HomeMy WebLinkAboutWPO201900052-78285-Full Inspection ReportV NOTICE TO COMPLY Hand delivered Project: WP0201900052 BERKMAR DRIVE APARTMENTS - VSMP Operator/Contractor: Umer Hasan with Breeden Construction UPTOWN VILLAGE LLC Issued Date: 1/28/2022 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 434 296-5832 Under section § 17-900 of the Albemarle County Code, this is your NOTICE TO COMPLY with the requirements of the Land Disturbance Permit (or Agreement in Lieu of a Plan) for the referenced project and to immediately take corrective measures to address erosion and sediment control deficiencies on this property. This Notice to Comply is being issued because of the following deficiencies: Deficiency: Stablize as needed. Must have temporary stabilizing if not being actively worked Corrective Action: Deficiency: Current site conditions are conducive to endangerment to downstream property and waterways Corrective Action: Deficiency: Denuded areas not active after14 says must be stabilized Corrective Action: Deficiency: Silt fence and stone entrances to work sites needed Corrective Action: Deficiency: Basin must be stabilized Corrective Action: Deficiency: Maintain clear and debris free inkets Corrective Action: Deficiency: Maintain controls to reduce sediment loss Corrective Action: Deficiency: Install wash facilities Corrective Action: Deficiency: Install proper washout Corrective Action: Deficiency: Waste container must be protected per program requirements Corrective Action: Unless subsequently amended in writing by this office, it is expected all of these corrective measures will be completed by. Reinspections as a result of this notice to verify corrective measures will incur a $170 fee for the first reinspection and $270 for each subsequent reinspection for single-family dwelling units (§ 17-207). Reinspections as a result of this notice to verify corrective measures will incur a $283 fee for the first reinspection and $383 for each subsequent reinspection for VESCP and VSMP permits (§ 17-207 and § 17-208). Failure to take effective corrective measures will result in a Stop Work Order upon reinspection. A 4% technology fee is due with each payment. County Inspector Name: Geoff Elsie County Inspector Phone Number: (434) 296-5832 orA1.4 Inspection Result: Notice to Comply Ljk GI'.�ti� COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP/VESCP PERMIT SITE INSPECTION REPORT Project Name: BERKMAR DRIVE APARTMENTS - VSMP project/WPO Number: WP0201900052 TMP: 03200000005400 DEQ Permit Number (if applicable): VAR100044 Project Operator: Umer Hasan with Breeden Construction Operator Telephone #: (804) 382-5645 Project Contact: UPTOWN VILLAGE LLC Contact Telephone #: Contact E-Mail: ericj@breedenconstruction.com Qualified Personnel (QP): Delton Banton with AG Dillard Inspector: Geoff Elsie Weather (Wet/Dry/Rain): Disturbed Acreage: Inspection Date & Time: 1/26/2022 Single -Family: Stage of Construction: Grading Re -Inspection: No COVERAGE & POSTING REQUIREMENTS Compliant? Reviewed during re -inspection? No Comments/Description 1 Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A) (9VAC25-870-31 0)(Al b. Co. Code §17-300, 17-302) 2 A copy of the notice of coverage letter is posted conspicuously near the main entrance of the construction activity? (CGP Part II.C) Notice of the location of the SWPPP is posted near the site's entrance, if 3 applicable, and information for public access is provided? (9VAC25-870- 54.G)(CGP Part II D.2 & 3) SWPPP AVAILABILITY AND CONTENTS Compliant? Reviewed during re -inspection? No Comments/Description 4 The SWPPP is on -site or made available during the inspection? (CGP Part II D.1 & 2)(9VAC25-870-54.G) 5 The SWPPP contains a signed copy of the registration statement? (CGP Part II A.1.a) 6 The SWPPP includes, upon receipt, a copy of the notice of coverage letter and the CGP? (CGP Part II A.1.b & c) The SWPPP includes a narrative description of the nature of the 7 construction activity, including the function of the project? (CGP Part II A.1.d) The SWPPP includes a legible site plan identifying all appropriate 8 measures and that includes the locations of support activities and the onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7)) Page 1 of 4 9 The SWPPP contains the name, phone number and qualifications of "Qualified Personnel" conducting inspections? (CGP Part II A.6) 10 The SWPPP contains an approved erosion and sediment control plan? (9VAC25-870-54.B)(CGP Part II.A.2) The SWPPP contains an approved stormwater management plan or an 11 existing construction site has a stormwater management plan that ensures compliance with the water quality and quantity requirements? (9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ II.0 ❑ 12 The SWPPP contains an adequate pollution prevention plan? (9VAC25- 870-54.D)(CGP Part II.A.4) The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of 13 concern, exceptional waters and the additional controls measures applicable? (9VAC 25-870-54.E)(CGP Part IIA.5 (a-b)) 14 Delegation of Authority is provided and signed in accordance with Part III K? (CGP Part 11 A.7) 15 The SWPPP is signed and dated in accordance with Part III K? (CGP Part 11 A.8) SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES Compliant? Reviewed during inspection? No Comments/Description Is the SWPPP being amended whenever there is a change in the design, 16 construction, operation, or maintenance that has a significant effect on the discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870- 54.G) Has the SWPPP been amended if inspections or investigations by the 17 operator's qualified personnel, or by local, state or federal officials find that existing control measures are ineffective in minimizing pollutants in discharges? (CGP Part II B(2))(9VAC25-870-54.G) 18 Contractor(s) that will implement and maintain each control measure are identified? (CGP Part 11 B(3))(9VAC25-870-54.G) Have there been updates to the SWPPP when any modifications to its implementation have occurred, including a record of dates when major 19 grading activities occur, construction activities temporarily or permanently cease on a portion of the site or stabilization measures are initiated? (CGP Part 11 B.4(a))(9VAC25-870-54.G) 20 Is there documentation in the SWPPP of replaced or modified controls? (CGP Part 11 B.4(b))(9VAC25-870-54.G) 21 Is the SWPPP updated to indicate areas that have reached final stabilization? (CGP Part 11 B.4(c))(9VAC25-870-54.G) Is the SWPPP updated to indicate properties that are no longer under the 22 legal control of the operator and the dates on which the operator no longer had legal control over each property? (CGP Part II B.4(d))(9VAC25-870- 54.G) Does the SWPPP identify the date of any prohibited discharges, the 23 volume released, actions taken to minimize the impact of the release and measures taken to prevent the recurrence of any prohibited discharge? (CGP Part 11 B.4(e-f)) (9VAC25-870-54.G) 24 mendments, modifications, or updates to the SWPPP are signed in accordance with Part III K? (CGP Part II B(5))(9VAC25-870-54.G) INSPECTIONS AND CORRECTIVE ACTIONS Compliant? Reviewed during inspection? No Comments/Description Inspections required by the SWPPP are conducted at the required 25 frequency, including a modified frequency for impaired water(s), approved TMDL(s), and exceptional waters when applicable? (CGP Part II F (2)) (CGP Part II A.5.b.3) 26 Inspection reports are completed and signed in accordance with CGP Part 11 F (3-4)? (CGP Part 11 F (3-4)) Page 2 of 4 27 Corrective actions are taken consistent with the requirements of the CGP? (CGP Part II G(1-2)) ESC AND SWM PLAN IMPLEMENTATION Compliant? Reviewed during inspection? Yes Comments/Description 28 Have stream buffers and steep slopes been protected as shown on the yes plan? Sequencing of the project is implemented in accordance with the yes 29 approved erosion and sediment control plan and stormwater management plans? (9VAC25-870-54.B and C) Have all denuded areas requiring temporary or permanent stabilization Denuded areas not active after14 says must be been stabilized, and have stabilization requirements for impaired waters, stabilized 30 approved TMDL(s), pollutants of concern and exceptional waters, when No applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25- 880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8)) (CGP II E(1-2)) Are soil stockpiles adequately stabilized with seeding and/or protected yes 31 with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II A.2(c)) (9VAC25-870-54.B) A permanent vegetative cover has been established that is uniform, N/A 32 mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Have sediment trapping facilities been constructed as the first step in land No Silt fence and stone entrances to work sites needed 33 disturbance activities? (9VAC 25-840-40.4) (CGP Part 11 A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Have earthen structures been stabilized immediately after installation? Yes 34 (9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.6) Are sediment traps and basins installed in accordance with MS-6 and the NO Basin must be stabilized 35 approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Are finished cut and fill slopes adequately stabilized to prevent or correct NO Stablize as needed. Must have temporary stabilizing if 36 excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1- not being actively worked 2)) (9VAC25-870-54.B) Is concentrated runoff down cut or fill slopes contained in an adequate yes 37 permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is adequate drainage or other protection provided for water seeps? N/A 38 (9VAC 25-840-40.9) (CGP Part 11 A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Do all operational storm sewer inlets have adequate inlet protection? No Maintain clear and debris free inkets 39 (9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870- 54.13) Are stormwater conveyance channels adequately stabilized with channel yes 40 lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B) Is in -stream construction conducted using measures to minimize channel N/A 41 damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are temporary stream crossings of non -erodible material installed where N/A 42 applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) 43 Is necessary restabilization of in -stream construction complete? (9VAC N/A 25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B) Are utility trench operations conducted and stabilized in accordance with N/A 44 MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are soil and mud kept off paved or public roads to minimize the transport No Maintain controls to reduce sediment loss 45 of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) 46 Have all temporary control structures that are no longer needed been N/A removed and disturbed soil resulting from their removal permanently Page 3 of 4 stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54. B ) Are properties and waterways downstream from development adequately Current site conditions are conducive to 47 protected from erosion, sediment and damage in accordance with the No endangerment to downstream property and standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840- waterways 40.19(a-n)) 48 Permanent control measures included in the SWPPP are in place? N/A (9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a)) POLLUTION PREVENTION PLAN IMPLEMENTATION Compliant? Reviewed during inspection? Yes Comments/Description Practices are in place to prevent and respond to leaks, spills, and other releases including (i) procedures for expeditiously stopping, containing, N/A 49 and cleaning up spills, leaks, and other releases; and (ii) procedures for reporting leaks, spills, and other releases in accordance with Part III G? (CGP Part II A.4.e(1))(9VAC25-870-56) Practices are in place to prevent the discharge of spilled and leaked fuels N/A 50 and chemicals from vehicle fueling and maintenance activities? (CGP Part II A.4.e(2))(9VAC25-870-56) Practices are in place to prevent the discharge of soaps, solvents, 51 detergents, and wash water from construction materials, including the N/A clean-up of stucco, paint, form release oils, and curing compounds? (CGP Part II A.4.e(3))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from vehicle No Install wash facilities 52 and equipment washing, wheel wash water, and other types of washing? (CGP Part II A.4.e(4))(9VAC25-870-56) 53 Concrete wash water is directed into a leak -proof container or leak -proof No Install proper washout settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56) Practices are in place to minimize the discharge of pollutants from No Waste container must be protected per program 54 storage, handling, and disposal of construction products, materials, and requirements wastes? (CGP Part II A.4.e(6))(9VAC25-870-56) Practices are in place to prevent the discharge of fuels, oils, and other No 55 petroleum products, hazardous or toxic wastes, and sanitary wastes? (CGP Part II A.4.e(7)(9VAC25-870-56) Practices are in place to minimize any other discharge from the potential N/A 56 pollutant -generating activities not addressed above, when applicable? (CGP Part II A.4.e(8))(9VAC25-870-56) Page 4 of 4 Construction General Permit Site Inspection Report Request for Correction Action Check Regulatory Citation/Legal Occur. Observation Recommended Corrective List # Requirement* Action 36 (9VAC 25-840-40.7) Stablize as needed. Must (CGP Part II A.2(c)) have temporary stabilizing if (CGP II E(1-2)) not being actively worked (9VAC25-870-54. B ) 47 (9VAC 25-840-40.19(a- Current site conditions are n)) conducive to endangerment to downstream property and waterways 30 (9VAC 25-840-40.1) Denuded areas not active (9VAC25-870-54.B) after14 says must be (9VAC25-880-60) (CGP stabilized Part I F.1(a)) (CGP Part 11 A.5.b(1)) (CGP Part 11 A.2.c (8)) (CGP 11 E(1-2)) 33 (9VAC 25-840-40.4) Silt fence and stone entrances (CGP Part 11 A.2(c)) to work sites needed (CGP 11 E(1-2)) (9VAC25-870-54. B ) 35 (9VAC 25-840-40.6) Basin must be stabilized (CGP Part 11 A.2.c (9)) (CGP Part 11 A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-54. B ) 39 (9VAC 25-840-40.10) Maintain clear and debris free (CGP Part 11 A.2(c)) inkets (CGP 11 E(1-2)) (9VAC25-870-54. B ) 45 (9VAC 25-840-40.17) Maintain controls to reduce (CGP Part 11 A.2(c)) sediment loss (CGP 11 E(1-2)) (9VAC25-870-54. B ) 52 (CGP Part 11 A.4.e(4)) Install wash facilities (9VAC25-870-56) 53 (CGP Part 11 A.4.e(5)) Install proper washout (9VAC25-870-56) 54 (CGP Part 11 A.4.e(6)) Waste container must be (9VAC25-870-56) protected per program requirements Recommended 2/3/2022 Corrective Action Deadline: Targeted Re- 2/3/2022 Inspection Date: Comments: Site needs to have all internal and adjoining roads cleaned and protected, proper wash facilities are to be installed and used. Install additional measures internally to prevent further sediment loss. Maintain all pollution prevention measures as required by the approved plan. Install barriers at the mobile home park that clearly mark no entrance. *Refers to applicable regulation found in the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 et seq.), Virginia Erosion and Sediment Control Regulations (9VAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880). Construction General Permit Site Inspection Photo Log Photos for Item 33 TimePhoto_20220126_114215.j pg.jpg Photo Description: Example of missing silt fence TimePhoto_20220126_114844.j pg.jpg 706.08KB MM 922KB lyvek .7yvek TV TYv k ''-k Tyvek T vek Tyuek TWi Ty,�w� yvek�W.. a�� Photo Description: Example of missing siltfence and need for a stone entrance ........ ......... ......... Photos for Item 35 TimePhoto_20220126_115250.jpg.jpg 603.19KB aw"219 AN] Photo Description: Stablize basin Photos for Item 39 Time Photo_20220126_114050.jpg.jpg 617.68KB _ •sue ._.r.•- ---Jan 26, 2022 11:40:50 AM 3333 Mineral Drive Earlysville ;le County Virginia Photo Description: Debris filled inlet protection Photos for Item 45 Time Photo_20220126_114237.jpg.jpg 1.18MB Photo Description: Example of internal road conditions TimePhoto_20220126_114615.jpg.jpg 781.88KB Photo Description: View of sediment into mobile home park Photos for Item 52 TimePhoto_20220126_114641.jpg.jpg 910.98KB Photo Description: No wash facilities but a posting stating the requirements Photos for Item 53 TimePhoto_20220126_114738.jpg.jpg 1.02MB Photo Description: Access to washout is limited Ti mePhoto_20220126_114816.jpg.j pg •v"G 1.29MB Photo Description: Masonry mixer not contained Photos for Item 54 TimePhoto_20220126_114423.jpg.jpg 476.64KB Photo Description: Example of the current conditions of the waste containers Photos for Item 55 Time Photo_20220126_114508.jpg.jpg 508.19KB Photo Description: Proximity of inlet to portable toilet is non conforming "e '4"'e x Q—I'uc ME----FW County Inspector COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road Charlottesville, Virginia 22902 434 296-5832 Inspection Date: 1/28/2022