HomeMy WebLinkAboutWPO202200004 Correspondence 2022-02-07From:
Frank Pohl
To:
Greg Harper; Jack Kelsev
Cc:
Stavros Calos
Subject
RE: The Square Parking
Date:
Friday, March 17, 2017 1:41:14 PM
Jack and I talked this morning. Considering the area is already impervious, this can fall under a
maintenance exemption (repaving of existing or paving of impervious gravel) so long as there is not
an increase in impervious area and the use is the same (parking and travel lane). A VESCP is still
required for erosion and sediment control considering the land disturbance will be greater than
10,000 sf.
Let me know if you have any questions or concerns.
Frank V. Pohl, PE, CFM
County Engineer
County of Albemarle
(434) 296-5832 Ext. 7914
From: Greg Harper
Sent: Friday, March 17, 2017 8:41 AM
To: Frank Pohl <fpohl@albemarle.org>; Jack Kelsey <JKELSEY@albemarle.org>
Cc: Stavros Calos <scalos@albemarle.org>
Subject: RE: The Square Parking
The Crozet wetland was built with the intent to serve projects such as this. However, we never
formalized the wetland as a pro-rata basin. Stavros was recently advised by a DEQ staff that we
could set it up as a nutrient bank instead of a pro -rate system. We'd be happy to move this forward
on this ASAP but I'm not sure what the timing would be.
From: Frank Pohl
Sent: Thursday, March 16, 2017 6:02 PM
To: Jack Kelsey <JKELSEY2Dalbemarle.ore>
Cc: Greg Harper<gharoer2Dalbemarle.org>
Subject: RE: The Square Parking
Jack,
Tomorrow is Friday... LOL. I think we should talk this through. I have a 10 am site visit, do you want
to discuss at say 9 am?
Greg, do you know if that basin/wetland project has any additional capacity to provide treatment for
future County projects?
Frank
Frank V. Pohl, PE, CFMI
County Engineer
County of Albemarle
(434) 296-5832 Ext. 7914
From: Jack Kelsey
Sent: Thursday, March 16, 2017 4:45 PM
To: Frank Pohl <foohl(a)albemarle.org>
Subject: The Square Parking
Frank,
By the end of Friday I need to determine an order of magnitude cost for improvements to The
Square parking and sidewalks in front of the buildings. So I'll need to know if and how the new
storm water management regs would be applied; and if the new Crozet SWM basin we built would
address any requirements from the new regs. Total disturbed area would be about 20,000 sf.
Any assistance would be appreciated.
Jack ll. Eelser. PE
Ihnspurtatiun En rineer
hrilities S Duranmental Senires
Prajertllanauement Ilisisian ht 3,376