HomeMy WebLinkAboutSUB199300105 Approval - County Final Plat 1993-10-16 pros Ar./
4116,70,-
17/tGly\'
COUNTY OF ALBEMARLE
Dept. of Planning & Community Development
401 McIntire Road
Charlottesville, Virginia 22902-4596
(804) 296-5823
December 23, 1993
Gaylon Beights
Development Corporation of Virginia
One Boars Head Place
Charlottesville, VA 22901
RE: (SUB-93-105) Redfields Phase 2A Final Plat
Dear Mr. Beights:
The above-noted final plat received December 16, 1993, has been reviewed and
administratively approved by the Planning Department. Please note that this
approval is subject to the following conditions:
1. The final plat shall not be submitted for signature nor shall it be
signed until the following conditions are met.
a. Department of Engineering approval of grading and drainage plans
and calculations;
b. Completion of the stormwater detention facility or Department of
Engineering approval of alternate stormwater detention plans and
calculations;
c. Recordation of a County standard "Maintenance Agreement" for the
stormwater management facility;
d. Department of Engineering approval of an erosion control plan;
e. Virginia Department of Transportation approval of road and
drainage plans and calculations; and
2. Administrative approval of final plat.
In order to be eligible for administrative approval by the agent, a final site
development plan shall be submitted on a submittal deadline with the
appropriate fee within six (6) months of the approval of the preliminary plan.
Gaylon Beights
Page 2
December 17, 1993
In any case, the final site development plan shall be submitted within one (1)
year of the approval of the preliminary plan or the approval shall expire. If
the final plan is submitted after six (6) months, but within one (1) year,
adjacent owners will be renotified and the plan will be reviewed through the
Site Review Committee and, if necessary, the Planning Commission.
During the above time period, the applicant shall work to satisfy the
conditions of preliminary site development plan approval. The applicant shall
have the appropriate agency notify this Department in writing that the
applicable conditions have been met.
To obtain tentative approvals for the final site development plan from the
agencies represented on the Site Review Committee, the applicant shall submit
the appropriate plans and materials to each agency, individually, for their
review. Once the plans have been tentatively approved by each agency, the
applicant shall have each agency notify the Planning Department in writing,
that tentative approval has been secured.
Once tentative approvals are secured, the final plan shall be submitted to
this Department, as stated above. The final plan mylar can be signed at the
scheduled Site Review Meeting if after staff review, the final plan meets all
ordinances and conditions of approval.
If you should have any questions or comments regarding the above-noted action,
please do not hesitate to contact me.
Sincerely,
' \\424
Yolanda Hipski
Planner
YH/jcw
cc: Fred Missel
pF AI.BF,
Ch
ti/ r
1111111
I•/�.lv\a
COUNTY OF ALBEMARLE
Dept. of Planning & Community Development
401 McIntire Road
Charlottesville, Virginia 22902-4596
(804) 296-5823
December 20, 1993
Gaylon Beights
Development Corporation of Virginia
One Boars Head Place
Charlottesville, VA 22901
RE: (SUB-93-105) Redfields Phase 2A Final Plat
Dear Mr. Beights:
The above-noted final plat received December 16, 1993, has been reviewed and
administratively approved by the Planning Department. Please note that this
approval is subject to the following conditions:
1. The final plat shall not be submitted for signature nor shall it be
signed until the following conditions are met.
.a:'. Department of Engineering approval of grading and drainage plans
and calculations;
Completion of the stormwater detention facility or Department of
Engineering approval of alternate stormwater detention plans and
calculations;
Recordation of a County standard "Maintenance Agreement" for the
stormwater management facility;
Department of Engineering approval of an erosion control plan;
Virginia Department of Transportation approval of road and
drainage plans and calculations; and
2. Administrative approval of final plat.
In order to be eligible for administrative approval by the agent, a final site
development plan shall be submitted on a submittal deadline with the
appropriate fee within six (6) months of the approval of the preliminary plan.
Gaylon Beights
Page 2
December 17, 1993
In any case, the final site development plan shall be submitted within one (1)
year of the approval of the preliminary plan or the approval shall expire. If
the final plan is submitted after six (6) months, but within one (1) year,
adjacent owners will be renotified and the plan will be reviewed through the
Site Review Committee and, if necessary, the Planning Commission.
During the above time period, the applicant shall work to satisfy the
conditions of preliminary site development plan approval. The applicant shall
have the appropriate agency notify this Department in writing that the
applicable conditions have been met.
To obtain tentative approvals for the final site development plan from the
agencies represented on the Site Review Committee, the applicant shall submit
the appropriate plans and materials to each agency, individually, for their
review. Once the plans have been tentatively approved by each agency, the
applicant shall have each agency notify the Planning Department in writing,
that tentative approval has been secured.
Once tentative approvals are secured, the final plan shall be submitted to
this Department, as stated above. The final plan mylar can be signed at the
scheduled Site Review Meeting if after staff review, the final plan meets all
ordinances and conditions of approval.
If you should have any questions or comments regarding the above-noted action,
please do not hesitate to contact me.
Sincerely,
o a Hipski
Planner
YH/j cw
cc: Fred Missel