HomeMy WebLinkAboutSDP202200012 Review Comments Initial Site Plan 2022-04-27��oFAts Ben Holt
�r COUriL Of Albemarle Senior Planner, Planning
y bholt(cDalbemarle.org
T.. Community Development Department Telephone: (434) 296-5832 ext. 3443
Memorandum
To: Michael Chandler, michael(o)shimo-en¢ineerine.com ; Justin Shimp, iustin0shimo-en¢ineerine.com
Date: April 27, 2022
Re: SDP202200012 River's Edge — Initial Site Plan — Review Comments
All comments in the attached letter must be addressed prior to Final Site Plan approval: [Each comment is preceded by
the applicable reference, which is to the Subdivision/Zoning Ordinances unless otherwise specified].
Albemarle County Planning Services (Planner) — Ben Holt, bholt(ccbalbemarle.org
1. [32.4.2.1.F] - County records show that the $448.00 notification fee has not been paid. This fee must be paid prior
to approval of the initial site plan.
2. [32.5.2.A] — General info. Under Zoning notes, indicate that property includes flood hazard overlay.
3. [ZMA2018-18] — Show/label the location of the sanitary pump station.
4. [32.5.2.G] — Indicate setback of pump station from streams/waterways.
5. [32.5.2.H] — Show FEMA floodplain limits and GIS stream buffer on sheets C4, 5, 6 and C11, 12 and 13.
6. [32.5.2.N] — Existing and proposed improvements. Indicate location of trash containers and/or dumpster pads.
Please contact Ben Holt in the Planning Division by using bholt(cb_albemarle.org or 434-296-5832 ext. 3443 for further
information.
Comments from Other Reviewers:
Albemarle County Engineering Division — John Anderson, landerson2(aDalbemarle.org — requested changes, see
attached.
Albemarle County E911 Services — Andy Slack, aslack(cDalbemarle.org — requested changes, comments attached.
Albemarle County Building Inspections — Betty Slough, bslough(7a.albemarle.org — requested changes, see attached.
Albemarle County Department of Fire & Rescue — Howard Lagomarsino, hlagomarsino(aDalbemarle.org — requested
changes, see attached.
Virginia Department of Transportation (VDOT) — John Wilson, John.c.wilson(aDvdot.virginia.gov - requested changes,
see attached.
Albemarle County Service Authority (ACSA) — Richard Nelson, rnelson(aDserviceauthority.org requested changes, see
attached.
Rivanna Water & Sewer Authority (RWSA) — Dyon Vega, dvega(aDrivanna.org — requested changes, see attached.
Dept. of Conservation & Recreation (DCR) — Justin Deel, lustin.deel(aDdcr.virginia.gov — comments attached.
WWW.ALBEMARLE.ORG
401 McIntire Road, North Wing, I Charlottesville, VA 22902-4579
Albemarle County Parks & Recreation — Tim Paladino, tpadalino(cDalbemarle.org — requested changes, see attached.
Albemarle County Architectural Review Board (ARB) — Khris Taggart, ktaggartt?a.albemarle.org — see action letter
attached.
Vi9'i'1'JA_14:3 :I u1_1 R 4 *01:ih
401 McIntire Road, North Wing, I Charlottesville, VA 22902-4579
qoe at, 401 McIntire Road, North Wing
Charlottesville, VA 22902-4579
�r County of Albemarle Telephone: 434-296-5832
i.
COMMUNITY DEVELOPMENT DEPARTMENT WWW.ALBEMARLE.ORG
Site Plan review
Project title:
River's Edge Initial Site Plan
Project file number:
SDP202200012
Plan prepares
Shimp Engineering, 912 E. High St., Charlottesville, VA 22902
Michael Chandler, michael(i�shimp-engineering.com
Owner or rep.:
Rivers Edge Holdings, LLC / P.O. Box 6458, Charlottesville, VA 22906-6458
tomatweeksAgmai1. com
Plan received date:
14 Mar 2022
Date of comments:
1 Apr 2022
Plan Coordinator:
Ben Holt
Reviewer:
John Anderson
Engineering has reviewed the initial site plan and offers these review comments for Final Site Plan approval.
SDP2022-00012
1. CIO: Recommend label trail features presently not labeled.
2. C11,C12,C13
a. Show Aabel steep slopes. Additional comments possible, once steep slopes overlay shown.
b. (CU3 Ensure Engineered level spreader meets design criteria for downslope Max. grade /Min.
slope length listed in VA DEQ Storrnwater Design Specification No. 2, Table 2.2. Alternatively,
replace ELS with detention that attenuates concentrated storm runoff release at this discharge
point.
c. 14 Apr 2020 ZMA Application Plan, sheet 20, Note 2 states: `If permitted under applicable
stormwater regulations, stormwater discharge may be to level spreader or similar facility to open
space. If conditions do not permit such discharge, stormwater may be conveyed to the stream or
river in an adequate channel (shown in gray) with slope stabilization as applicable, where stream
bank disturbance occurs.' Conditions likely do not permit ELS; with WPO plan, ensure proposed
drainage /SWM meet VDOT /BMP Clearinghouse Min. standards, design criteria, etc. A possible
alternative to ELS is detention pipe along site access /travel way, with gradual release of detained
flow via storm pipe down /across preserved slopes to stream, or river. Also, item 2.b. above.
d. Submit WPO Application /plan at earliest convenience. WPO plan approval is required for final
site plan approval.
e. SWM facility easement (plat /deed) recordation is required prior to WPO plan approval.
f. Provide private access easement to connect U.S. Rt. 29 with residential development.
3. C4-05-C6(andCll-C12-C13)
a. Show and label FEMA mapped floodplain.
b. Show and label GIS stream buffer overlay.
4. C12
a. Retaining walls >3-ft. ht. require a building permit and must include safety railing.
b. Retaining walls >4-ft ht. require PE -sealed geotechnical plans.
c. Proposed retaining walls along site access require VDOT GR-2 guardrail (unrecoverable slopes,
vertical drop), provide GR-2 and ensure retaining wall (PE -seal design), roadway construction,
and GR-2 installation all conform with VDOT standards for guardrail type (web/post), rail post
spacing, terminal treatment, horizontal clearance to back -slope, etc.
d. Submit retaining wall PE -sealed plans that show GR-2 to Engineering prior to /as condition of
final site plan approval.
Engineering Review Comments
Page 2 of 3
5. C8, C9, C10
a. Label sanitary pump station with wet well.
b. Provide sight distance profile south/left at U.S. Rt. 29.
c. Provide Name for site access /travelway for a-911 purposes.
d. Obtain VDOT Land Use permit for work within U.S. Rt. 29 RW.
e. Show proposed sanitary connection with Ex. RWSA /ACSA facility at U.S. 29.
f. If road bore required beneath U.S. Rt. 29 for utility purposes, provide notes, details, schematics,
graphics, Notice to Contractor etc. concerning safe utility operation within VDOT RW, or as
required by ACSA /RWSA to meet utility /Agency requirements.
g. Coordinate all aspects of site /entrance work at U.S. Rt. 29 (within RW) with VDOT. A MOT
may be required.
h. Provide posted /advisory speed limit sign/s on site access.
i. Provide `No parking' sign/s at intervals along site access.
j. Recommend `Yield' signs to establish thru movement.
k. Design site entrance culvert pipe to pass the 25-yr event.
6. C11,C12,C13
a. Show Aabel ACSA sanitary sewer /water line easements.
b. Label all retaining walls. Assign Wall identifiers (letter, #) for ease of reference. Provide
TWBW elevations.
c. (Cl 1) Provide suitable ditch runout for 6' travelway ditch at U.S. Rt. 29. Design must avoid and
limit potential erosion at U.S. Rt. 29, or other locations. Further, this point discharge must meet
state stormwater management (stormwater quantity) regulations.
d. (C12) Engineering prefers design abandon ditch to Rt. 29, and instead, more nearly approximate
design shown on sheets 20,21 of 14 Apr 2020 ZMA Application plan, which shows no
conveyance to U.S. Rt. 29 RW.
e. (C13) Revise proposed 340 LF 108" CMP underground detention system which presents liability,
with few if any positive offsets (perhaps less initial expense). Unless rock precludes multiple
smaller systems, installation of proposed 340 LF 9' DIA system will require significant SWM
facility easement width (Ref. ACDSM Easement diagram, p. 15), which requires, for a system this
size, at least 37' wide SWM easement (assume 1' bedding, 3' cover). In the future, when the
system is replaced, there will be no vehicular access to the entire lower parking area that serves
nearly half the Rivers Edge development. Also, should there be performance issues with a single
detention system, there is no backup to treat a portion of developed runoff. If the proposed single
system is bypassed, it is possible the entire volume of impervious area runoff could route across
preserved steep slopes. ZMA Application plan sheet 19 presents a system approximately half the
length proposed. Propose alternate detention that maintains partial access to lower parking lot
should future circumstance warrant excavation of parking areas to repair or replace the UG
detention system. Consider alternative SWM design that locates multiple detention practices
nearer to residences and upper tier parking (for example, 4 — 85 LF systems would provide
identical detention capacity without compromising access to this degree, and would permit at least
partial water quantity treatment should incident affect one of several systems. As it is, incident
affecting a single system may prevent or compromise storm detention, entirely. Engineering
disapproves current proposed SWM design on access /maintenance basis, as well as scale of
departure from ZMA Application plan. With WPO plan, provide bypass of any SWM facility
while mitigating impact of bypass flow to critical resources, especially preserved steep slopes.
f. Provide CG-6 or CG-7 along site access/travel way wherever storm runoff concentrates against
curb. If ZMA approval explicitly exempts site from curb -gutter requirements at Ch. 14 /18, please
direct Engineering to exemption. Otherwise, please see 18-32-7.2.2.a. / 14-412.B., provide curb
with gutter.[Note: sheets 20-22 of ZMA Application plan show inlet design along site access.]
g. Provide PE -sealed sanitary effluent pump station design, incl. pump curves, pump type, wet well
design, alarms, remote sensing, etc. as provided with documents or during presentation to PC or
BOS in 2020, or in /with ZMA documents, etc. Recommend furnish evidence of coordination or
approval with or from DEQ, relative to sanitary pump station design. Albemarle will not review
Engineering Review Comments
Page 3 of 3
or approve pump station design. ACSA is unlikely to review or approve pump station design. It
is incumbent upon developer (per approved ZMA) to obtain approvals needed to construct the
pump station, to ensure remote sensing system is operational, and that station will be maintained.
7. C 15: Show proposed storm lines and utilities (sanitary sewer/water) in light line -type on this sheet, to
highlight potential conflicts. For example, proposed storm lines are proposed to cross at least 5 parking
islands proposed to be planted with large canopy species. Revise storm pipe locations to avoid landscape
conflicts.
8. Ensure steep slopes disturbance is consistent with sheet 23 14 Apr 2020, ZMA Application, and does not
exceed 39,100 sq. ft. approved with ZMA. Show /label Area (ft) of Preserved Steep Slope impact with
WPO and ESP.
9. Ensure stream buffer disturbance is consistent with sheet 24 14 Apr 2020, ZMA Application, and does not
exceed—23,000 sq. ft. approved with ZMA. Show Aabel Area (ftz) of stream buffer impact with WPO and
ESP.
10. C 14: Public drainage easement (downstream of SWM) should not propose storm pipe beneath /through a
retaining wall. If unavoidable, provide concrete headwall Aintel details with PE -seal, similar to Versa-Lok
Tm standard. Comment does not anticipate approval of public drainage easement with pipe penetration
beneath or through a retaining wall, a configuration to avoid.
11. C 16: Include Site Access (travelway) section with stone /pavement depths, see River's Edge Street Section,
sheet 28 of ZMA Application plan. Provide site access pavement design based on full buildout ADT.
12. Provide VDOT LD-229 (storm drain design computations) and LD-204 (stormwater inlet computations).
13. Provide complete storm profiles with labels, rim ANV elevations, slope, DIA, compaction notes, etc.
14. Provide road profile generally consistent with ZMA Application plan ZMA201800018, sheets 17, 18
(revised 14 April 2020) with smooth vertical curves, K-sag /crest values (sufficient sight distance), etc.
Please feel free to call if any questions: 434.296-5832 -x3069
Thank you
J. Anderson
SDP202200012 River's Edge ISP 040122.docx
4 OP A�qF
County of Albemarle
IlI GEOGRAPHIC DATA SERVICES OFFICE
COMMUNITY DEVELOPMENT DEPARTMENT
r �2G1N"'
PLAN REVIEW COMMENTS - E911
APPLICATION#: SDP202200012
TMP: 03200-00-00-005A1
DATE: 4/8/22
Andrew Slack
aslack@albemarle.org
tel: 434-296-5832 ext. 3384
fax: 434-972-4126
We recommend providing three (3) candidate names for each road to our office for
review, in case your first choices are not acceptable.
Before final plans are submitted, please add 4 road names to the plans for the new travel ways
and locations of proposed structures. The existing road names, Rivers Edge Road and Rivers
Edge Lane can be used again, however there will need to be new road names for the 2 additional
road ways that serve the new proposed structures. For example. Rivers Edge Road could be
used as the main entrance accessing Route 29. Rivers Edge Lane could be used for proposed
structures 1 - 10. A third road name will need to be created for structures it - 18 and a fourth
road name will need to be created for proposed structures 19 - 34.
A PDF version of the Ordinance and Manual can be found here:
https://Risweb.albemarle.orR/Risdata/Road Namine and Property Numberin¢ Ordinance and Manual.odf
Please consult the County's Road Name Index to check your road names prior to submittal. The
Index can be found here: https://Ifweb.albemarle.org/Forms/RoadName]ndex
Parcel and mapping information can be found here: https://Risweb.albemarle.org/gpv 51/Viewer.aspx
If you should have any questions, please do not hesitate to contact our office.
WWW.ALBEMARLE.ORG
401 McIntire Road, Suite 228 1 Charlottesville, VA 22902-4596
SDP2022-12 Rivers Edge— Initial Site Plan
Comments: CDD Inspections— Betty Slough
bslouah@albemarle.ore
04-11-2022
Add the following note to the general notes page:
• Retaining walls greater than 3 feet in height require a separate building permit. Walls exceeding
4 feet in height require a stamped engineered design also. Walls require inspections as outlined
in the USBC.
• Accessible parking spaces, access isles, and accessible route shall be installed in accordance with
ICC ANSI A117.1-09 and the 2018 Virginia Construction Code.
• Where the flood level rims of plumbing fixtures are below the elevation of the manhole cover of
the next upstream manhole in the public sewer, the fixtures shall be protected by a backwater
valve installed in the building drain, branch of the building drain or horizontal branch serving
such fixtures. Plumbing fixtures having flood level rims above the elevation of the manhole
cover of the next upstream manhole in the public sewer shall not discharge through a backwater
valve.
• All roof drains shall discharge in a manner not to cause a public nuisance and not over sidewalks.
• Buildings or structures built before January 1, 1985 must have an asbestos survey performed in
order to apply for a demolition permit.
• Asbestos removal permits are required if positive for such from Albemarle County and VDOLL
Contact VDOLI for their additional requirements and permits for demolition projects at 540-562-
3580 x131.
• All water, sewer and fire lines require NEW inspection and testing procedures. The ACSA
performs any testing and inspections of the public sewer and water main(s).
Additional Notes:
• The Albemarle County Building Inspections Department(ACBID) does a visual inspection and
witnesses the testing of the building drain, water service pipe and the sprinkler lead-in
connection.
• The developer/contractor is responsible to retain a Special Inspector as outlined in the updated
Albemarle County Policy for Site Utilities to perform the visual inspection and testing of all
utilities not covered by the ACSA or ACBID. This includes building sewers, water and fire line
branches between the main and the meter(s)/building(s).
• The Special Inspector's report must be submitted and approved by the Albemarle County
Engineering Department prior to a Certificate of Occupancy being issued.
• Sidewalks are not shown from the parking areas to each building. Accessible routes are not
shown.
SDP2022-12 Rivers Edge— Initial Site Plan
Comments: Albemarle Co Fire & Rescue — Howard Lagomarsino
hlaeomarsino@albemarle.org
4-13-2022
1) Please clarify the heights of the buildings, especially the three story buildings to ensure they conform
to the following standard: fire aparatus access roads are rquired to provide access to within 150 ft of all
side so fthe ground level from the road and to have a minimumk travel way width of 20 ft if the height of
the building is 30 feet or less and 26 feet if the height of the building is over 30 ft.
2) Fire hydrants are required along the entrance road with a minimum spacing of 1000 ft to address
transportion emergencies on the entrance road.
3) Where there are buildings, the number of hydrants required depend on the calculated needed fire
flow. Please place a note on the plan indicating the needed fire flow, so the plan can be evaluated top
ensure the proper number of hydrants and the needed fire flow are met
4) Fire Hydrant spacing for the buildings is based on the needed fire flow calculation. Please place a note
on the plan indicating the needed fire flow so the plan can be evaluated for proper spacing (generally,
the least onerous spacing is every 500 ft with no building more than 250 ft from a hydrant - as the
needed fire flow rises, spacing decreases)
5) Please provide a note on the plan toi indicate the available fire flow from the ACSW
6) If the buildings are required to have sprinklers installed, then the FDC needs to be properly labeled on
the plan, labeled with appropriate signage and have a hydrant within 100 feet of the connection and
arranged so that the travel way is not obstrcuted when in use inn cnjunction with the hydrant.
7) During construction and demolition, the following fire prevention steps are required, so please note
them on the plan:
a) Smoking shall be prohibited in areas where smoking makes conditions such as to make smoking a
hazard and these areas shall be designated with no smoking signs per Virginia Statewide Fire Prevention
Code.
b) Areas where smoking can occur, shall have appropriate receptacles for discarded smoking
materials per Virginia Statewide Fire Prevention Code
c) Per the Virginia Statewide Fire Prevention Code, vehicular access for firefighting shall be provided
at all construction and demolition sites, provide access to within 100 ft. of temporary or permanent fire
department connections, and have no overhead wiring or other overhead obstructions lower than 13 ft.
6 inches; this access may be via permanent or temporary road, but shall be capable of supporting fire
apparatus in all weather conditions.
d) Contractor shall ensure the street numbers are always plainly visible from the frontage street
during construction per the Virginia Statewide Fire Code
e) An approved water supply for firefighting operations shall be in place and available as soon as
combustible materials arrive on site.
f) Waste and combustible debris shall be removed from the building at the end of each day and
disposed of in accordance with the Virginia Statewide Fire Code
g) Fire extinguishers shall be provided, with not less than one approved fire extinguisher at each
stairwell, on all floor levels where combustible materials have accumulated, in every storage and
construction shed and in areas of special; hazards, such as where flammable and combustible liquids are
stored or used, in accordance with the Virginia Statewide Fire Code
h) Operations involving the use of cutting and welding shall comply with the Virginia Statewide Fire
Prevention Code and shall require a permit from the Albemarle County Fire Marshal's Office
COMMONWEALTH of VIRGINIA
DEPARTMENT OF TRANSPORTATION
Stephen C. Brich, P.E. 1401 East Broad Street
Commissioner Richmond, Virginia 23219
March 30, 2022
County of Albemarle
Department of Community Development
401 McIntire Road
Charlottesville, VA 22902
Attn: Ben Holt
Re: River's Edge — Initial Site Plan
SDP-2022-00012
Review # 1
Dear Mr. Holt:
(804)786,2701
Fax: (804) 786,2940
The Department of Transportation, Charlottesville Residency Transportation and Land Use
Section, has reviewed the above referenced plan as submitted by Shimp Engineering, dated 01
March 2022, and offers the following comments:
Land Use
1. Please label if access road will be public or private.
2. Please show route 29 existing right of way on plans.
3. Please refer to the VDOT Road Design Manual, appendix F, access management
design standards for entrances and intersections. Please provide geometry at entrance;
Minimum width for commercial entrances needs to be 30 ft., or greater.
4. Please refer to VDOT's Road Design Manual for design criteria for right turn
lane/taper, appendix F-pg., F-119, commercial entrance designs along highways with
shoulders. Please provide geometry for right turn lane\taper on plans.
5. Please provide a 12'ft., offset on right side of entrance from end of radii to edge of
pavement.
6. Please provide a minimum of 48'11., or greater taper on right side of entrance, from
end of radii, to edge of pavement.
7. Right turn lane needs to be 12' ft., for the first 100'ft., then start your transition for
the next 100' ft., to tie into the edge of pavement.
8. Please show existing section of guardrail on plans.
9. Guardrail will need to be replaced with construction of taper, please install upgraded/
current guardrail in accordance with VDOT's Road and Bridge standards, and
specifications, and please show on plans.
10. Please show mill and overlay on plans in accordance with WP-2 and show limits of
mill and overlay.
VirginiaDOT.org
WE KEEP VIRGINIA MOVING
11. The mill and overlay will require work to the centerline, so flagging operations will
be necessary. Please provide MOT plan in Accordance with Virginia Work Area
Protection Manual.
12. Intersection sight distance needs to be based on the design speed of 60mph, 665ft'.
13. Please provide intersection sight distance profile, sight line triangles on plans.
14. Please provide drainage\ditchline calculations.
15. Will culvert pipe be needed for entrance?
16. Note that the final site plan must show conformance with the VDOT Road Design
Manual Appendices B (1) and F, as well as any other applicable standards,
regulations or other requirements.
Please provide two copies of the revised plan along with a comment response letter. If further
information is desired, please contact Willis C. Bedsaul at 434-422-9866.
A VDOT Land Use Permit will be required prior to any work within the right-of-way. The
owner/developer must contact the Charlottesville Residency Transportation and Land Use
Section at (434) 422-9399 for information pertaining to this process.
If further information is desired, please contact me at 434-422-9782.
Sincerely,
John Wilson, P.E.
Assistant Resident Engineer -Land Use
Charlottesville Residency
VirginiaDOT.org
WE KEEP VIRGINIA MOVING
From: Richard Nelson
TO: Ben Hol
Subject: SDP202200012 River's Edge — Initial Site Plan - Digital
Date: Friday, April S, 2022 5:03:17 PM
CAUTION: This message originated outside the County of Albemarle email system. DO
NOT CLICK on links or open attachments unless you are sure the content is safe.
Ben,
I recommend SDP202200012 River's Edge— Initial Site Plan — Digital for approval with the following
conditions:
Submit water/sewer construction drawings to ACSA for review.
Provide fixture counts to determine meter size.
RWSA to approve water main connection.
RWSA water main connection is not in the correct location.
Existing ACSA sewer manhole does not appear to be in the right location. The sewer manhole should
be further to the east.
Provide retaining wall detail showing any geofabric along entrance road.
Relocate portion of water main into travel way outside of parking spaces.
Existing water service line will need to be called to be abandoned.
DEQ approval will be required for pump station.
This project falls within the Special Rate District South Zone. Draft connection fees can be provided
upon request.
Thanks,
Richard Nelson
Civil Engineer
Albemarle County Service Authority
168 Spotnap Road
Charlottesville, Virginia 22911
(434) 977-4511
From:
Dyon Vena
To:
Ben Holt
Cc:
devreview@rivanna.oro; Richard Nelson
subject:
RE: TRANSMITTAL - SDP2022-12 Rivers Edge - Initial Site Plan
Date:
Friday, April 1, 2022 3:30:37 PM
Attachments:
ImaneDO1. pro
River"s Fdge Comments.msn
NRW PHASF2 04A 33.ndf
RWSA General Notes.doc
CAUTION: This message originated outside the County of Albemarle email system. DO
NOT CLICK on links or open attachments unless you are sure the content is safe.
RWSA has reviewed River's Edge Initial Site plan dated 3/1/22 by Shimp Engineering and has the
following comments.
General Comments:
1. 1 have attached our previous comments.
2. Include RWSA general notes (attached).
Sheet C11:
1. It appears the RWSA 12" Cl waterline has been incorrectly surveyed. I have attached the as-
builts, but locations should be verified by field location and test pit.
2. Please include a note to test pit before the jack and bore for tap on WL.
3. Please include RWSA tapping notes.
Let me know if you have any questions.
Thank you,
Dyon Vega
Civil Engineer
RIVANNA
WATER 6 SEWERAUTHORITY
Rivanna Water & Sewer Authority
(434) 977-2970, East. 170
695 Moores Creek Lane
Charlottesville, VA 22902
www.rivanna.ore
Please use our DevReviewiTE)Rivanna.org email for all development review related Items, Thank
you.
From: Dvan Vega
To: Christopher Perez
Cc: vrort@rivanna.om; Richard Nelson
Subject: River"s Edge Comments
Attachments: imaae0m.ona
NRW PHASE2 04A 33.pdf
Chris,
RWSA has reviewed the River's Edge initial site plan dated 21/7/2020 and has the following
comments:
Sheet 8:
1. Please show size of connection to RWSA 12" Cl waterline.
2. Waterline is shown on wrong side of road. I have attached a drawing showing where the
waterline should appear.
3. Coordinate WL connection with RWSA and include RWSA connection notes below.
4. There is likely a gas line in close proximity with the 12" Cl WL.
Wet Tap on RWSA Waterline
Add the following note to the utility plan sheet that shows the proposed connection:
"Contractor shall coordinate with RWSA and ACSA for the connection to the existing RWSA 12" waterline.
Contractor shall use due diligence to protect the RWSA 12" waterline during construction and tapping.
Contractor shall verify the horizontal and vertical location, the outside diameter and the pipe material of
the 12" waterline prior to ordering the tapping sleeve. RWSA shall be contacted 3 business days in advance
of the test pit and shall be present during the test pit. The tapping sleeve shall be approved by RWSA prior
to being ordered. The tapping contractor shall be approved by RWSA prior to the tap.
A minimum of 3 business days notice shall be given prior to installation of the tapping sleeve. The XX"xXX"
tapping sleeve and valve shall be installed plumb. Following the placement and testing of the XX"xXX"
tapping sleeve and valve, a concrete pad and thrust block shall be placed under and behind the tapping
sleeve and allowed to set prior to making the tap.
Add the following note to the waterline profile sheet that shows the proposed connection:
"A minimum of 3 business days notice shall be given to RWSA prior to installation of the tapping sleeve.
Please see the note on sheet "XX- reference utility plan sheet" for more information regarding the
connection to the RWSA waterline'
Let me know if you have any questions.
Thanks,
Dyon Vega
Civil Engineer
escription: rwsa symbol
❑®
Rivanna Water & Sewer Authority
(434) 977-2970, Ext. 170
695 Moores Creek Lane
Charlottesville, VA 22902
www.rivanna.org
Rivanna Water & Sewer Authority (RWSA)
General Water & Sanitary Sewer Notes
Last Revised: April 2016
1. All materials and methods of construction shall comply with the latest version of the General
Water and Sewer Design and Construction Standards — Version 1.0, adopted in December 2015,
except as modified below or modified in special notes.
2. RWSA shall approve all construction materials and methods of construction. A preconstruction
conference shall be held with RWSA prior to the start of any work.
3. The contractor shall be responsible for notifying Miss Utility (1-800-552-7001).
4. RWSA Engineer (Victoria Fort at (434) 977-2970 ext. 205) shall be notified three business days
prior to the start of construction.
5. All work is subject to inspection by RWSA staff. No tie-ins to the existing system shall be made
without coordination with and the presence of RWSA staff. No work shall be conducted on
RWSA facilities on weekends or holidays without special written permission from RWSA.
6. For sanitary sewer line construction: RWSA may require bypass pumping for tie-ins to the
existing system. All doghouse manholes must be pressure -tested before a connection is made to
the system.
7. The location of existing utilities as shown on the plans is from data available at the time of design
and is not necessarily complete or accurate. The Contractor shall be responsible for the
verification of the location, size and depth of all existing utilities, both surface and subsurface.
The Contractor shall immediately notify the Engineer of any discrepancies between the plans and
field conditions. The Contractor shall use due diligence to protect all utilities and structures from
damage at all times, whether shown on the plans or not. Damage to any existing utilities shall be
repaired by the Contractor to the original condition at no additional cost to the Owner.
8. Erosion and sediment control facilities shall not be permitted in the RWSA easement without
special written permission from RWSA. No grading shall be permitted in the RWSA easement
unless permitted otherwise by RWSA in writing.
9. No blasting shall be permitted within 100 feet of RWSA facilities without written permission and
RWSA approval of the blasting plan. Ground monitoring during blasting and a pre -blast survey
may be required. For blasting within 100 feet of any operative RWSA sewerlines, bypass
pumping and/or pre- and post -CCTV may be required. RWSA may also require certification
from a licensed professional engineer stating that the proposed blasting will not damage any
RWSA facilities. Damage to any utilities due to blasting shall be repaired by the Contractor to
the original condition at no additional cost to the Owner.
10. The contractor shall observe minimum separation requirements for utility crossings. When a
crossing is made under an existing facility, adequate structural support shall be provided for the
existing pipe. The area of the crossing shall be backfilled with compacted 57 stone to the
springline of the existing pipe.
11. New water main installations shall be pressure tested, chlorinated, flushed and have water
samples approved prior to making any permanent connection to the public water system.
Approved methods of filling and flushing new water mains will be required to prevent any
contamination of the public water system.
12. All easements for new RWSA facilities shall be recorded prior to placing the new facilities into
service.
13. No permanent structural facilities will be permitted in the RWSA easement. This includes
building overhangs, retaining walls, footers for any structure, drainage structures, etc.
14. Trees are not permitted in the RWSA easement.
From: Deel. lu<tin
To: Ben Holt
Subject: Re: SDP2022-12 River"s Edge - Initial Site Plan
Date: Thursday, March 17, 2022 11:22:00 AM
CAUTION: This message originated outside the County of Albemarle email system. DO
NOT CLICK on links or open attachments unless you are sure the content is safe.
Ben, this proposed development is within the Dam Break Inundation Zone (DBIZ) for Chris
Green Lake Dam, a County owned dam. DCR does not recommend development within the
DBIZ. However, further development would not impact the hazard classification or spillway
capacity requirements for Chris Greene Lake Dam, which is already a high hazard dam and
the spillway requirements are at the maximum.
Justin
Justin Deel, P.E.
Regional Dam Safety Engineer
Department of Conservation & Recreation
804-221-0476
On Tue, Mar 15, 2022 at 2:19 PM Ben Holt <bholl(g4a1bemarle_o4> wrote:
Hi Justin, here is the link to the initial site plan for SDP2022-12 River's Edge.
I've also attached files related to previous approvals, which included a zoning map
amendment to allow multi -family development, a special permit to permit development
within steep slopes and an approval for a central sewage system.
Due date for site plan review comments is 4.12.22. Thank you,
Ben Holt, AICP
Senior Planner
Albemarle County
434-296-5832 ext. 3443
SDP2022-12 Rivers Edge— Initial Site Plan
Comments: Parks & Rec— Tim Paladino
tpadalino@albemarle.ore
04-11-2022
1. ZMA201800018: Please provide a greenway easement (or other similar public access easement) on
the western side of the subject property, in the location(s) shown as "Public Access Pedestrian Path" on
Sheet 11 of the approved ZMA201800018 Application Plan. Please show the easement area on the site
plan (in addition to the separate submission of a plat).
2. ZMA201800018: Please clarify if the "Future Pedestrian Connection" bridge across Flat Branch shown
in ZMA201800018 will be provided (constructed) by owner/developer.
3. Please provide a detail and/or notes for the "New Paved Pathway" that is proposed to "Connect to
Future County Trail Network."
4. Advisory comment / recommendation: To help facilitate the planned future greenway along the North
Fork Rivanna River, please consider voluntarily providing an additional small greenway easement (or
other similar public access easement) on the northwestern side of the subject property, over the
riparian slopes that are located between US-29 and the existing structure to be preserved (2256 Rivers
Edge Lane). That additional easement area would provide a complete connection across the subject
property, from the "Future Pedestrian Connection" across Flat Branch to the VDOT ROW under the US-
29 bridges; and would help enable the County's future construction of the planned greenway
connections along the North Fork Rivanna River between the UVA North Fork Research Park and
downstream areas.
5. Advisory comment / recommendation: To help support the public's use of the planned future blueway
(water trail) on the North Fork Rivanna River, please consider determining the feasibility of voluntarily
dedicating any additional small greenway easement area(s) in one or more strategic locations along the
subject property's 1.0 miles of frontage on the North Fork Rivanna River. Such additional easement
areas would provide paddlers and other water trail users with formal permission to take a break from
paddling; and would accommodate temporary daytime recreational use of the riverfront (if appropriate
riverfront sites exist, without being incompatible with the planned private uses and improvements of
the subject property).
S't OF ALB
County of Albemarle
i Community Development Department - Planning
April 21, 2022
Justin Shimp
Shimp Engineering
912 East High Street
Charlottesville, VA 22902
Khris Taggart, Planner
ktaggart@albemarle.ora
Telephone: (434) 296-5832 ext. 3278
RE: ARB-2022-21: River's Edge (TMP: 032000000005AO and 032000000005A1)
Dear Mr. Shimp,
At its meeting on Monday, April 18, 2022, the Albemarle County Architectural Review Board unanimously
voted to forward the following recommendations on the above -noted Initial Site Development Plan to the agent
for the Site Review Committee:
• Regarding requirements to satisfy the design guidelines as per § 18-30.6.4c(2), (3) and (5) and
recommended conditions of initial plan approval:
o Prior to Initial Plan approval the following items shall be resolved to the satisfaction of the ARB:
None. The ARB recommends approval of the Initial Plan without conditions.
• Regarding recommendations on the plan as it relates to the guidelines: None.
• Regarding conditions to be satisfied prior to issuance of a grading permit: None
• Regarding the final site plan submittal:
A Certificate of Appropriateness is required prior to final site plan approval. The following items and all
items on the ARB Final Site Plan Checklist must be addressed:
1. Provide architectural designs with the next submittal.
2. Provide site sections to clarify the visibility of the proposed development from the EC street.
3. Update the plans to include information on accessory structures and equipment.
4. Include the standard mechanical equipment note on the architectural plans.
5. Provide a lighting plan with the next submittal.
6. Provide landscaping that helps integrate the site entrance into the EC, taking into consideration
any future signage that will be needed.
7. Identify trees that are to remain that meet the landscaping requirements for interior roads.
8. Revise the site plan to show large trees, 40' on center and 2'/2" caliper at time of planting, along
the portion of the interior travelway closest to the EC.
9. Revise the site plan to show large trees, 40' on center and 2'/2" caliper at time of planting, along
the portion of the pedestrian pathway closest to the EC.
WWW.ALBEMARLE.ORG
401 McIntire Road, North Wing, I Charlottesville, VA 22902-4579
10. Revise the landscape plan to show all trees at 2'/2" caliper at planting.
11. Revise the landscape plan to increase the variety of trees to a minimum of four species for
increased plant health.
12. Revise the existing conditions sheet to identify the existing wooded areas north and south of
Rivers Edge Lane in the vicinity of the EC. If any of this vegetation is to remain, revise the
appropriate sheets of the site plan to reflect this.
13. Show tree protection fencing on, and coordinated throughout, the grading, landscaping, and
erosion and sediment control plans.
You may submit your application for continued ARB review at your earliest convenience. Application forms,
checklists and schedules are available on-line at https://www.albemarle.org/government/community-
development/apply-for/planning-and-site-development-applications. Please be certain that your ARB submittal
addresses all checklist items and the above -noted comments. If you have any questions concerning any of the
above, please feel free to contact me.
If you have any questions concerning any of the above, please feel free to contact me.
Sincerely, ,
Khris Taggart, Planner
cc: River's Edge Holdings LLC
P.O. Box 6458
Charlottesville, VA 22906
File