HomeMy WebLinkAboutSDP202100088 Review Comments Major Amendment, Final Site Plan 2022-01-11SDP2021-88 N Garden Fire Dept
Comments: CDD ARB : Khris Tatggart
ktaggart@albemarle.org
12-20-2021
An ARB Countywide Certificate of Appropriateness application is required for review. In Part B of the
ARB application form (https://www.albemarle.org/Home/ShowDocument?id=956 ), that would be a
Countywide Certificate of Appropriateness for Additions toARB-approved buildings." Here is a link
(https://www.albemarle.org/Home/ShowDocument?id=966 ) to the submittal requirements for that
type of application.
SDP2021-88 N Garden Fire Dept
Comments: CDD Inspections— Betty Slough
bslouah@albemarle.ore
12-27-2021
Replace Note 9 under Plan notes on page 2 with this:
1. All water, sewer and fire lines require NEW inspection and testing procedures. The ACSA
performs any testing and inspections of the public sewer and water main(s).
2. The Albemarle County Building Inspections Department(ACBID) does a visual inspection and
witnesses the testing of the building drain, water service pipe and the sprinkler lead-in
connection.
3. The developer/contractor is responsible to retain a Special Inspector as outlined in the updated
Albemarle County Policy for Site Utilities to perform the visual inspection and testing of all
utilities not covered by the ACSA or ACBID. This includes building sewers, water and fire line
branches between the main and the meter(s)/building(s).
4. The Special Inspector's report must be submitted and approved by the Albemarle County
Engineering Department prior to a Certificate of Occupancy being issued.
SDP2021-88 N Garden Fire Dept
Comments: Fire/Rescue—Howard Lagomarsino
hlaeomarsino@albemarle.org
12-20-2021
1. Please add a note to the plan with the ISO calculated needed fire flow of the building
2. Please add a note on the plan as to the nearest water source available to support fire
suppression operations.
SDP2021-88 N Garden Fire Dept
Comments: ACSA — Richard Nelson
rnelson@serviceauthority.org
12-17-2021
No Objection, project is outside ACSA service area