Loading...
HomeMy WebLinkAboutSUB199300105 Review Comments 1993-12-21 V. 4 OV A Liip rai C.,Yearaii COUNTY OF ALBEMARLE Department of Engineering 401 McIntire Road Charlottesville, Virginia 22902-4596 (804) 296-5861 December 21, 1993 Mr. Fred Missel, ASLA RE CEIVED The Cox Company Ute 2 1 1993 220 East High Street Charlottesville, VA 22902 q.: re: Redfields Phase 2A Planning Dear Mr. Missel: The following recent submittals regarding the above referenced project have been reviewed: a. 10/27/93 Redfields Phase 2A Final Plat & Road Plans b. 12/08/93 Memorandum - Redfields Pond c. 12/15/93 Transmittal - County Standard Maintenance Agreement& Proof of Recordation d. 12/16/93 Memorandum - Phase 2A Stormwater Detention & Management The following comments regarding this information are offered as they relate to the conditions of final approval as outlined in my memorandum (12/15/93) to Yolanda Hipski: 1. Grading and Drainage Plan Approval - Previously approved drainage calculations (approved 12/12/90) do not appear to include computations or design information for the ditches receiving stormwater discharge from drainage structures 1, 25, and 7. The following items and conditions must be satisfactorily addressed: la. Provide ditch sections. lb. Provide additional topographic information for the area south of the lc. Provide adequate ditch calculations for each receiving channel. ld. Provide 20' permanent drainage easements along these ditches. The permanent drainage easement should begin at the outfall, or terminus of other drainage easements, and end at a natural water course. FAX (804) 972-4060 Mr. Fred Missel 21 December 1993 Page 2 2. Stormwater Detention - 2a. Delineate which portions of Phase 2a are controlled and which are uncontrolled by the stormwater detention structure. 2b. Submit plans and adequate channel computations for offsite channels receiving stormwater discharges. This information is specifically required in order to ensure that increased runoff generated on site which is not controlled by the stormwater detention pond does not negatively impact adjacent properties. 3. County Standard Maintenance Agreement - satisfied. 4. Erosion Control Plan Approval - required prior to final plat approval. 5. VDOT Approval - satisfied. 6. Road Bonding - required prior to final plat signature. Please contact me at your earliest convenience if you have questions regarding these comments or require additional information. Sincerely, ptJl ' c Don Franco, PE Civil Engineer II ACF/ CC: Jack Kelsey Job File - SUB 93-105 Reading File - b93105_c.fin