HomeMy WebLinkAboutSUB202100128 Review Comments Road Plan and Comps. 2022-02-11 (2)qoe atg 401 McIntire Road, North Wing Charlottesville, VA 22902-4579 County of Albemarle Telephone:434-296-5832 m COMMUNITY DEVELOPMENT DEPARTMENT WWW.ALBEMARLE.ORG Road and Drainage Plan Review Project title: Southwood Redevelopment - Village 2 Road Plan Project file number: SUB202100128 Plan preparer: Timmons Group Clint Shifflett [clint.shifflett@timmons.com] Owner or rep.: Charlottesville Habitat for Humanity Andrew Vinisky[avinisky@cvillehabitat.org] Plan received date: 26 July 2021 (Rev. 1) 6 December 2021 Date of comments: 23 September 2021 (Rev. 1) 11 February 2022 Reviewer: Matt Wentland Clint, We have reviewed the plans and have the following comments: Engineering 1. Show the Forest & Open Space easement from the Village 1 plans. No improvements are allowed in this area (including stone dust trails) and any grading will require DEQ BMP Spec. 4 Soil Amendments to be used. (Rev. 1) Comment partially addressed. It appears some of the hatching may not be showing up. 2. Private drainage easements should be a minimum of 10' wide. The easement width calculation from the Design Standards Manual should still be used for pipes not at minimum depth. (Rev. 1) Comment addressed. 3. Drainage easements that are not a constant width should be labelled as variable width. Some of the other easement widths appear to be incorrectly labelled (such as the 10' label on the easement for pipe 101). (Rev. 1) Comment addressed. Revision 1 Comments 4. The yard drains behind the cul-de-sac lots are not showing up on the plans. Planning -Rebecca Ragsdale Planning comments will be forwarded when they are received. VDOT VDOT comments are attached to this email. ACSA - Richard Nelson Engineering Review Comments Page 2 of 3 Submit a copy of the utility plans to ACSA ATTN: Alex Morrison RWSA sewer capacity certification will be required. Please include the following information; proposed daily sewer flow, proposed construction start, projected buildout completion. GIS and Fire Rescue had no objection. Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Process: After approval, plans will need be bonded. The bonding process begins when the plan is approved, and the applicant submits a bond estimate request form and fee to the Department of Community Development. A plan reviewer will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted to the County, who will record the agreement. After bonding and agreements are complete, county staff enters project information in a DEQ database for state application processing, if a DEQ permit is required. DEQ reviews the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter, which must be posted at the construction site. After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Applicants must complete the request for a pre -construction conference form and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre - construction conference, should everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that work may begin. Engineering Review Comments Page 3 of 3 County forms can be found on the county website forms center under engineering; https://www.al bemarle.org/government/com munity-development/apply-for/engineering-applications If you have any questions or concerns, please contact me either by email (mwentland@albemarle.org) or by phone at 434-296-5832 ext. 3458. Sincerely, Matt Wentland, P.E. Civil Engineer II File: SUB202100128 Southwood Village 2 Road Plan review comments revl 02-11-22.docx