLATION OF ANY ADDITIONAL EROSION CONTROL MEASURES NECESSARY TO PREVENT EROSION AND
SEDIMENTATION M DETERMINED BY THE PION APPROWNG AOTHORIM
EST: ALL DISTURBED MANY ME TO DRAIN TO APPROVED SEDIMENT CONTROL MEASURES AT ALL TMES DURING LAND )STURBING ACTIVITIES AND
DURING SITE DEVELOPMENT UNTIL FINAL STMNZATON A ACHIEVED. AFTER MICH, UPON APPROVAL OF THE PLVMPPROWNG MTRCFM, TXE
CONTROLS SHALL BE RESIGNED. MAPPED SEDIMENT AND THE DISTURBED SOIL AREAS RESULTING FROM THE REMOVAL OF TEMPORARY
MEASURES SHALL BE PERMANENTLY STARIUZM TO PREVENT FURTHER EROSION AND SEDIMENTATION.
ES@ WRING DEWATERING OPERATIONS, WATER WILL BE PUMPED INTO AN APPROVED FILTERING DEVICE.
ES4 THE CONTRACTOR SHALL INSPECT ALL EROSION CONTROL MEASURES AT LEAST EVERY 2 WEEKS AND IMMEDL47LY ARTS EACH
RUNOFFGRODUENG BUNFALL EVENT. MY NECESSARY REPAIRS OR CLEANUP TO MAINTAIN THE EFFECTVENE$$ OF THE EROSION CONTROL
MOCESSHALLSE NUM IMMEDIAMLY.
ESSD. THE CONTACTOR IS RESPONSIBLE FOR THE DAILY REMOVAL OF SEDIMENT TWAT HAS BEEN TRANSPORTED ONTO A PAVED OR PUBLIC ROAD
SURFACE.
ES11 SEEDING OPERATIONS SHALL BE INITIATED WITHIN T DAYS AFTER REACHING FINAL GRADE OR UPON SUSPENSION OF GRADING OPERATIONS MR
AN ANTICIPATED DURATION OF GREATER THAN 14 DAYS OR UPON COMPLETION OF GRAMS OPERATIONS MR A SPECIFIC AEA
ES12: THE CONTRACTOR SHALL BE RESPONSIBLE FOR PREVENTING SURFACE AND AIR MOVEMENT OF DUST FROM EXPOSED SOILS WHICH MAY PRESENT
HEALTH HAZARDS, TRAFFIC SAFETY PROBLEMS, OR HARM ANIMAL OR PLANT LIFE
ES13: A MEW IS REQUIRED FOR PROJECTS DISTURBING 2,500 SQUARE FEET OR GREATER IN A DESIGGASD CHESMEN(E PAY PRESERVATION AREA
(CBPA) OR ONE MORE OR GREATER OUTSIDE THE OEM FOR MORE INFORMATION ABU THE VIRGINIA STORMWATER MANAGEMENT PROGRAM
PERMITTING WES PAGE AT: DtlIrJ/wwxq�.virginiagov/PPgramyWaler/$IomrvalerManagemenLaslDs
UNLESS OTHERWISE INDICATED, ALL EROSION AND SEDIMENT CONTROL MACROS SHALL BE CONSTRUCTED AND FW WAINED IN ACCORDANCE WITH THE
MINIMUM STANDARDS AND SPECIFICATIONS OF THE RATEST EDITION OF THE NRGINW EROSION AND SEDIMENT CONTROL REGULATIONS AND VESC
HANDBOOK OR COUNTY OF ALBERMARLE STANDARDS, WHICHEVER ARE MORE STRINGENT.
A STAB UZED STONE PAD WITH A FILTER FABRIC UNDERLINES LOCATED AT POINTS OFVEHICNAR INGRESS AND EGRESS ON ACONSTRUCDON SITE
SILT FENCE-3.05
A TEMPORARY SEDIMENT BARRIER CONSISTING OF A SYNTHETIC FILTER FABRIC STRETCHED ACROSS AND ATTACHED TO SUPMRTNG POST$ AND
ENTRENCHED.
ASEDIMENTFILTER LOCATEDATTHE INIETTO STORM SEWER CULVERTS.
A TEMPORARY RIDGE OF COMPACTED SOIL CONSTRUCTED ATTHE TOP OR BASE OFASLOMG DISTURBEDAREA
ATEMPORARY PONDINGAREA FORMED BY CONSTRUCTING AN GAWKISH EMBANHMEM WITH ASTONE OIRLET.
OUTLET PIRTOWDON -3.18
A PFRMANEM OUREf PROTECTION MEASURE THAT CONSIST$ OF STRUCTURALLY LINED APRONS OR OTHER ACCEPTABLE ENERGY DISSIPATING DENCM
PLACED AT THE OUTLETS OF ALL PIPS OR PAYED CHANNEL SECTIONS.
TEMPORARY SEEDI NG - 3.31
THE STABLISHMEM OFATEMPORARY VEGETATIVE COVER ON DISTURBED AREAS THAT WILL NOT BE BROUGHT TO FINAL GRADE FOR PERIODS OF SO DAYS
TOONE WAR BY SEEDING WITH APPROPRIATE RPNDLYGROWING ANNUAL PLANTS.
PERMNIENTSSDING-3M
THE SLABLISHMENT OF PERENNIAL VEGMATVE COVER BY PANTING SEED ON MUGHGRADED AREAS THAT WILL NOT BE BROUGHTTO FINAL GRADE FOR A
YEAR OR MORE OR WHERE PSMMNEW VEGETATIVE COVER IS NEEDED ON ANEGRADED AREAS IN ACCORDANCE WITH EROSION AND SEDIMENT CONTROL
TECHNICAL BULLETIN NO.4: NUTRIENT MANAGEMENT FOR DEVELOPMENT SITS.
MULCHING-3.35
APPLICATION OF PANT RESIDUES OR OTHER SUITABLE MATERIALS TO DISTURBED SURFACES TO PREVENT EROSION AND REDUCE OVERLAND FLOW
VELOETIS. FOSTERS PLANT GROWTH BY INCREASING AVAILABLE MOISTURE AND PROVIDING INSULATION AGAINST EXTREME HEAT OR COLD. SHOULD BE
APPLIED TO ALL SEEMS OPERATION, OTHER PUNT MATERIALS WHICH CO NOT PRONDE ADEQUATE SOIL PROMOTION BY THEMSELVES, AND RARE AREA$
WHICH CANNOT BE SODDED DUE TO THE SEASON BUT WHICH STILL NEED PROTECTION TO PREVENT SOIL LOSS.
THE INSTALLATION OF A PROTECTIVE COVERING(BLANKET)OR A BOIL STABNZAT)N MAT ONAPREPARED PLANTING AREA OF A SSb SLOPE CMNNE OR
SHORELINE
E&S LEGEND
® SAFETY FENCE
SF SILT FENCE
®TME PROT IION
�® LIMITS OF DISTURBANCE
® DIVERSION DIKE
ILA INLET PROTECTION
® OP OOTLETPRO STRON
COVERT INLET PROTECTION
CD CHECK CAN
CE CONSTRUCTION ENTRANCE
TH S TEMPORARY/PERMANENTSFEDING
AND MULCHING
REMOVE TREE
SAWCUT
DEMOLISH PAVEMENT
FROWCO STEEPSLOFES
FROM COUNIYGIS
WATER PROMOTION ORDINANCE
BUFMR/SWYFAH EOODPWN
IN GENERAL, ALL EROSION AND SEDIMENTATION CONTROL MEASURES SHALL BE CHECKED GAILY AND AFTER EACH RAINFALL EVENT GREATER THAN O25
INCHES. MEASURES SHOULD BE CLEANED AND REPAIRED ACCORDING TO THE FOLLOWING SCHEDULEANDTHE VIRGINM EROSION AND SEDIMENT CONTROL
HANDBOOK. THE FOLLOWING WILL BE CHECKED IN PARTIW Wi:
1 THE CONSTRUCTION ENIBWCES AND CONSTRUCTION ROAD STABILIZATION PLEAS SHALL BE MAINTAINED IN A CONDITION WHICH WILL PREVENT
TRACKING OR FLOW OF MUD ONTO PUBLIC RIGHISOFWAY THROUGH PERIODIC TOP DRESSING WITH ADDITIONAL $TONE ANI WASHING AND
REWORKING OF AMONG STONE.
2. SEDIMENT DEPOSITS SHALL BE RESIGNED FROM SILT FENCE AMR EACH RAINFALL. UNDER NO CIRCUMSTANCES SHALL DEPOSITS BE ALLOWED TO
ACCUMUTATE ABOVE WllF THE HEIGHT OF THE FENCE. DAMAGED OR UNDERCUT SILT FENCE SWll1 BE REPAIRED IMMEDIATELY. SHOULD SILT FENCE
BECOME INEFFECTIVE OR REACH THE END OF THE EXPECTED USEPBIF LIFE FABRIC SHALL BE REPLACED IMMEDIATELY. UPON SILT FENCE FEW_
DRESS PONY SEDIMENT DEPOSITS TO CONFORM WITH MATINS GRADE AND SEED.
3. INLET PROTECTION SHALL BE CHECKED REGULARLY FOR SEDIMENT. IF EXCESSIVE SEDIMENT IS PRESENT, OR IF EXCESSIVE PONDING OCCURS AFTER
RAINFALL, THE $TONE SHALL BE PULLED AWAY AND CLEANED OR REPLACED.
4. STONE USED IN CULVERT INLET PROTECTION SHALL BE INSPECTED REGULARLY MR CLOGGING AND REPLACED AS NEEDED TO MAINTAIN FULL
FUNCDONALITY. UNDER NO CIRCUMSTANCES SHALL SEDIMENT BE ALLOWED TO ACOUMUTATE ABOVE ONEHAIF OF THE HFIGHT OF THE INLET
PROTECTION. ACCUMULATED SEDIMENT SHALL BE REMOVED AND UPSTREAM AREAS PERMW EARLY STABILIZED BEFORE THIS CONTROL A REMOVED.
5. CHECK DAMS SHALL BE INSPECTED REGULARLY TO ENSURE THE CENTER OF THE DAM IS LOWER TWOS THE EDGES. SEDIMENT SHALL BE REMOVED
WHEN IT REACHES ONE HALF THE HFIGHT OF THE DAM.
6. MY WIL WITHIN TREE PROTECDON AREAS THAT IS INADVERTENTLY COMPACTED SHNL BE AERATED WITH AN IRON BAR EVERY M INCHES TO A DEPTH
OF 1 INCHES. PHYSICAL DAMAGE TO TREES SHALL BE REPAIRED AS OUTLINED IN THE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK SECTION
3.3E TRES THAT ME STRESSED OR DAMAGED SHALL RECEIVE AN APMJPRATE APPLICATION OF FERTILIZER TO AID RETCMERY.
T. ALL SEEDED AREAS WILL BE CHECKED REGULARLY TO SEE THAT A GOOD STAND IS MAINTAINED. AREAS SHOULD BE FERTILIZED AND RESEEDED AS
NEEDED.
S. ALL TEMPORARY EROSION AND SEDIMENT MEASURES SHALL BE MPSED OF WITHIN THIRTY (30)DAYS AFTER FINAL SITE STABILIZATION A ACHIEVED
AGO VEGETATION IS STABLSHED. FINAL SIZE STABIUZATION SHALL BE APPROVED BY THE OWNER AFTER THE INSPECTOR HAS DETERMINED TRAT THE
SITE IS STABILIZED.
MANAGEMENT STRATEGIES:
THE FOLLOWING SEQUENCE OF EVENTS AND EROSION CONTROL MEASURES SHALL BE INCORPORATED INTO THE CONSTRUMON SCHEDULE MR THIS
PROJECT AND SHALL APPLY TO ALL CONSTRUCTION ACOVTIS WITHIN PROJECT OMITS.
1 CONSTRUCTION WILL BE SEQUENCE) SO TRATTRENCHING AND EXCAVATION OPERATIONS CAN BEGIN AND END AS QUICKLY AS POSIBIF.
2. SOIL STOCKPILES WILL EE PROTECTED WITH APPROPRIATE EROSION CONTROL MEASURES. STOCKPILES REMAINING FOR MORE TWOS 14 DAYS SHALL
BETEMPORAMLYSEEDED.
3. THE CONTRACTOR SHALL ME APPROPRIATE CONSTRUCTION METHODS TO MINIMIZE DISTURBANCE ALONG MANAGED SLOPS AND EUSRNG STAFF
SLOPS WHERE EROSION HAZARD A HIGH.
C ALL STORM SEWS INUM THAT ARE MACE OPERABLE DURING CONSTRUCTION SHALL BE PROTECED WITH INLET PROTECTION SO THAT
SENMENTU MWASRMNOT MM ECOMV MCESVSTEM.
5. PREVIOUSLY GRASSED AREASSMLL BESEEDED AMID STRAW MULCHED IMMENATELYARTER TRENCHING OPERATION.
6. ALLTHEEROSION AND SENMENTCONTROL MEASURSSHALLBE INSPECTED46 HOURSMTER EVERY RAIN SENT GREAIEfl THAN 0.251NCHESAND
EVERY 5 DAYS EVEN IFA RAIN EVBW DOS NOTOCW R. REQUIRED REPAIRS $HALL BE MADEAS NEEDEDTO MANTAIN DSIGNEDSTANDARD.
T. PERMANENT VMETATIONSHALLNOT BE CONSIDERED ESTABLISHED UNTIL A GROUND COVERED A ACHIEVED THAT IS UNIFORM, MATURE ENOUGH TO
SURVNE AND WILL INHIBIT EROSION.
R. THE CONTRACTORS SHALL BE RSPONSIBIE FOR ALL THE INSTALLATION AND MAINTENANCE OF ALL EROSION AND SEDIMENT CONTROL PRACTICES.
MINIMUM STANDARD COMPLIANCE:
MSl HAVE TEMPORARY AND PSMANEM$LPBILIZATION BEEN ADDRESSED IN THE NARRATIVE? RAVE THE PROPOSED PRACTICES MEN SHOWN ON
THE PLAN? YES
SEEDSPMIRCATON YES MULCHING YES GRAVEL YES
MS2 WAS STABILIZATION OF SOIL STOCKPILES BEEN ADDRESSED IN THE NARRATIVE? YES.
IS SEDIMENTTRAPANG MEASURESPROV DEW? YES.
MS3 W15MAINTENANCEOFPMR ENTSTABIUZATIONBMNADDRESSEDMREXPOSEDMM?YES.
VISA PRESMIMEMIRAPPINGFAEUTISTOBECONSTRUCTEDASARRSISSPINMA?YES
MS5 HASSTAMRIZATION OF EARTHEN STRUCTURES BEEN ADDRESSED? YES.
MSG MESEDIMEW WINS REQUIRED WHERE NEEDED? NO. N/A
MST HASSTAMRIZATION OF COTAND ALL SIDFES BEEN ADEQUATELY ADDRESSED? YES.
MSS PRE PAVED FLUMES, CHANNELS OR SLOPED BRAINS REQUIRED WHERE NECESSARY? NO. WA.
MS9 HASSTAMRIZATION THROUGH SURFACE ROUGHENING OR OIRIFT PROTECTION BEEN ADMEMED?NO. NA
MGM IS ADEQUATE INLET PROTECTION REQUIRED ON ALL OPERATIONAL STORM $ EWER INLET"] YES.
vl 11 HAS MMINENANCE OF PERMANENT STABILIZATION BEEN ADDRESSED FOR CONVEYANCE AND REC MNG CHANNELS?YES.
MS12 MEINSTREAM CONSTRUCTION MEASURES REQUIRED$0 THAT CHANNEL DAMAGE IS MINIMIZED?NO. N/A
MS13 ME TEMPOBWY STREAM CROSSINGS OF NON£RODIBIE MATERIAL REQUIRED WHERE APPLICABLE? NO. N/A
MS14 THIS REGUTATION REQUIRES THAT ALL MPIIGBLE FIEDERAL,STATE AND LOCAL REGUATONS PERTAINING TO WORKING IN OR COMING LIVE
WATERCOURSES BE FOLLOWED. NO. WA
MS35 HAS RSTMILIZATION OF MANY SURIECT TO INSTREAM CONSTRUCTION BEEN ADEQUATELY ADDRESSED?NO. N/A
MS36 IS STABILIZATION OF UOUTY TRENCHES AWRSSED? YES.
MSlT ISTHEMARSPORT OFSOILAND MUD ONTO PUBLIC ROADWAYS PROPERLY CONTROLLED? U.E CONSTRUCTION ENIMNCS, WASH RACKS,
DAILY CIFPNING OF ROADWAYS, TRANSPORT OF SEDIMENT TO AMMAR FAELD D YES.
MSM HAS THE REMOVAL OF TEMPORARY PRACTICES BEEN AWRSSED?YS.
HAS MAINTENANCE OF PRACTICES BEEN ADDRESSED? (I.E. REPAIR OF MUMRS AND REMOVAL OFACWMUTATED SEDIMENT) YES.
MS19 ME PROPERTIES AND WATERWAYS DOWNSTREAM FROM DEVFIAPI.IENT ADEQUATELY PROTECTED FROM EROSION AND SEDIMENT DEPOSITOR!
DUE TO INCREASES IN PEAK STORM WATER RUNOFF? YES.
EROSION AND SEDIMENT CONTROL SEQUENCING:
L. CONTRACTOR SHALL DUN DUCT APREJAN$TRUCBON MEETING WITH THE PLAN AFFIRMING AUTHORITY PRIOR TO ANY LAND DISTURBANCE OR ME CONTROL
INSTALIAPONS.
2. INSTALLCONSTRUMONEN WARM,SMIMENTTAP,MDPERIMETERCONTROL$ PRIORTOANY.BUTRBWCE.
3. ONCE INIPAL MFASURMME IN PACE, RMUMM INSPECTION OFTRE INIBALEROSIONMOSEDIMEM D3MROL MEASURE$ EROMTHE WUNIYOF
PLPERMMLE EPOS INSPECTOR. CALL 24NOUR$ IN AOVMCEOF INSPECTION.
A MOTELTP4RMM DOGE ONMRMEDURAPONOFTHEMWECF.
5. WMMMCEDEMOURONNECESSARYTOP MRMMOMSEDWORKONL (INCWDINGEXfAVARONWORK).
6. WNTRN.iORnJLEAVEMX NG$T lUL MF INANONEMASNECONDIPONUNRLNECES YTOIN$T4 MOPASEDIMMMEMEMS.DISURBM
META$NOFIMPROVEDSHPIIMSEEDEDWITHIN14DAYSOFDL R&WCE.
T. WNSMUMMORMSTRUMR6,IFAWLICMLE,SFARRNGATTXEWWNSIBFAMTERMINU$ORn.N.MCNPLLALLIXGVAnOMSMDTRENCHMFAS.
G COMMENCE CONSTRUCTION OF PROPOSED PAVING AND SIZE ELEMENTS, WITH THE EXCEPTION MANY MARGINS AMPS.
9. FOR GRASSYMEAS: INSTALL PERMANENT SEEDING AND MULCH. STMIDZEALL DISTURBED AREAS
LO. FOR GRAVELMFAS: FALLOFF GRAVEL AFTER TRENCHING AND EXGVAPON OPERATORS ARE COMPLETE.
L3. FEARS ANY EROSION AND REMOVE ANY$EDIMENT.
L5. DRESS AND OVERSEED ALL DISTURBED MFAS M NECESSARY TO AFFECT PERMW ENT VEGETATIVE COVER. STAN LUE ALL REM NI NO DISTURBED MFAS
WITH TOMAH, $RED, AND MULCH ONCE WORK IS COMPERE.
16. REMOVE SAN MEW MAP AND ASSOCIATED DIVERSION DINED ONCE PERMANENT VEGETATIVE COVER HAS BEEN ESTATLUTED ON SITE.
L]. BEGIN LATBA INSTAION OF ANY PROPOSED PS ONCE ALL WNTRIBUUNG AREAS ME STABILIZED AND MEE OF DEBRIS. REFER TO I N$TA11AnoN CH ECNH$T
AND INSPECTION MILESTONS FOR CONSTRUCTION MILESTONES. INSTALL REMAIN ENT CONVEYANCE CHARNETS TO BM PS AT TO IS TIME, STMILIZING
IMMEDIATELY CORM EG2 TYPE I MATTING.
M AFTER RNA- SITE STAN UUMION AND APPROVAL FROM THE APPROMCOTE EROSION AND SMIM ENT CONTROL AUTHORITY, THE SILT FENCE, IN LET PROTECTION
AND OTHER STMIUUTON MEASURES SHALL BE HEMMED.
W
Z
J
Lu
U
z
Lu
0
LA. )
cr
cr
z
J
O
cr
F—
z
O
U
F—
z
L1J
Lu
W
U)
n
z
Q
z
O
U)
O
Lu
G
APPROVED DCH
SUBMISSION NO. 1
T H E W 0 R H O F
L I N E + G R A D E
C! I.0
I
W
Z
J
SILT FENCE
I OWUIUOEMFA 0.6]AC _ _ _ _ �'
LOD 1329C4 SF
U a O
LLJ
o Z
LLJ
1 I I \ \ — — ` LLL �eeee3sss>� \ 2313$'BOTFOM®]28.0 I \ \ �\ / J
\ >� >� TOPWEESroFAOE]30.16 — \ 1 �' a
SF IF TOPOWIMRAGEM63' \ —�
T. M. 85-ID TRACT Z I \ —, _ �� I w w o
\ — \ \ \ \ smIMFNFTRM N ; m W
TOPEM&WNMENi ]32.63' / W
55.45 ACRES �7V/ I \ ` \ 9MIN.: DRNN4GEMEAIAO AC , / Q Q (n
CYRENN W. SPgRlfMAN I \ \ / _ — \ SF LF \ \ - ,z o I I \ \ \ \
D.B. 5439-/79 D.B. 5433-/35 8 /36 PLAT
ZONED RA
USE RES/DENTIAL p
�/ o LLJ
RAm �WOETTTga„�T UR A4�
Us , B S'r 1111C APPROVED
)CH
SUBMISSIONN0.
PROJECT 230]00]
THE WORK OF
\ \ \ \ \ \ \ \ \ \`— // // / //\ I / / /�// I /l l /l l l / / // / / / /' \\ ` ✓� I l / LINE + GRADE
z, ;1 EROSION AND SEDIMENT CONTROL PLAN PH 1 C2.1
1•-30:0 SO SO
///
i
SLK✓FI'E-0TOPOG.ZIPHY
_ e /
�LASTA PREAD T°RE IIU D
GsrAmFn snE is srnaalsD / / /
-SLOW M,INIEk,MCE °flJI1NDCDVER
ON SLOPES S:S OR SIEFPEN-SEE ✓ / /
(/
I
_ ARCHIlEC1UMLP1ANsmRSEED MU
/
\ \ \ \ I ``\ I I I / s ' 3�'�y / / / /� x%%%ii%i✓i i ♦ LOD 1321p SF \ is
W
Z
J
\ I\ I\ \ 11 \ \\ `\ a jm ! / � \ _ M �, � 1 / '�91;,����'�1�%Ji„t1'%f��;,Y• .♦ / \ \ N
a
a
\\ \ \\ 36L\\ \\ \ \ \ \ `\\ \ \ �•-�"` �-sPn�F niR onarnna sREnwvm \ \ \ WAMNG u\ 1— / , \) \ / (W,) a O
LLJ Z > p
a� C)
�0 Z
Lu
LEVELSFRFMER TO RE INSLPIIF➢ I \ \ \ \ \ / O: Q
T.M. 85-ID TRACT Z I \ \ — ._ SF - �` \ (usrnFiER snE¢srnaurFn — \ . \ \ 1 \\ / Lu 2
% m LLJ
5545 ACRES \ I l
CYRENA W. SPARfMAN \ \\ \ — \ \ ORaMsoEAnG Q a (n
D.B. 5439-179 D. B. 5433-/35 8 L36 PLAT \\ \ \ \s 1� \,` Q
ZONED RA ' — \ _ \ '`�.. z
USE RES/DENTIAL I / / / — — \ \ \ \ 1 \ I o (r \ `\ O
Lu
SF 62lF �C
4D1
\SF 37IF
R YMp O ArW BETTY FF/NEY I '9IOH 14 � ?6
J95 PN`
OSF rzesio: vnv[ APPROVED )CH
SUBMISSION NO. 1
PROJECT 2107007
T H E W 0 R H 0 F
\ \ \ \ \ \ \ \ \ \`_ // // / //\ I ( / /,// I // / /( ( ( / / // / / / /' \\ L ✓� I/ / LINE + GRADE
z, ;1 EROSION AND SEDIMENT CONTROL PLAN PH 2 C2.2
\'-W: o 30 60
STONE
CONSTRUCTION
�r
ENTRANCE
r61rR a. MR.
EF—
' �J
e
SIDE ELEVATION
On
x
,
~ .1VFIFNr
\'
1.
gMan, PLO ELDERS
EMPLE.
PLAN VIEW
SECTION B-B
Source: Adapted from 19R3 Maryland Starldarda for Soil Plate 3.02.1
Erasion end Sediment Cnntrnl, grad Va. DSWC
O 3.02-1 CONSTRUCTION ENTRANCE
DETUL I
SECTION A -A
ImRSNusaEE LNE NnNUTexa. rllnenN a r IS m11. le
OETAIL 2
SECTION A -A
- ME —CAL SECTION I1011 ON PLANS FOR SIM 1LOPPECOMEM IF" NO ITS
OEC-3 (OUTLET PROTECTION)
CONSTRUCTION OF A SILT FENCE
(WITHOUT WIRE SUPPORT)
I. GET THE S'OMIK ES. E. EXCAVATE A 4'% C TRENCH
➢PSXOPE AILING THE LINE OF
31AKK5.
aIM
III III .
5. STAPL. FILTER MATERIAL 4. RACATIM AN➢ COMPACT
TO STAKES AND EEISND THE EXCAVATED SOIL.
IT INTO THE TRENCH.
nag
r��
III
SHEET FLOW INSTALL4TION
(PERSPECTIVE GORE)
I I
I I
POINTS A SHOULD RE HIGHER THAN POINT S.
Source: Adapted from Installation of S raw agd Fabric Filter
Barriea for Sediment Control, Sherwood W Wyam Plate 3.05-2
O 3.05-2 SILT FENCE
TeLE E3zia
IREVISEDJUNE200,S)
TEMPoRPRVSEEDING SPECIFICATIONS
OUICH REFERENCE FOR PJL REGIONS
EFFMGnax
.PEaes
F 111
ANRAUFS
NNI
PREFEREENNE
FERTILIZER & LIME
TaEIE 3.32A
(REVISED TUNE SORG)
PFRALNFNTSFFMNG SCFtlFlfJTONS FOR PROMONT AREA
SEED
VNOIISE
SPERLES
AFNJGMINMT6 FENACNE
�q e�
1, o.
—1
LEE
FERTII
+ GREPER ,0�INEEPERP—PER&MIMEO Boa
ea
SEDIMENT TRAP VOLUME COMPUTATIONS
ST-1
I IXalnage Arne RLNG)l RaqulreE SmreOe Elevetlona
1
cowl
Incr.
Incr.
Cum,
143 193 CY
L
W
Area
Vol.
Vol.
Vol.
el Pape ]30.16
Elawtlan
IFQ
IFI)
ISFI
ICFI
ICY)
(LV)
RE py ]31.6i
]ID.OJ
39
ii
6)6
0
0
0
T4
W
cp]..
]30.W
K
31
1446
21W
86
85
WET CRY anNmkmenl
1-1
50 1
33
z-GIISPRODI
131
1 216
TEMPORARY DIVERSION DIKE
Compacted SPIT
r min. C
—FIw
4.a mCn.
SENUME' Va DSWC Plate 3.09-1
O 3.09-1 DIVERSION DIKE
SILT FENCE CULVERT INLET
PROTECTION
LIME stag PGa tar
OPTIONAL STONE COMBINATION**
Source: Adapted from VDOT Standard
Sheets and V. DSWC
O SEEDING SCHEDULE -PIEDMONT O 3.08-1 CULVERT INLET PROTECTION
Plate 3.Ml
TEMPORARY SEDIMENT TRAP
E to w/NNE
- v
O'w m/Nu
CROSS SECTION OF OUTLET
/-memNx1N.dRE5L DOG
IF FEET
~ � IFP. men
1 GRSE aOa . .MALL Il OO i 5] p i5
OUTLET (PERSPECTIVE VIEW)
Source: Va. DSWC Plate 3.13-2
O 3.13-2 SEDIMENT TRAP (STONE OUTLET)
TYPICAL TREATMENT — I
(SOIL STABILIZATION BLANKET)
INSTALLATION CRITERIA
s
NuroR um N",<a
.IF Sam DID inRnm I, Ater.
IPAR .. TNw 11
Emre��,sE
I 1 ,
tar
rr r s � PLAN V W~
STAPLING DIAGRAM
°r sr:NE � � Fan w mi aNw54iw°r.Gnµx m
rrdEr�rmlr �`� rwvr
T T
Source: VDOT Road and Bridge Standards
O 3.36-2 EC-2 INSTALLATION
W
Z
J
Lu
O
Z
Lu
0
Lu a
J �
Lu
W
Q
J
Q
LI.I
0
J
O
cr
F-
Z
O
O
F-
Z
Lu
Lu
W
Z
Q
Z
O
V/
O
QI
LLI
G
APPROVED DCH
SUBMISSION NO. 1
Plate 3362 T H E W 0 R K O F
I N E GRADE
C2.3
Section 5. Stormwater Management Plan
' I I I 1 I /v/ / /1 //i/ //A// I %/ !// //�i/' �///1I /\// /'%%// / //I 1/ /'\/� —�/ / // iI-�_//I /TiVi T— \ T'T//—/Ti/ I�//\' _�/ i/'/�/'�. I/A'/J i I/ / //// /T/I / /� //�R I� �I ///l— �/ — �I/ I / /— 'r/�il �I / i — ////— / il/ �/ /—_i— ///'� '—/—/V—/ /J / /��_/—�`/—'/—� —/l/ /�3/— \X'��E— R�l T\_ — R_—�—O—_\�_ ` ;�\� —�\_ � �\\A _\\r�\ \`�=��— \ \\ A\\\A_\\ L£\�� E\ L\ O\ —\^� '� \ o.6��o\ �AC� C� �� �� �—z_i——l3n _�—�6�9-- -_se_�'—e—F$/v—��/'_I�//,/�—/v/////-6��///� ///—//�.i/../.r� /// 'j�—'/i// / /�/'/ ii/j/// //// / i. % ////�/ / /////////�/// yi %/G/ /////♦/ // / �'////// //// /// / /// // // /// A/S/�V / i// `///` //,� // ///i` / // / / /i//////// i/j///// ///// / /// / ///j/ /
LEoG. sE0—RUN— E\DJ/a0. w
— I
FIMOaRFERSvEloD\uAS RAE\RA
DMISDFDISTUF
Ra
3
ANDE
I TME OF CONCENTRATION
PAM
DRAINAGE olvloE
SURFACEFLOWARROW
Am WA�N
E
Tc-sMBUFFER/SaarEN2 FLWOPIAIry
c=0
.55 caLNEDnLOPES
FROM
UNIUDER LEVELiOMAC
SPREADER DAI LOD3C4SF
l l I I
/
CUINERTAS
DA-as3 AC`
\\�� ♦ SHEET F49AC AC T /
\TCUSMINSA2 DA) \\ \ O.A9AC \
\\\V A AV AAVA\ A\VAVA V A V A I I V A A AV A \\ �A�
SXEETFLOWAREAA V A_ V A 1 V 1 I I I A S lb
INauDDEES VEL
�v vvvvy�Ov'vvvAv VAVA\VA 1\ II 1 1 1 A v� (INCLUDES vvA •� —I
I`A. VS�1 YRH�\T\IDA=030 N l I
G P\��RA \ \ \ \ LEVEL SPflENEflA \
\\\ \\\5✓.HL/TL\I�WLVERi Al DAI I 1 \
\\\\CxRE�4WSP�\��✓ I III I I 1 \ \ \ —�___ \� \\\\lcoelns
nZ.B \511J313551/,61P4�I
\\\\\ \zbMEAkQ1I1111 I1II 1 /r
vvA �i/S�•�5����iV����AI II I I I I I I I I I 1/ ��
NA, /
�N1
��ll \\IV1VA IIAII III llllll/l/llJ I llIll////�//, //v��v�r� V�VAAA\vv vvv vvv v v'�\ /�,�« I �Aai � �;.
111 l\VA \\V AI I I I III /if l/lI l l llllll // /v I ll I I I\ \ VAA V vv vv vv vi
\1111IIIIIIIIIII111\l\\\
\\ 11\l\IIIII jlllliilll;l\
RAYM N ArWOETrvFmNEv
C6F.'�OENTW /
z, ;1 POSTDEVELOPMENT STORMWATER MANAGEMENT PLAN
50
w
U
Z
L
0
G-
APPROVED DCH
SUBMISSION NO. 1
T H E W 0 R H O F
L I N E + G R A D E
C5.1
Section 6. Pollution Prevention Plan.
(reference State Regulation 9VAC25-880-70 part II section AA)
D. Plan showing pollution activities and prevention practices
// o
/ W z
Lu
umrs ov sueuEYEo rorocaAvriry�/
I.EVELSPRFADERTO DEINSTAll
;RER 3ITEI 1AflIuzED
LOW M4INTENANCE GROUND COVER •�\ / / /' '
ONSLOPE33:SORSTEEPER-SEE /
pRCTUCA RU SI PLANS FOR SEED MIX
LF (FE3NC4 RUBPA)
L g W ' / ' /� p'� i°(%f:� A LOD 1323CC SF \
'o%,,,
PoflT>\AHN(�I Q/e J9` EC2TYPE 1 1
Lu
_LEVEL
MATING
SPREADER ONCESSTOCKIN\\ \\\ \,\ \ \ \ \\ \\ 1\ \��'�/ \ ``\��. — \\ \\0 WASX EDMEMPS�MOF \\•" E \\ \`S I / \) / / LLJ
0 OF
U ui
S 43 LF— �\ IEVELSIPR!R TO RE INSTPIIF➢ I \— \\ Q Z
VSTAFIER SIZE IS STPBN}ED W 0
T. M. 85-/0 TR CT Z \ — \ - — — — \ \ \ SEDIMENT
RAP \ / > m
5545 ACRES \ \ Dfl N GEAR A A3 4c \ I / / Q a
CYRENA W. SPARKMAN \ \ — — \ \ S SB \ ) ` / J
D.B. 5439-179 D.B. 5433-05 8 156 PLAT \ — 1 \ \ \ -1" 1 `
ZONED RA \I O
USE: RESIDENTIAL / / / / — _ \ \ \ \ \� oD f \\
SF GY LF V �b
NAYMCNOdNO BETTYRUNEY
1 �P 08J95P64/4
/ / '� l US �SICENFIAC APPROVED UCH
SUBMISSION NO. 1
PROJECT 2107007
THE WO RH OF
/( LINE + GRADE
NOTECOMRACTg2TOMARNUPR SW"MYCINNGESINTHERE
z, ;1 POLLUTION PREVENTION PLAN — X1.0
1 30:0 SG ED
E. Sources of Pollutants, locations, and prevention practices
Pollutant, or Pollutant Prevention Practices,
Generating Activity Location on site Control Measures
F. Sources of Pollutants, continued. Common activities and minimum control and prevention
practices
Pollutant, or Pollutant
Location on site
Prevention Practices,
Generating Activity
Control Measures
Follow Erosion and Sediment Control
Clearing, grading, excavating, and on-
Land disturbance area
Plan. Dispose of clearing debris at
stabilized areas
acceptable disposal sites. Seed and mulch,
or sod within 7 days of land clearing
Cover storm drain inlets and use drip
Paving operations
Roads and driveways
pans and absorbentloil dry for all paving
machines to limit leaks ands ills
Direct concrete wash water into a leak -
Concrete washout
Current location and detail shown
proof container or leak -proof settling
and cement waste
on plan
basin that is designed so that no overflows
can occur
Enclose or cover material storage areas.
Mix paint indoors in a containment area or
Structure construction, stucco,
Structures
in a flat unpaved area. Prevent the
painting, and cleaning
discharge of soaps, solvents, detergents
and wash water, paint, form release oils
and curing compounds.
Water shall be filtered, settled or similarly
Dewatering operations
Dewatering sites shown on plan
treated prior to discharge as shown on
Ian.
Designated areas for material delivery
Material delivery and storage
Designated area shown on plan
and storage. Placed near construction
entrances, away from waterways and
drainage paths
Material use during building process
Building areas
Follow manufacturer's instructions
. MSDS's attached.
waste collection area will not receive a
substantial amount of runoff from upland
Solid waste disposal
Current designated container areas
areas and does not drain directly to a
on plan
waterway. Containers have lids covered
before periods of rain, or are in a covered
area Scheduled collection to prevent
Pollutant, or Pollutant
Location on site
Prevention Practices,
Generating Activity
Control Measures
overfilling. MATERIALS NOT TO BE
BURIED ON -SITE
Convenient and well -maintained
portable sanitary facilities will be
Sanitary waste
Current locations shown on plan
provided, and located away from
waterways or inlets. Such facilities shall
be regularly maintained.
Apply fertilizers in accordance with
Landscaping operations
Landscape areas shown on plan
manufacturer's recommendations and
not during rainfall events
To be treated in a sediment basin or
Wash Waters
Wash areas shown on plan
better control as specified on plan.
Minimize the discharge of pollutants
from equipment and vehicle washing
Vehicle and equipment washing
Designated areas and details shown on
Provide containment and filtering for all
plan
wash waters per the plan
Minimization of exposure to precipitation and stormwater. Minimize the exposure of building materials, building products,
construction wastes, trash, landscape materials, fertilizers, pesticides, herbicides, detergents, sanitary waste, and other materials
present on the site to precipitation and to stormwater.
G. Non-stormwater discharges (9VAC25-880-70-E)
Discharge
Pollutants or Pollutant
Constituents
Location on Site
Vehicle washout
Sediment, paints, oils
See pollution prevention plans
Dust control spray
Adhesives, sediment
See ESC plans
Pavement and building wash
Soaps, detergents, residual material
See ESC plans
Landscape irrigation
Fertilizers, sediments
See landscape and ESC plans
Concrete washout
Lime, concrete admixtures
See pollution prevention plans
Paint/masonry washout
Paint, oils, construction materials
See pollution prevention plans
K Persons responsible for pollution prevention practices
Name: Owner, Cyrena Sparkman (until contractor is selected)
Address: 41 Wicket Way; POB 2304 Cashiers, NC 28717
Email: cy@sparkman.net
Phone Number: (703)200-1947
I. Response and reporting practices
Minimize dischargesfrom spills and leaks. Minimize the discharge of pollutants from spills and leaks and implement chemical
spill and leak prevention and response procedures as follows.
Respond to all spills, leaks and discharges as follows,
All spills will be cleaned up immediately upon discovery. Spent absorbent materials and rags will be hauled off -
site immediately after the spill is cleaned up for disposal at the nearest landfill.
Report all spills, leaks and discharges as follows,
Spills large enough to discharge to surface water will be reported to the National Response Center at 1-800-424-8802.
J. Pollution Prevention Awareness
All employees will be trained via biweekly tailgate sessions. The sessions will address the
following topics: Erosion and Sediment Control Practices, Non-Stormwater Pollution Prevent
Practices, Waste Management and Materials Storage Practices, and Emergency Procedures
specific to the construction site.
Formal training will be provided for staff with specific stormwater responsibilities, such as
installing and maintaining BMPs. The formal training will cover all design and construction
specifications, and will occur before any BMPs are installed on the site.
Section 7. Discharges to impaired waters, surface waters within an applicable TMDL
wasteload allocation, and exceptional waters.
Runoff from this site discharges to HUC 020802040101 Stockton Creek — Mechums River, which is listed as impaired on
the DEQ Integrated List of All Waters in Virginia. Causes of impairment are Benthic Macroinvertebrates Bioassessments.
Section 8. Qualified personnel
The following personnel are responsible for inspections;
Name: Daniel Hyer, PE (until another consultant is selected)
Address: 113 4t' St NE STE 100 Charlottesville, VA 22902
Email: dhyer@line-grade.com
Phone Number: (434)262-0163
Section 9. Signed Certification
CERTIFICATION
"I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in
accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted.
Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering
the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am
aware that there arc significant penalties for submitting false information, including the possibility of fine and imprisonment
for knowing violations."
Operator Name:
Company:
Title:
Signature:
Date:
Cyrena Sparkman, Property Owner (Contractor TBD)
Section 10. Delegation of authority.
Delegation of Authority
I, (name), hereby designate the person or specifically described position below to be a duly authorized
representative for the purpose of overseeing compliance with environmental requirements, including the Construction General Permit,
at the construction site. The designee is authorized to sign any reports, stormwater
pollution prevention plans and all other documents required by the permit.
(name of person or position)
(company)
(address)
(city, state, zip)
(phone)
By signing this authorization, I confirm that I meet the requirements to make such a designation as set forth in the Construction
General Permit (CGP), and that the designee above meets the definition of a "duly authorized representative".
Operator Name:
Company:
Title:
Signature:
Date:
Section 11. General permit copy
To be included with final SWPPP.
Section 12. Inspection logs
Section 12a. Corrective Action Log
Project Name: Waverly Residence
SWPPP Contact:
Inspection
Date
Inspector
Name(s)
Description of Deficiency
Corrective Action Needed (including planned
date/responsible person)
Date Action
Taken/Responsible
person
Section 12b. SWPPP Amendment Log
Project Name: Waverly Residence
SWPPP Contact:
Amendment No.
Description of the Amendment
Date of Amendment
Amendment Prepared by
Names and Title
Section 12c. Grading and Stabilization Activities Log
Project Name: Waverly Farm
SWPPP Contact:
Date
Grading
Activity
Initiated
Description of Grading Activity
Date Grading
Activity Ceased
(Indicate
Temporary or
Permanent)
Date When
Stabilization
Measures are
Initiated
Description of Stabilization Measure and
Location