County of Albemarle
m COMMUNITY DEVELOPMENT DEPARTMENT
VSMP Permit Plan Review
Project title:
Brookhill VSMP for Road Improvement Plan
Project file number:
WPO201800013-amendment 2
Plan preparer:
Scott Collins [scott@collins-engineering.com]
Owner or rep.:
Riverbend Development [Alan Taylor]
Plan received date:
18 Aug 2021
Rev. 1 received:
05 Nov 2021
Date of comments:
28 Sept 2021
Rev. 1 comments:
02 Dec 2021
Reviewer:
Emily Cox
401 McIntire Road, North Wing
Charlottesville, VA 22902-4579
Telephone: 434-296-5832
WWW.ALBEMARLE.ORG
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is denied/approved.
The rationale is given in the comments below. The VSMP application content requirements can
be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP
must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Please provide existing VAR permit number that covers this area along with the current
coverage map for Brookhill. Rev. 1: This map needs to be updated. The map should
match the plan for Blocks 16 & 17.
2. Rev. 1: The registration statement area should match Blocks 16 & 17 (with this plan area
in parentheses).
3. Rev. 1: The registration statement and section 9 must be signed.
4. Rev. 1: Please update the projected start date since it has already passed.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
' PPP was not provided. Rev. 1: Comment addressed.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is denied, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-
403.
1. The original WPO201800013 showed 2 level spreaders(LS-10 & LS-11). It appears LS-10
is shown as existing on this plan. It is our understanding that both of these have been
removed. Please only show what is existing on site. Rev. 1: Comment addressed.
2. Please provide an updated Brookhill water quality compliance table with this plan. The
one shown on the original WPO201800013 is outdated. This also relates to comment #1
regarding the removal of the level spreaders. Rev. 1: Comment addressed.
Engineering Review Comments
Page 2 of 3
3. Please add a note somewhere on the plan that amendment 1 to this plan was withdrawn.
Don't want someone in the future searching for amendment 1. Rev. 1: Comment
addressed.
Rev. 1: [Sheet 91 Please clarify this note below, with what plan(s)? WP020210007, any
others?
4. Water quality requirements for this plan ('NPO 201800013 Amendment a2) have previously been sutisdmd.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion
control plan content requirements can be found in County Code section 17-402.
1. VDOT approval will be necessary for this work in the right-of-way. Do you have their
approval for what is proposed for this E&S work? Trying to prevent the need for another
plan amendment. Rev. 1: Comment not addressed.
2. Per the detail, please show the location of the dewatering devices. It is understood that
the dewatering pump will move with the work. Rev. 1: Comment addressed.
3. Outlet protection sizing requirements are shown, but not the calculations. Please show
how the dimensions were determined. Rev. 1: Where did the Q come from and what
year storm is it? Please provide calculations.
4. Please update project description on sheet 4. Please state the proposed limits of
disturbance with this plan and update the completion date (2022?). Rev. 1: Comment
addressed.
The VSMP permit application and all plans may be resubmitted for approval when all comments
have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete
permit package with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a
meeting to discuss this review.
Process:
After approval, erosion and sediment control and stormwater management improvements must
be bonded. The bonding process begins when the plan is approved, and the applicant submits a
bond estimate request form and fee to the Department of Community Development. A plan
reviewer will prepare estimates and check parcel and easement information based on the
approved plans. The County's Management Analyst will prepare bond agreement forms, which
will need to be completed by the owner and submitted along with cash, certificates or sureties
for the amounts specified. The agreements will need to be approved and signed by the County
Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and
forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and
recorded. The County's Management Analyst or other staff will prepare the forms and check for
Engineering Review Comments
Page 3 of 3
ownership and signature information. The completed forms will need to be submitted to the
County, who will record the agreement.
After bonding and agreements are complete, county staff enters project information in a DEQ
database for state application processing, if a DEQ permit is required. DEQ reviews the
application information based on local VSMP authority approval. At this time, the DEQ portion of
the application fees will need to be paid directly to the state. For fastest processing, this is done
electronically with the emails provided on the application. DEQ should notify applicants with
instructions on how to pay fees. When DEQ approves the application, they will issue a permit
coverage letter, which must be posted at the construction site.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction
conference. Applicants must complete the request for a pre -construction conference form and
pay the remainder of the application fee. The form identifies the contractor and responsible land
disturber, and the fee remaining to be paid. This will be checked by county staff, and upon
approval, a pre -construction conference will be scheduled with the County inspector. At the pre -
construction conference, should everything proceed satisfactorily, a joint VSMP and grading
permit will be issued by the County so that work may begin.
County forms can be found on the county website forms center under engineering;
httos://www.albemarle.org/government/community-development/aooly-for/engineering-aool ications