HomeMy WebLinkAboutWPO201100071 Correspondence 2012-04-23 NP Engineering
April 23, 2012
County of Albemarle
Department of Community Development
401 McIntire Road
Charlottesville, VA 22901
Re: ESC Plan comments
Restore'n Station (WPO-2011-00071)
Mr. Phil Custer:
I am writing to address the Erosion and Sediment Control Plan comments provided in your letter
dated March 2, 2012 for the Restore'n Station site plan. I have addressed each comment
individually and listed the comment and intended response for clarity.
1. It appears that the ESC Plans were all printed at 30 scale, not 40. If this is correct, please
replace all references to 40 scale with 30 scale.
RESPONSE: The plans are 30 scale and all reference to 40 scale have been removed.
2. On all three phases, please clearly show and label the limits of disturbance boundary.
RESPONSE: The disturbance boundary has been clearly identified.
(Rev. 1)In phases 1 and 2, extend the limits of disturbance around the outlet protection below the sediment
basin. In phase 2, show the limits into the VDOT ROW. In phase 3, show limits of disturbance.
REV 1 RESPONSE: Items above have been addressed in this plan revision.
3. Please show all proposed grading on Phase 2 and Phase 3. It is difficult to evaluate the
adequacy of these phases without proposed contours. Additional comments may be
necessary because the plan was not able to be fully evaluated.
RESPONSE: Phase 2 and 3 grading have been shown as well as the items to be
completed in each phase.
(Rev. 1)In phase 3,please show the proposed grade lines for the fill required to provide the proper cover
over the detention facility and the final proposed grading in the area of the sediment basin after it is
removed. An adequate channel will need to be provided in the area previous disturbed by the sediment
basin.
REV I RESPONSE: Items above have been addressed in this plan revision.
4. Related to the previous comment, the sediment basin and sediment trap should be sized
for the largest watershed each facility will likely experience as the site is filled in. For
instance, the site will likely be tipped towards the sediment basin, since the stormwater
680 IVY FARM DRIVE•CHARLOTTESVILLE,VIRGINIA 22901
•PHONE:(434)531-7387•
Restore'n Station-WPO C.,...,nents-EC Plan (WPO-2011-00071)
Page 2
April 23, 2012
facility is located in the vicinity, so its drainage area will increase as the earthwork
progresses.
RESPONSE: The sediment basin has been designed for a total of 4.68 acres (sum of the
3.83 acres in drainage area I and 0.85 acres in drainage area 2). Revised sediment basin
calculation sheets are attached.
(Rev. 1) The sediment trap drainage area is larger than the watershed shown in the plan. Free Town Lane
does not divert water away from this trap as the map implies.
Since the last submittal, structure 7B was added which indicates a larger watershed to the sediment basin
than designed Please account for this acreage in the calculations.
Also, when the design of the sediment basin was moded, an error was made with regard to the
embankment. According to the calculations, the top of embankment must be 691, but the plan is graded to
show an embankment top of 690. Please correct. An embankment width of at least 6ft is required
REV 1 RESPONSE: Items above have been addressed in this plan revision. The silt trap
near Free Town lane has been moved north. Structure 7B area has been added-
recalculating the area, due to more defined drainage areas, has resulted in the same
area to the sediment basin as 4.68 acres. The drainage map has been modified to show
this. In addition, the sediment basin was modified to show a top of embankment
elevation of 681, and a top width of 6'.
5. Silt fence is frequently proposed perpendicular to contour lines in this plan which is not
allowed per state guidelines. In these instances,water will not travel through the fence
but will be redirected downhill, like a diversion. Please replace the silt fence on the east
side of the property line with a diversion from the northeast corner to the sediment trap.
On the west end of the property, please simply remove the silt fence. If a visual
boundary is desired by the applicant, I recommend a type of safety fence.
RESPONSE: Revisions to the silt fence have been made as noted above.
(Rev. 1) Comment has been addressed, though the first step in the construction sequence was not modified
accordingly. It seems step 3 can refer to silt fence. Similarly, the construction sequence still refers to
raintanks, which have been eliminated with this application. The contech structures should be installed
after the site has been stabilized, in phase 3.
REV 1 RESPONSE: Items above have been addressed in this plan revision. Raintank
references have been removed. Contech structures (Cistern and System 2) will be
installed in Phase 3.
6. Please remove the silt fence from directly below the outlet of both settling facilities. Silt
fence cannot receive concentrated flow.
RESPONSE: Silt fence has been removed from the plan as noted above.
7. During the review of the preliminary site plan, the Chief of Current Development, Bill Fritz,
approved the disturbance of a 20ft wide section of the undisturbed buffer to the south.
Please show the area of the buffer that was approved for disturbance. It appears that
the area shown on this submittal does match the area approved by Bill. If the area
proposed for disturbance is, in fact, different, another waiver of this disturbance may
need to be processed.
RESPONSE: The undisturbed buffer is shown per prior approval. No revisions are necessary.
(Rev. 1)In this ESC application, the center of the 2011 of allowable disturbed buffer is 99ft from the
680 IVY FARM DRIVE•CHARLOTrESVILLE,VIRGINIA 22901
•PHONE:(434)531-7387•
Restore'n Station-WPO C.,....nents-EC Plan (WPO-2011-00071)
Page 3
April 23, 2012
property corner. In the approved preliminary plan, the center of the 20ft buffer is 74 5ft from the property
corner. The disturbed area of this buffer was moved However, Bill Fritz has determined that this change
does not negatively affect the previous approval and the revised location is acceptable
8. The embankment of the sediment basin ties into existing grade within the undisturbed
buffer (see where the 676 contour line would be). Please modify the plan to make sure
no disturbance to the undisturbed buffer occurs, other than the area previously
authorized.
RESPONSE: The sediment basin has been shifted north to prevent disturbance to the buffer area.
9. In plan view, please draw the sediment basin bottom as 671.
RESPONSE: Sediment basin bottom has been noted as 671 on the plan as noted above.
(Rev. 1) Comment has not been addressed. Please draw the 671 contour line in the sediment basin and
modem the bottom dimensions to meet this contour line. Update the sediment basin bottom dimension
reference in the embankment detail accordingly.
REV 1 RESPONSE: Items above have been addressed in this plan revision. The bottom
elevation is 671. The 671 contour line is shown as well as bottom dimensions.
10. Please show Permanent Seeding (PS) symbols throughout the plan where necessary.
RESPONSE: Permanent seeding symbols have been added to the plan as noted above.
1 1. Please include the county's paved wash rack detail in this sheet set. This detail can be
found in the county's design manual on page 28 of 35.
RESPONSE: Paved wash rack detail has been added to the plan as noted above.
12. The county has updated its standard ESC Note set. Please use the latest version found in
the county's design manual.
RESPONSE: The ESC note set has been updated on the plan as noted above.
13. An analysis of the downstream channel per Minimum Standard 19 was not provided with
the ESC plan. Please refer to page 7 (of 35) of the County's Design Manual and the
Virginia Erosion and Sediment Control Handbook for what the county expects for an
analysis of downstream channels. Per state law, this analysis must be performed using
the 24-hour storm.
RESPONSE: The calculations for the MS-19 are included in the SWM plan and
calculations.
(Rev. 1)Comment has not been addressed. A downstream channel analysis is required in any situation
where the velocity,peak rate, or volume of runoff is increased in a development. Normal detention does
not eliminate the requirement for the applicant to check downstream channels because volume is increased
unless a significant amount of infiltration is provided. If an analysis cannot be performed, the applicant
must proceed as if an inadequate channel is present and provide over-detention meeting State Code
Section 10.1-561.
REV 1 RESPONSE: This item is addressed through the calculations of the SWM plan. It is the
intent to "over-detain" to meet the requirements.
14. Please provide the cross-sections and calculations (2-year velocity and 10-year
capacity) for the new VDOT ditch. Please specify any liner, if necessary.
RESPONSE: North arrows have been added to the site plan.
680 IVY FARM DRIVE•CHARLOTTESVILLE,VIRGINIA 22901
•PHONE:(434)531-7387•
Restore'n Station-WPO C _ ments-EC Plan (WPO-201 1-00071)
Page 4
April 23, 2012
(Rev. 1)Comment has not been addressed. The response to this comment in the applicant's letter refers to
the placement of north arrows on the plan.
REV 1 RESPONSE: Items above have been addressed in this plan revision. Ditch
calculations are included in the plan.
15. To receive a bond estimate, please provide a completed Bond Estimate Request Form to
the County Engineer after all comments have been addressed. All owners of properties
disturbed with this application must sign this document and be party to the bond unless
all offsite easements are recorded. The easements must be written in a manner that
allows the county and its assigns to the construction site.
RESPONSE: The bond estimate request is attached as noted above.
(Rev. 1) WPO bond amounts will be calculated after plan approval.
REV 1 RESPONSE: Ok.
I trust that the above comments are adequately addressed for final site plan and WPO
approval. Should you have questions regarding the revisions, please call me at (434) 531-7387.
Sincerely,
at erkins, P. .
680 IVY FARM DRIVE•CHARLO'iTESVILLE,VIRGINIA 22901
•PHONE:(434)531-7387•
Pipes.txt
BasinFlow printout
INPUT:
Basin:
13 Contour Areas
Elevation(ft) Area(sf) Computed Vol . (cy)
671.60 1513.60 0.0
672.10 942.00 22.5
672.60 743.00 38.1
673.10 619.00 50.7
673.60 540.00 61.4
674.10 495.00 71.0
674.60 481.00 80.0
675.10 495.00 89.1
675.60 540.00 98.6
676.10 619.00 109.4
676.60 743.00 122.0
677.10 942.00 137.5
677.60 1513.60 160.1
5 Storage Pipes
Storage pipe 0
name: one
diameter (in) 72.000
length (ft) 84.000
invert (ft) 671.600
angle 0.000
volume (cy) 87.965
Storage pipe 1
name: two
diameter (in) 72.000
length (ft) 84.000
invert (ft) 671.600
angle 0.000
volume (cy) 87.965
Storage pipe 2
name: three
diameter (in) 72.000
length (ft) 84.000
invert (ft) 671.600
angle 0.000
volume (cy) 87.965
Storage pipe 3
name: four
diameter (in) 72.000
length (ft) 84.000
invert (ft) 671.600
angle 0.000
volume (cy) 87.965
Storage pipe 4
name: five
diameter (in) 72.000
length (ft) 84.000
invert (ft) 671.600
angle 0.000
volume (cy) 87.965
Page 1
Pipes.txt
Start_Elevation(ft) 671.60 Vol . (cy) 0.00
4 Outlet Structures
Outlet structure 0
Orifice
name: lower
area (sf) 0.136
diameter or depth (in) 5.000
width for rect. (in) 0.000
coefficient 0.600
invert (ft) 671.600
multiple 1
discharge into riser
outlet structure 1
Orifice
name: upper
area (sf) 0.196
diameter or depth (in) 6.000
width for rect. (in) 0.000
coefficient 0.600
invert (ft) 674.000
multiple 1
discharge into riser
Outlet structure 2
Culvert
name: name
multiple 1
discharge out of riser
D (in) 15.000
h (in) 0.000
Length (ft) 160.000
Slope 0.050
Manning's n 0.025
Inlet coeff. Ke 0. 500
Equation constant set 0
Invert (ft) 671.600
Outlet structure 3
weir
name: name
length (ft) 1.500
side angle 0.000
coefficient 3.000
invert (ft) 676.600
multiple 1
discharge into riser
4 Inflow Hydrographs
Hydro9raph 0
Modified_Rational
name: post dev captured
C 0.850
Area (acres) 1.750
IDF file: a2
time of concentration (min) 6.00
receding factor 1.670
time increment 3.00
time limit (min) 200.00
fudge factor 1.00
storm: crit. duration (79 iterations)
volume (cy) 306.70
Page 2
Pipes.txt
peak flow (cfs) 2.223
intensity (in/hr) 1.494
time to peak (min) 6.000
duration of peak (min) 54.08
routed true
Hydrograph 1
Modified_Rational
name: post dev captured
C 0.850
Area (acres) 1.750
IDF file: a10
time of concentration (min) 6.00
receding factor 1.670
time increment 5.00
time limit (min) 200.00
fudge factor 1.00
storm: crit. duration (250 iterations)
volume (cy) 339.52
peak flow (cfs) 4.767
intensity (in/hr) 3.205
time to peak (min) 6.000
duration of peak (min) 24.04
routed true
Hydrograph 2
Modified_Rational
name: post dev captured
C 0.850
Area (acres) 1.750
IDF file: a100
time of concentration (min) 6.00
receding factor 1.670
time increment 5.00
time limit (min) 200.00
fudge factor 1.00
storm: crit. duration (125 iterations)
volume (cy) 427.86
peak flow (cfs) 7.118
intensity (in/hr) 4.785
time to peak (min) 6.000
duration of peak (min) 19.04
routed true
Hydrograph 3
SCs
name: name
Area (acres) 2.000
CN 93.000
Type 2
rainfall , P (in) 5.600
time of conc. (hrs) 0.1000
time increment (hrs) 0.0200
time limit (hrs) 30.000
fudge factor 1.00
routed true
peak flow (cfs) 12.151
peak time (hrs) 11.917
volume (cy) 1286.465
OUTPUT:
Routing Method: storage-indication
Page 3
Pipes.txt
Hydrograph 0
Routing summary of Peaks: post dev captured
inflow (cfs) 2.224 at 6.00 (min)
discharge (cfs) 0.924 at 66.00 (min)
water level (ft) 673.790 at 66.00 (min)
storage (cy) 210.391
Hydrograph 1
Routing summary of Peaks: post dev captured
inflow (cfs) 4.771 at 10.00 (min)
discharge (cfs) 1.27 at 35.00 (min)
water level (ft) 674.295 at 35.00 (min)
storage (cy) 266.071
Hydrograph 2
Routing summary of Peaks: post dev captured
inflow (cfs) 7.123 at 10.00 (min)
discharge (cfs) 1.950 at 30.00 (min)
water level (ft) 674.945 at 30.00 (min)
storage (cy) 338.298
Hydrograph 3
Routing summary of Peaks: name
inflow (cfs) 12.094 at 11.92 (hrs)
discharge (cfs) 2.697 at 12.12 (hrs)
water level (ft) 676.203 at 12.12 (hrs)
storage (cy) 473.932
Fri Mar 02 15:41:53 EST 2012
Page 4
raintankl.txt
BasinFlow printout
INPUT:
Basin:
4 Contour Areas
Elevation(ft) Area(sf) Computed vol . (cy)
671.60 3974.00 0.0
672.00 3974.00 58.9
674.00 3974.00 353.2
675.80 3974.00 618.2
Start_Elevation(ft) 671.60 Vol . (cy) 0.00
2 Outlet Structures
Outlet structure 0
Culvert
name: name
multiple 1
discharge through dam
D (in) 6.000
h (in) 0.000
Length (ft) 50.000
Slope 0.010
Manning's n 0.013
Inlet coeff. Ke 0.500
Equation constant set 0
Invert (ft) 672.000
Outlet structure 1
Culvert
name: name
multiple 1
discharge through dam
D (in) 6.000
h (in) 0.000
Length (ft) 50.000
Slope 0.010
Manning's n 0.013
Inlet coeff. Ke 0. 500
Equation constant set 0
Invert (ft) 675.300
3 Inflow Hydrographs
Hydro9raph 0
Modif-ied_Rational
name: post dev captured
C 0.900
Area (acres) 1.490
IDF file: a2
time of concentration (min) 6.00
receding factor 1.670
time increment 1.00
time limit (min) 200.00
fudge factor 1.00
storm: specified duration
volume (cy) 298.78
peak flow (cfs) 1.620
intensity (in/hr) 1.208
time to peak (min) 6.000
duration of peak (min) 75.00
routed true
Page 1
raintankl.txt
Hydrograph 1
Modified_Rational
name: post dev captured
C 0.900
Area (acres) 1.490
IDF file: a10
time of concentration (min) 6.00
receding factor 1.670
time increment 1.00
time limit (min) 200.00
fudge factor 1.00
storm: specified duration
volume (cy) 478.46
peak flow (cfs) 1.905
intensity (in/hr) 1.421
time to peak (min) 6.000
duration of peak (min) 105.00
routed true
Hydrograph 2
Modified_Rational
name: post dev captured
C 0.900
Area (acres) 1.490
IDF file: a100
time of concentration (min) 6.00
receding factor 1.670
time increment 1.00
time limit (min) 300.00
fudge factor 1.00
storm: specified duration
volume (cy) 981.02
peak flow (cfs) 2.287
intensity (in/hr) 1.706
time to peak (min) 6.000
duration of peak (min) 185.00
routed true
OUTPUT:
Routing Method: storage-indication
Hydrograph 0
Routing Summary of Peaks: post dev captured
inflow (cfs) 1.620 at 6.00 (min)
discharge (cfs) 0.749rat 85.00 (min)
water level (ft) 673.110 at 86.00 (min)
storage (cy) 222.244
Hydrograph 1
Routing Summary of Peaks: post dev captured
inflow (cfs) 1.905 at 6.00 (min)
discharge (cfs) 0.977 at 116.00 (min)
water level (ft) 673.833 at 116.00 (min)
storage (cy) 328.667
Hydrograph 2
Routing Summary of Peaks: post dev captured
inflow (cfs) 2.287 at 6.00 (min)
discharge (cfs) 1.516 at 194.00 (min)
water level (ft) 675.462 at 194.00 (min)
storage (cy) 568.450
Page 2
raintankl.txt
Mon Nov 07 17:36:01 EST 2011
Page 3
z R I _ _ .
071. 6
L 170;-JArec.
L 3 W k g6 l 371"(
yea. I
,5 2,515.52 )7pq' 6,y R y 2_
`17 2. 6 1.0 2.0 `t.47 I L-6 67,6 77 3
973.1 1 .6 1 ,6 5,11 110 '56 ' I q't-f `ic ( 1q
972),6 G2D I 5.7 16-.7 gb ' ( i)50 710
L114.1 25 . 3 5.v /1-0-1 �6 I 0 -7760y LOC
0 6 0.0 'goti t(rb l