HomeMy WebLinkAboutSDP200400030 Review Comments 2004-06-17 C! 7/45/o
gay oo AL
friRGjNP
COUNTY OF ALBEMARLE
Department of Planning&Community Development
401 McIntire Road,Room 218
Charlottesville,Virginia 22902-4596
(434)296-5823 Ext.3385
Fax(434)972-4012
MEMORANDUM (FAX)
TO: Dex Sanders (540-829-2591)
FROM: Stephen B. Waller AICP, Senior Planner
DATE: June 17, 2004
RE: SDP 04-030 Albemarle Baptist Church Final Site Plan
The Albemarle County Department of Planning and Community Development will approve the
above-mentioned final site plan when the following items have been addressed satisfactorily.
Please note that the following conditions are those that have been identified at this time.
Additional conditions may be added or eliminated based on further review. [Where appropriate,
comments are preceded by the applicable reference.]:
[SP 01-047, #1] Administrative approval of all conditions of the Architectural Review
Board's Certificate of Appropriateness.
2 [SP 01-047, #4] Virginia Department of Health approval of the proposed well and septic
systems.
3. [SP 01-047, #8] Please provide a note on the cover sheet to clarify that this proposal is
only being reviewed for the improvements identified as part of Phase I. Future phases
will require amendment(s) showing alterations to the limits of clearing, as well as
revisions to erosion and sediment control plans, landscaping and other relevant aspects of
the current plan.
[SP 01-047, #9] The Virginia Department of Transportation must grant approval of the
entrance and any other improvement related to the public road rights-of-way. In
comparing the revised plan with the original proposal, it appears that the trees addressed
in VDOT comments, dated April 5, 2004,have not been adjusted to address concerns for
site distance.
5. [32.7.9.8.c(3)] Show the locations of any ground-based HVAC equipment or any other
similar utilities. Please note that such items are considered to be objectionable feature
that must be screened from adjacent rural and residential properties and public roads.
Albemarle Baptist Final
June 17, 2004
Page 2
Mylars will not be accepted for signatures until all departments have granted final tentative
approval. In accordance with Section 32.6.1,mylar copies of the site plan must be sealed, signed
and dated by an architect,professional engineer, land surveyor, or certified landscape architect
when submitted for final approval.
Please contact me at your earliest convenience if you have any questions or require further
assistance.
Copy: File SDP 04-030