Maria,
I confirmed that Sec. 9 of the SWPPP must be signed prior to WPO plan approval. Sec. 9 certifies the entire SWPPP packet is
accurate. Sec. 6.E, 8 (named individuals responsible for PPP, ESC inspections), and Sec. I (Registration statement) signature
may wait until a contractor is chosen, without affecting WPO plan approval. We do, however, need Sec. 9 of the SWPPP
signed to approve the WPO plan. Yes, until the WPO plan is approved, the site plan cannot be approved. I hope this helps,
thank, Maria.
John E. Anderson, PE I Civil Engineer II
Department of Community Development I County of Albemarle, Virginia
401 McIntire Road I Charlottesville, VA 22902
434.296.5832 ext. 3069
From: Maria McCarty <mmccarty@sehinc.com>
Sent: Monday, October 18, 2021 2:53 PM
To: John Anderson <janderson2@albemarle.org>; Brad Weiss <bweiss@sehinc.com>; Michelle S. Simpson, PE
<msimpson @ rivanna.org>
Cc: Austin Marrs <amarrs@rivanna.org>; Frank Pohl <fpohl@albemarle.org>; Andy Reitelbach
<mreitelbach@albemarle.org>
Subject: RE: Planning Application Review for WP0202100035 AIRPORT RD. PUMP STATION - VSMP - DIGITAL. [
Engineering review comments ]
Jim,
I would like to clarify the expectations for the SWPPP and PPP. On past project with the county I have
submitted the SWPPP without any signatures, because we wanted the contractor to submit the
application. The county responded to our submittal as follows:
A. Stormwater Palliation Prevention Plan (SWPPP)
The SWPPP content requiremems can he found in County Code section 17-405. A SWPPP must contain
(1) a PPP, (2) an ESCP, (3) a SW MP, and (4) any TMDL measures necessary.
1. The Registration Statement and Certification will need to he completed and signed prior to scheduling a
pre�onstruction meeting and permit issuance.
If we wait to submit the completed and signed SWPPP until after bidding, will that hold up any other reviews,
such as site plan?
Thanks,
Maria
Maria McCarty, PE (Lic. MN)
Engineer
Short Elliott Hendrickson, Inc.
507.237.8378 direct I Working from Home 507.508.4707 mobile 1651.490.2000 main
Building a Better World for All of Us@
Follow SEH on Twitter I Facebook I Linkedln I Instagram
From: John Anderson <ianderson2@albemarle.ors>
Sent: Friday, October 15, 20214:07 PM
To: Maria McCarty <mmccarty@sehinc.com>; Brad Weiss <bweiss@sehinc.com>; Michelle Simpson
<msimpson@rivanna.org>
Cc: Austin Marrs <amarrs@rivanna.org>; Frank Pohl <fpohlCa@albemarle.org>; Andy Reitelbach
<mreitelbach@albemarle.org
Subject: Planning Application Review for WP0202100035 AIRPORT RD. PUMP STATION - VSMP - DIGITAL. [ Engineering
review comments ]
The Review for the following application has been completed:
Application Number = WP0202100035
Reviewer = John Anderson
Review Status = Denied
Completed Date = 10/15/2021
This email was sent from County View Production.
Maria,
Brad, Michelle,
Thanks for your patience; attached also in CV.
Additional CV comment:
`ESC. SWM plans approved, SWPPP incomplete.'
Enjoy the weekend
best, J. Anderson