1. Move the fire hydrant and water meter to a less visible location and add landscaping to provide more complete
s c reeni ng /integration.
Response: Per confirmations at the ARB meeting on 11/15/2021, the hydrant remains were previously
proposed. Additional landscape plantings have been provided around the hydrant to aid in screening the
hydrant from the public right-of-way.
2. Revise the photometric plan using an LLF of 1.0 for all fixtures.
Response: The LLF has been updated to 1.0 for all fixtures as requested.
3. Revise the finish for the parking lot lights (poles and fixtures) to bronze.
Response: The parking lot lights have been updated to have a bronze finish as requested.
4. Add a street tree along Greenbrierwest of the monument sign and add shrubs between Greenbrier and the 8-
space parking row.
Response: Shrubs have been provided between the 8 parking spaces and Greenbrier Dr. An additional
tree has been provided along Greenbrier Dr., j ust west of the monument sign, in order not to block the
visibility of the sign from Greenbrier Dr.
5. Add landscaping between the Greenbrier sidewalk and the new path connecting the sidewalk to the parking lot
to compensate for the lack of trees in other required locations.
Response: Low-level plantings have been provided on both sides of the new sidewalk.
6. Provide additional low- level planting along the Rt. 29 and Greenbrier f rontages to offset visual impacts,
compensate forsmallertrees and help establish an overall coordinated landscape.
Response: Additional low-level plantings have been provided along Route 29 and Greenbrier Drive.
7. Revise the Luminaire Location Summary to correspond to the 22' 11" maximum canopy height and make other
corresponding corrections as necessary, while maintaining a maximum of 30 fc under the canopy.
Response: Luminaire location summary has been updated to show fixtures under the 22' 11" maximum
canopy height while maintaining a maximum of 30 fc under the canopy as requested.
8. Revise the photometric plan using an LLF of 1.0 for all fixtures. Reduce the illumination under the fuel pump
canopy to a maximum of 30 fc.
Response: The photometric plan has been updated to use an LLF of 1.0 for all fixtures as requested. The
illumination under the fuel pump canopy has been updated to be a maximum of 30 fc as requested.
9. Revise the landscape plan to integrate the monument signs more fully into the landscape.
Response: The Monument signs are fully integrated withinthe landscape beds, similarto other Wawa
locations.