COUNTY OF ALBEMARLE
Dept. of Planning & Community Development
401 McIntire Road
Charlottesville, Virginia 22902.4596
(804) 296-5823
MEMORANDUM
TO: Development Corporation of Virginia
FROM: Yolanda A. Hipski, Planner
DATE: September 2, 1993
RE: Site Review Comments - SUB-83-105 - Redfields Phase 2A
Final Site Plan
The Site Review Committee reviewed the above referenced plan/plat
on September 2, 1993. Pertinent comments from the following
agencies are attached:
• Planning Department - contact Planner - 296-5823
• County Engineer - contact Jack Kelsey - 296-5861
• Fire Officer - contact Jay Schlothauer - 296-5832
• Service Authority - contact Pete Gorham - 296-5810
oW* Health Department - contact Gary Rice - 972-6259
• Virginia Department of Transportation - contact
John DePasquale - 296-n102
• Soil Conservation Service - contact Gordon Yager - 296-9337
• Watershed Management - David Hirschman - 296-5861
• Zoning - contact Babette Thorpe - 296-5875
The Committee' s comments will reflect information available at
the time the plan/plat was reviewed, but should not be considered
final.
Please revise the plan/plat to include the attached comments and
submit seven ( 7) full size copies and one 11 x 17 copy of the
revised plan/plat no later than 5 : 00 p.m. September 13, 1993.
Site Review Comments - Redfields, Phase 2A
Page 2
September 2 , 1993
No plan/plat will be scheduled for Planning Commission review
until all necessary information and items marked with ** on the
comments are submitted, in a form satisfactory to the Director of
Planning and Community Development.
Provided that you meet the stated deadline for revisions , and
the revisions are satisfactory, your plan/plat will be heard
by the Planning Commission on October 5, 1993, 7 : 00 p.m. ,
Meeting Room #7 , Second Floor, County Office Building,
401 McIntire Road. THE APPLICANT OR A REPRESENTATIVE MUST
BE PRESENT AT THE PLANNING COMMISSION MEETING.
The Planning Commission will not review plans/plats which
occasion sight distance, grading, or other easements (excluding
those for public utilities) , without evidence from the developer
that permission is obtainable. This evidence must be submitted
by the revision deadline for this item to proceed to the Planning
Commission at the above-noted date.
In such case in which the developer does not revise the plan to
include recommendations of the committee, the developer shall
submit in writing to the agent by the revision date a statement
as to the reasons and justification for not incorporating such
recommendations in the revised plan.
Thank you.
YAH/blb
cc: The Cox Company
SITE REVIEW COMMENTS - SUB-93-105 - REDFIELDS PHASE 2A FINAL SITE
PLAN
** 1. Variation in site development plans and subdivision
plats from approved PRD application plans may be
permitted by the Director of Planning and Community
Development ( Section 8 . 5 . 6 . 3 of the Zoning Ordinance) .
The Director may administratively approve minor
modifications after finding that such variations are
generally in keeping with the spirit and concept of the
approved application plan; in accordance with the
Comprehensive Plan; and in accordance with the
regulations currently in effect.
Sheet 8 of 25 indicates a total of 57 lots shall
ultimately be constructed with Phase 2 . However, the
rezoning plan allowed "49 suburban single family
detached residential units" . "Road L" , or "Canvas Back
Lane" , was allowed a total of 26 units. This plan,
however, creates a total of 30 residential lots and one
pump station lot. Confirm this increase does not
interfere with prior road approvals for vehicle trips
allowed. The previous rezoning plan indicated 23 . 4
acres shall be "Open Space and one Single Family
detached" . Confirm that at lease 23 . 4 acres shall
remain as "Open Space and one single family detached"
in Phase 2 . ( See comment 2 ) .
Once these items have been addressed, be sure to revise
Page 3 of 25 of the packet to redistribute these lots .
Be sure the total number of lots does not exceed the
original approval nor the Open Space area decrease in
size. These variations must comply with Section
8. 5 . 6 . 3 . Therefore, request from the Director of
Planning and Community Development a variation of the
Redfields Zoning Plan in accord with Section 8 . 5 . 6 . 3 .
to allow a new distribution of lots in Phase 2 . Please
call me if you have any questions .
** L.- Remove reference to "future development" on Page 6 of
25 , replace with "Open Space and one Single Family
Dwelling" . Staff cannot administratively approve this
variation.
** 3 . Zoning Proffer 4 states:
"The proposed recreation center shall be constructed
with Phase I" .
I understand the applicant has had extensive
discussions with both the Zoning Administrator and the
Director of Planning and Community Development. Ms .
Thorpe of the Zoning Department clearly noted in her
comments that her approval will not be issued until a
building permit has been has been issued and
construction started for the recreation center. I am
confirming this issue with the Director of Planning and
Community Development. If you have any comments
regarding timing, please contact me, or Babette, as
soon as possible.
4 . I have discussed the pump station location with the
Albemarle County Service Authority. I understand that,
given design constraints such as slope, this location
may be difficult to change. This department, however,
is concerned about possible conflicts between
residential lots and noxious characteristics of pump
stations (visual, noise, odor) .
** 5. If the pump station shall remain at its proposed
location, this department will require screening
between the pump station and residential lots . Provide
a double staggered row of wet tolerable screening
trees, spaced fifteen ( 15 ) feet on center. Note "This
screening shall be maintained and replaced if any
should die".
** 6 . Be sure to note the pump station shall be dedicated to
the Albemarle County Service Authority.
** 7 . On Page 6 of 25 , be sure to note the access easement to
the pumping station. Also, note that the setback must
be 20 feet. If you wish to modify this setback, submit
a request in accord of Section 8 . 6 . 5 . 3 ( see comment 1 ) .
** 8 . A landscape plan shall be required for the double
frontage lots ( lots 25 , 26 ,' 27, 28 , 29 and 30 ) .
** 9. Address comments from all other agencies .
''®114
a 'w—
ay
friRcirly'
COUNTY OF ALBEMARLE
Department of Engineering
401 McIntire Road
Charlottesville, Virginia 22902-4596 RECEIVED
(804) 296-5861
MEMORANDUM 4Ub' . 1 1993
Planning Dept
TO: Yolanda Hipski, Planner
.
FROM: Don Franco, PE - Engineer tP
RE: Site Review Meeting of 2 September 1993
DATE: August 31, 1993
Redfields Phase 2-A Preliminary Plat (SUB-93-105)
Watershed Boundary - Upper Rivanna River watershed, Moores Creek subwatershed
Streams/Watercourses - Intermittent streams as shown on site plan. An intermittent tributary
to Moores Creek runs along the eastern edge of the parcel. Moores Creek roughly follows the
railroad tracks at the northern tip of the parcel.
Wetlands - 2 ponds are associated with the intermittent stream at the eastern edge of the
parcel.
Water Resources Protection Areas Ordinance - Applies only to the main stem of Moores
Creek along the parcel's northern edge. Moores Creek does not seem to be affected by this
phase of the development.
Final Plat approval will not be granted until satisfactory address of the following:
1. Subdivision plat should be at 1" = 100' and the maximum sheet size should be 11"x18"
with a 1" border;
2. The drainage easements associated with the VDOT right-of-way shown on the
subdivision plat (sheet 6/25) should be dedicated to public use;
3. The portion of the drainage easements between lots 18/19 and 6/7 and 10' below the
outfall of the drainage pipe extending beyond the VDOT right-of-way should be
dedicated to public use; and
4. Department of Engineering approval of grading and drainage plans and calculations.
FAX (804) 972-4060
Yolanda Hipski
August 31, 1993
Page 2
5. Completion of the stormwater detention facility, partially bonded under the phase 1B
erosion control bond or submittal of calculations which demonstrate that the existing
structure provides adequate stormwater detention for 2A and all previously approved
improvements;
6. Recordation of a County standard "Maintenance Agreement" (see attached) is required
for the stormwater management facility.
7. Department of Engineering approval of the Erosion & Sediment Control Plan.
COUNTY OF ALBEMARLE
RECEIVED
9��"
®_� SEP 0 1 199i
7
Plannin
g Dept.
MEMORANDUM
TO: Yolanda Hipski, Planner
FROM: Babette Thorpe, Zoning Assistant
DATE: September 1, 1993
RE: Redfields, Phase 2A
Site Review Comments
1. You and I have discussed with the applicant the timing
involved between reviewing this plan and the construction of
the recreation center. As you know, proffer #4 of ZMA-89-18
stated: "The proposed recreation center shall be
constructed with Phase 1" . The Zoning Administrator has
agreed that we can accept this plan for review, without the
recreation facility having been built. We will not issue
tentative approval for phase 2A unless a building permit has
been issued for the recreation center. We will not issue
final approval until construction has begun on the pool.
Please discuss this with the Director of Planning to insure
that he concurs with this approach.
2 . Proffer #8 (2) of ZMA-89-18 calls for a 20-foot open space
strip and landscape easement adjacent to Tax Map 76, parcel
49B. Please have the applicant show this open space and
easement.
3 . Please clarify the intent of the easements shown on Lots 20
through 30. Will these areas be graded and replanted? Or
are these to be areas in which no clearing or grading is to
take place?
:�V s la%\
it `j�>x
io �, g
COMMONWEALTH of VIRGINIA
DEPARTMENT OF TRANSPORTATION
P 0 BOX 671
RAY D. PETHTEL CULPEPER,22701 DONALD R.ASKEW
COMMISSIONER DISTRICT ADMINISTRATOR
Mr. William D. Fritz September 1, 1993
Dept. of Planning &
Community Development
County of Albemarle
401 McIntire Road
Charlottesville, Va. 22901-4596
Dear Mr. Fritz :
We have reviewed the final plat for the subject development and
offer the following comments:
SUB-93-105 - Redfields Phase 2A Final Plat
No Comment
As always, any work done on VDOT right of way must be under
permit as issued by the Charlottesville Residency.
Sincerely,
mes C. Call
Des. Draft. Tech.
cc: Ms. A.G. Tucker
TRANSPORTATION FOR THE 21ST CENTURY
U.S. Department o tgr / cu | ture Page - 1
Soil Conservation Service 8/25/93
------------_-------------------------------____-------------------------_
NONTECHNICAL SOILS DESCRIPTION REPORT
FOR DESCRIPTION CATEGORY - A6R
Survey Area- ALBEMARLE COUNTY , VIRGINIA
_____----------------------------------
__________________________________
Map
Symbol Description
----------_---------------____-----------_----------____---______-----__ __
21B [ULPEPER FINE SANDY LOAM, Z TO T PERCENT SLOPES
Culpeper soils are deep and well drained . Permeability
and available water capacity are moderate . Runoff
erosion hazard vary with slope from medium to severe .
Ti | th is good . The organic matter content and the
natural fertility are low. React / on commonly / s very
strongly acid or strongly acid throughout , but / s
variable / n the surface layer because of local liming .
The root zone extends to a depth of W inches . Bedrow
/ s generally at a depth of 50 inches or more . The
subsoil has moderate shrink-swell potent / a | .
21[ CULPEPER FINE SANDY LOAM, T TO 15 PERCENT SLOPES
Culpeper soils are deep anU well drained . Permeability
and available water capacity are moderate . Runoff
erosion hazard vary with slope from medium to severe .
Ti | th / s good . The organic matter content and the
natural fertility are low. React / on commonly / s very
strongly acid or strongly acid throughout , but is
variable in the surface layer because of local liming .
The root zone extends to a depth of ]b inches . Bedrock
/ s generally at a depth of 50 inches or more . The
subsoil has moderate shrink-swell potential .
39D HAZEL LOAM, 15 TO 25 PERCENT SLOPES Hazel soils are
deep excessively drained soils . Permeability / s
moderately rapid . Available water capacity / s low.
Surface runoff / s rapid to very rapid . The hazard of
erosion is severe to very severe .The subsoil has low
shrink-swell potential . The root zone extends to a
depth of 20 inches . The organic matter 6ontent and the
natural fertility are ( ow. This soil commonly is
strongly acid or very strongly acid . Depth to bedrock
ranges from 20 to 40 inches .
48E LOUISBUR6 VERY STONY SANDY LOAM, 25 TO 45 PERCENT
SLOPES Louisburg soils are deep and well drained .
Permeability is rapid , and the available water capacity
/ s low. Eros / on hazard varies from severe to very
severe . The subsoil has very low shrink-swell
potential . The root zone extends to a depth of about 40
inches . The organic matter content and natural
fertility are low. The soil / s strongly acid or very
strongly acid thou8hout , but react / on / s variable
because of local liming . Bedrock is generally at a
depth of more than 48 inches .
U.S. Department of Agriculture Page - !
Soil Conservation Service $a/a
72 FEATURES
Survey Area- AL q± COUNTY, VIRGINIA
; Cemented l :Potential 2—-Risk of corrosion
Map s ol and . Bedrock . pan . Subsidence-- frost :Uncoated
so name : Depth Hardness 1 Depth Hardness : Initial Total : action : steel Concrete
In R R in
ae 2JJm 48- 48 HARD - - - MODERATE MODERATE MODERATE
21C ±Jam a- m HARD - - - MO RATE MODERATE MODERATE
3e HAZEL m- g HARD - - - MODERATE LOW HIGH
48E 3\S. 40- 40 HARD - - - LOW MODERATE
U.S. Department of Agriculture Page - 1
Soil Conservation Service 8/25/93
WATER FEATURES
Survey Area- ALBEMARLE COUNTY, VIRGINIA
Map symbol and :Hydrologic: Flooding High water table
soil name l group 1Freq Duration Months 1 Depth Kind Months
(Ft)
21B CULPEPER C NONE - 6.0- 6.0 -
t1C CULPEPER C NONE - 6.0- 6.0 -
39D HAZEL C NONE - 6.0- 6.0 -
48E LOUISBURG B NONE - 6.0- 6.0 -
• • U.S. Department of Agriculture Page - 1
Soil Conservation Service 8/25/93
SOIL INTERPRETATION REPORT
Survey Area- ALBEMARLE COUNTY, VIRGINIA
Map Symbol, Shallow Dwellings Small Local Streets Lawns,
Soil Name Excavations Without Commercial and Roads Landscaping,
Basements Buildings and Golf
Fairways
21B CULPEPER MODERATE MODERATE MODERATE SEVERE SLIGHT
Depth To Rock Shrink-swell Shrink-swell Low Strength
Too Clayey Slope
Z1C CULPEPER MODERATE MODERATE SEVERE SEVERE MODERATE
Depth To Rock Shrink-swell Slope Low Strength Slope
Too Clayey Slope
Slope
39D HAZEL SEVERE SEVERE SEVERE SEVERE SEVERE
Depth To Rock Slope Slope Slope Slope
Slope
48E LOUISBURG SEVERE SEVERE SEVERE SEVERE SEVERE
Slope Slope Slope Slope Large Stones
Slope
ALBEMARLE COUNTY SERVICE AUTHORITY
MEMO
To: Yolanda A. Hipski, Planner
FROM : Peter C. Gorham, Civil Engineer I
DATE: September 2, 1993
RE: Site Plan Technical Review for: Redfields Phase 2A Final Plat
The below checked items apply to this site. (TM 76R Parcel 1)
x 1. This site plan isAWVOtiat within the Authority's jurisdictional
area for:
X A. Water and sewer
B. Water only
C. Water only to existing structure
D. Limited service
X 2. A 12 inch water line is located approximately onsite
3. Fire flow from nearest public hydrant, located ist
from this site plan, is gpm+ at 20 psi re al.
X 4. An 8 inch sewer line is located onsitexkbotamx.
5. An Industrial Waste Ordinance survey form must be completed.
X 6. No improvements or obstructions shall be placed within existing
or future easements.
X 7. Water and sewer plans are currently under review.
8. and plans have been received and approved.
9. No plans are required.
X 19. Final water and sewer plans are required for our review and
approval prior to tiNaVFOVER4A granting tentative approval.
11. Final' site plan may/may not be signed.
12. RWSA approval for water and/or sewer connections. -
Comments: Pump station shall be sized to serve applicable portions of
Phase 5. Pump station shall also be located to serve future Phase 5.
The site plan does not show or incorrectly shows:
meter locations water line size
water line locations sewer line size
sewer line locations expected wastewater flows
easements expected water demands
SUB-93 105
4o1r11)4.7.,
eAt.gb
! C, :,.11 REcEiv,E0
' nE' U i993
COUNTY OF ALBEMARLE
Department of Inspections Planning Dept.
Charlottesville, Virginia 22901-4596
(804) 296-5832
MEMORANDUM
To: Yolanda Hipski - Planner
From: Jay Schlothauer - Deputy Director of Inspections
Date: August 31, 1993
Re: Redfields Recreation Center - Major Amendment (SDP-93-039)
(plans revised August 26, 1993)
The Inspections Department and the Fire Prevention Office have no
further comments. Approval may be granted by this office.
JS/js
cc: Fred Missel - The Cox Company
file