November 19, 2021
Richard Nelson
Albemarle County Service Authority
168 Spotnap Road
Charlottesville, VA 22911
RE: Response Letter #1 for SDP2021-00065 Albemarle Business Campus: Block 1
Dear Richard,
Thank you for your review of the final site plan for Albemarle Business Campus: Block 1. This letter
contains responses to ACSA comments dated August 26, 2021.Our responses are as follows:
General
1. Provide fixture counts for each building.
RESPONSE: The fixture counts will be submitted separately once received from the architect.
2. Backflow prevention will be required for each building.
RESPONSE: Comment received. Please see note 14 under General Notes on the cover sheet.
Please let us know if you'd like a different note/language regarding backflow prevention.
Sheet C7
1. The fire line for the Clubhouse should have the dashed " F" line.
RESPONSE: Comment received.
2. Shift the hydrant in front of Bldg. 101 away from proposed light pole.
RESPONSE: Please see the revised site plan for the new location of this hydrant.
3. Refer to provided PDF for water main and service line alignment going to Bldgs. 102 and 103.
RESPONSE: Thank you for the PDF for reference. Please see the revised water infrastructure in
this location.
4. Remove 8x4 tee and extend water main to serve Bldg. 105.
RESPONSE: Comment received. Water main has been extended.
5. A blow off assembly will be needed at the end of the water main near Bldg. 105.
RESPONSE: A blow off assembly has been added, per the PDF.
6. As part of ACSA's CIP Program, it is desired to have a future interconnect between
Mountainwood Road and Country Green Road for a looped feed. Is the developer willing to grant
additional easement to the ROW for future interconnect project?
RESPONSE: We have brought this to the developer's attention and is currently being reviewed.
912 E. High St. Charlottesville, VA 22902 1434.227.5140 1 shimp-engineering.com
7. Relocate M113A outside of the sidewalk.
RESPONSE: Str. 3A has been moved outside of sidewalk area.
Sheet C15
1. Include the following details: TD-3, TD-7, TD-12, TD-13, TD-14, TD-15, TD-19.
RESPONSE: These details have been added to C 17.
If you have any questions or concerns about these revisions, please feel free to contact me at
Rachel nkshimp-en ing eering com or by phone at 434-227-5140.
Regards,
Rachel Moon
Shimp Engineering, P.C.